[Adopted 10-5-2005 (Ch. VI, Art. 1, of the 1975 Code)]
No building permit required by the Building Code shall be valid until the building permit fees have been paid.
[1]
Editor's Note: Amended at time of adoption of Code (see Ch. 1, General Provisions, Art. I).
Building permit fees are calculated by the Building Official based on the estimated cost of construction determined in a manner established by the Board of Selectmen multiplied by a rate established by the Board of Selectmen.
Town projects are exempt from permit fees but must have permits as required by the Building Code.
There are no fees charged for certificates of occupancy.