[Ord. No. 1598, 3-9-2015]
A. 
Applicants proposing regulated activities in the Township that do not fall under the exemption criteria shown in Section 106 shall submit a stormwater management (SWM) site plan. The SWM criteria of this Ordinance shall apply to the total proposed development even if development is to take place in stages. Preparation and implementation of an approved SWM site plan is required. No regulated activities shall commence until the municipality issues written approval of a SWM site plan, which demonstrates compliance with the requirements of this Ordinance.
B. 
SWM site plans approved by the municipality, in accordance with Article IV, shall be on site throughout the duration of the regulated activity.
C. 
The municipality may, after consultation with the Department of Environmental Protection (PADEP), approve measures for meeting the state water quality requirements other than those in this Ordinance, provided that they meet the minimum requirements of, and do not conflict with, state law including but not limited to the Clean Streams Law.[1]
[1]
Editor's Note: See 35 P.S. § 691.1 et seq.
D. 
For all regulated earth disturbance activities, erosion and sediment (E&S) control best management practices (BMPs) shall be designed, implemented, operated, and maintained during the regulated earth disturbance activities (e.g., during construction) to meet the purposes and requirements of this Ordinance and to meet all requirements under Title 25 of the Pennsylvania Code and the Clean Streams Law. Various BMPs and their design standards are listed in the Erosion and Sediment Pollution Control Program Manual, No. 363-2134-008 (April 15, 2000), as amended and updated.
E. 
For all regulated activities, implementation of the volume controls in Section 304 of this Ordinance is required.
F. 
Impervious areas:
1. 
The measurement of impervious areas shall include all of the impervious areas in the total proposed development even if development is to take place in stages.
2. 
For development taking place in stages, the entire development plan must be used in determining conformance with this Ordinance.
3. 
For projects that add impervious area to a parcel, the total impervious area on the parcel is subject to the requirements of this Ordinance.
G. 
Stormwater flows onto adjacent property shall not be created, increased, decreased, relocated, or otherwise altered without written notification of the adjacent property owner(s) from the developer. Such stormwater flows shall be subject to the requirements of this Ordinance.
H. 
All regulated activities shall include such measures as necessary to:
1. 
Protect health, safety, and property;
2. 
Meet the water quality goals of this Ordinance by implementing measures to:
a. 
Minimize disturbance to floodplains, wetlands, and wooded areas.
b. 
Create, maintain, repair or extend riparian buffers.
c. 
Avoid erosive flow conditions in natural flow pathways.
d. 
Minimize thermal impacts to waters of this commonwealth.
e. 
Disconnect impervious surfaces (i.e., disconnected impervious areas, DIAs) by directing runoff to pervious areas, wherever possible. See Appendix C for detail on DIAs.[2]
[2]
Editor's Note: Appendix C is included as an attachment to this appendix.
3. 
To the maximum extent practicable, incorporate the techniques for low-impact development practices (e.g., protecting existing trees, reducing area of impervious surface, cluster development, and protecting open space) described in the Pennsylvania Stormwater Best Management Practices Manual, Pennsylvania Department of Environmental Protection (PADEP) No. 363-0300002 (2006). See Ordinance Appendix B for a summary description.[3]
[3]
Editor's Note: Appendix B is included as an attachment to this appendix.
I. 
Infiltration BMPs should be spread out, made as shallow as practicable, and located to maximize the use of natural on-site infiltration features while still meeting the other requirements of this Ordinance.
J. 
The design of all facilities over karst shall include an evaluation of measures to minimize the risk of adverse effects.
K. 
Storage facilities should completely drain both the volume control and rate control capacities over a period of time not less than 24 and not more than 72 hours from the end of the design storm.
L. 
The design storm volumes to be used in the analysis of peak rates of discharge should be obtained from the Precipitation-Frequency Atlas of the United States, Atlas 14, Volume 2, Version 3.0, U.S. Department of Commerce, National Oceanic and Atmospheric Administration (NOAA), National Weather Service, Hydrometeorological Design Studies Center, Silver Spring, Maryland. NOAA's Atlas 14 can be accessed at http://hdsc.nws.noaa.gov/hdsc/pfds/.
M. 
