[Ord. No. 1598, 3-9-2015]
This Ordinance shall be known and may be cited as the "Plymouth Township Stormwater Management Ordinance."
[Ord. No. 1598, 3-9-2015]
Plymouth Township finds that:
A. 
Inadequate management of accelerated runoff of stormwater resulting from development and redevelopment throughout a watershed increases flood flows and velocities, contributes to erosion and sedimentation, overtaxes the carrying capacity of streams and storm sewers, greatly increases the cost of public facilities to convey and manage stormwater, undermines floodplain management and flood reduction efforts in upstream and downstream communities, reduces groundwater recharge and threatens public health and safety.
B. 
Inadequate planning and management of stormwater runoff resulting from land development and redevelopment throughout a watershed can also harm surface water resources by changing the natural hydrologic patterns, accelerating stream flows (which increase scour and erosion of streambeds and stream banks, thereby elevating sedimentation), destroying aquatic habitat, and elevating aquatic pollutant concentrations and loadings such as sediments, nutrients, heavy metals, and pathogens.
C. 
A comprehensive program of stormwater management (SWM), including reasonable regulation of development and activities causing accelerated runoff, is fundamental to the public health, safety, welfare and the protection of the people of the municipality and all the people of the commonwealth, their resources and the environment.
D. 
Stormwater is an important water resource by providing groundwater recharge for water supplies and base flow of streams, which also protects and maintains surface water quality.
E. 
Public education on the control of pollution from stormwater is an essential component in successfully addressing stormwater.
F. 
Federal and state regulations require certain municipalities to implement a program of stormwater controls. These municipalities are required to obtain a permit for stormwater discharges from their separate storm sewer systems under the National Pollutant Discharge Elimination System (NPDES).
G. 
The development of solution cavities in bedrock, and sinkhole development, are coincident with karst terrain.
[Added by Ord. No. 1623, § 1, 8-8-2016]
[Ord. No. 1598, 3-9-2015]
The purpose of this Ordinance is to promote the public health, safety and welfare within Plymouth Township and the Stony Creek/Sawmill Watershed by maintaining the natural hydrologic regime and by minimizing the harms and maximizing the benefits described in Section 102 of this Ordinance, through provisions designed to:
A. 
Meet legal water quality requirements under state law, including regulations at 25 Pa. Code 93 to protect, maintain, reclaim, and restore the existing and designated uses of the waters of this commonwealth.
B. 
Minimize increases in stormwater volume and control peak flows.
C. 
Minimize impervious surfaces.
D. 
Provide review procedures and performance standards for stormwater planning and management.
E. 
Preserve the natural drainage systems as much as possible.
F. 
Manage stormwater impacts close to the runoff source, requiring a minimum of structures and relying on natural processes.
G. 
Focus on infiltration of stormwater to maintain groundwater recharge, to prevent degradation of surface and groundwater quality, and to otherwise protect water resources.
H. 
Preserve and restore the flood-carrying capacity of streams.
I. 
Prevent scour and erosion of stream banks and streambeds.
J. 
Provide standards to meet National Pollution Discharge Elimination System (NPDES) permit requirements.
K. 
Address certain requirements of the municipal separate stormwater sewer system (MS4) NPDES Phase II stormwater regulations.
L. 
Provide for proper operation and maintenance of all stormwater management facilities and best management practices (BMPs) that are implemented in the municipality.
M. 
To minimize the risk of sinkhole occurrence in areas of new development in karst terrain, and on lands adjacent to these developments, also in karst terrain.
[Added by Ord. No. 1623, § 2, 8-8-2016]
N. 
To minimize potential damage to existing or proposed improvements in areas where karst terrain is prevalent.
[Added by Ord. No. 1623, § 2, 8-8-2016]
[Ord. No. 1598, 3-9-2015]
The municipality is empowered to regulate land use activities that affect runoff, surface, and groundwater quality by the authority of:
A. 
Pennsylvania Municipalities Planning Code, Act 247, as amended.[1]
[1]
Editor's Note: See 53 P.S. § 10101 et seq.
B. 
Cite applicable municipal code, First Class Township Code (Act 331 of 1933, P.L. 1206; 53 P.S. § 55101).
[Ord. No. 1598, 3-9-2015]
All regulated activities and all activities that may affect stormwater runoff, including land development and earth disturbance activity, are subject to regulation by this Ordinance.
Regulated activities include, but are not limited to:
1. 
Land development;
2. 
Subdivisions;
3. 
Prohibited or polluted discharges;
4. 
Alteration of the natural hydrologic regime;
5. 
Construction or reconstruction of, or addition of new impervious or semipervious surfaces (i.e., driveways, parking lots, roads, etc.), except for reconstruction of roads where there is no increase in impervious surface;
6. 
Construction of new buildings or additions to existing buildings;
7. 
Redevelopment;
8. 
Diversion piping or encroachments in any natural or man-made channel; and
9. 
Nonstructural and structural stormwater management best management practices (BMPs) or appurtenances thereto.
[Ord. No. 1598, 3-9-2015]
A. 
Regulated activities that create impervious surfaces smaller than or equal to 5,000 square feet do not have to apply the volume control requirements of this Ordinance. Regulated activities of this size are exempt from the peak rate control requirements and the SWM site plan preparation located in Section IV of this Ordinance.[1] If the activity is found to be a significant contributor of pollution to the waters of this commonwealth, or the source of existing stormwater runoff problems, the municipality may enforce any of the above requirements.
Any activity defined under 105.4 and 105.8 shall not be exempt from these design standards.
[1]
Editor's Note: See Art. IV, SWM Site Plan Requirements.
B. 
Agricultural activity is exempt from the peak rate control requirements and SWM site plan preparation requirements of this Ordinance provided the activities are performed according to the requirements of 25 Pa. Code 102.
C. 
Forest management and timber operations are exempt from the peak rate control requirements and SWM site plan preparation requirements of this Ordinance provided the activities are performed according to the requirements of 25 Pa. Code 102.
D. 
Any aspect of BMP maintenance to an existing SWM system made in accordance with plans and specifications approved by Plymouth Township is exempt.
E. 
The use of land for gardening and/or landscaping for home consumption is exempt from the requirements of this ordinance.
F. 
Exemptions from any provisions of this Ordinance shall not relieve the applicant from the requirements in Section 301D through L.
G. 
Additional exemption criteria:
1. 
Exemption responsibilities. An exemption shall not relieve the applicant from implementing such measures as are necessary to protect public health, safety, and property.
2. 
Drainage problems. Where drainage problems are documented or known to exist downstream of or is expected from the proposed activity, the municipality may deny exemptions.
3. 
Exemptions are limited to specific portions of this Ordinance.
[Ord. No. 1598, 3-9-2015]
Any other ordinance or ordinance provision of the municipality inconsistent with any of the provisions of this Ordinance is hereby repealed to the extent of the inconsistency only.
[Ord. No. 1598, 3-9-2015]
Should any section or provision of this Ordinance be declared invalid by a court of competent jurisdiction, such decision shall not affect the validity of any of the remaining provisions of this Ordinance.
[Ord. No. 1598, 3-9-2015]
Approvals issued pursuant to this Ordinance do not relieve the applicant of the responsibility to secure required permits or approvals for activities regulated by any other applicable code, rule, act, or ordinance.