For all regulated activities, SWM BMPs shall be designed, implemented, operated, and maintained to meet the purposes and requirements of this Ordinance and to meet all requirements under Title 25 of the Pennsylvania Code, the Clean Streams Law, and the Storm Water Management Act.[4]
[4]
Editor's Note: See 35 P.S. § 691.1 et seq. and 32 P.S. § 680.1 et seq., respectively.
N. 
Various BMPs and their design standards are listed in the Pennsylvania Stormwater Best Management Practices Manual (PA BMP Manual).
[Ord. No. 1598, 3-9-2015]
Approvals issued and actions taken under this Ordinance do not relieve the applicant of the responsibility to secure required permits or approvals for activities regulated by any other code, law, regulation or ordinance.
[Ord. No. 1598, 3-9-2015]
Within the Sawmill Run Watershed these additive requirements must be applied.
[Ord. No. 1135, § 1, 9-27-1993; Ord. No. 1598, 3-9-2015]
A. 
Mapping of stormwater management districts. In order to implement the provisions of the Stony Creek/Saw Mill Run Stormwater Management Plan, the Township is hereby divided into stormwater management districts consistent with the Stony Creek/Saw Mill Run release rate map presented in the plan. The boundaries of the stormwater management districts are shown on an official map which is available for inspection at the Township office. A copy of the official map at a reduced scale is included in Appendix A of the plan for general reference.[1]
[1]
Editor's Note: Said map is on file in the Township offices.
B. 
Release rate districts. Within a given district, the postdevelopment peak rate of storm runoff must be controlled to the stated percentage of the predevelopment peak rate of storm runoff in order to protect downstream watershed areas. There are numerous release rate districts that differ in the extent to which postdevelopment runoff must be controlled. The release rates range from fifty (50) percent to one hundred (100) percent.
[Ord. No. 1598, 3-9-2015]
A. 
Release rate criteria. Any stormwater management controls required by this ordinance and subject to release rate criteria (50 percent to 100 percent) shall meet the applicable release rate criteria for each of the two-, five-, ten-, 25-, 50- and 100-year return period runoff events consistent with the calculation methodology specified in Section 303.3.
B. 
Location of district boundaries. The exact location of the stormwater management district boundaries as they apply to a given development shall be determined by mapping the boundaries using the two-foot topographic contours provided as part of the drainage plan. The district boundaries, as originally drawn, coincide with topographic divides, or in certain instances are drawn from the intersection of the watercourse and a physical feature such as the confluence with another watercourse or a potential flow obstruction (road, culvert, bridge, etc.) to the topographic divide consistent with topography.
C. 
Criteria for downstream capacity analysis. Any downstream capacity analysis conducted in accordance with this ordinance shall use the following criteria for determining adequacy for accepting peak flow rates:
1. 
Natural or man-made channels or swales must be able to convey the increased runoff associated with a two-year return period event within their banks at velocities consistent with protection of the channels from erosion. Acceptable velocities shall be based upon criteria included in the DEP Soil Erosion and Sedimentation Control Manual (February, 1988).
2. 
Natural or man-made channels or swales must be able to convey the increased 25-year return period runoff peak within their banks or otherwise not create any hazards to persons or property.
3. 
Culverts, bridges, storm sewers or any other facilities that must pass or convey flows from the tributary area must have sufficient capacity to pass or convey the increased flows associated with the 25-year return period runoff event, except for facilities located within a designated floodplain area that must be capable of passing or conveying the 100-year return period runoff. Any facilities that constitute stream enclosures per DEP's Chapter 105 regulations shall be designed to convey the 100-year return period runoff.
D. 
Runoff from site located in single release rate category area. For a proposed development site located within a single release rate category area, the total runoff from the site shall meet the applicable release rate criteria. For development sites with multiple points of concentrated runoff discharge, individual drainage points may be designed for up to a 100 percent release rate, so long as the total runoff from the site is controlled to the applicable release rate.
E. 
Runoff from site located in two or more release rate category areas. For a proposed development site located within two (2) or more release rate category areas, the maximum peak rate of runoff that may be discharged at any point is limited to the predevelopment peak rate of runoff at that point, multiplied by the applicable release rate. The control rates shall apply regardless of any grading modifications that may change the drainage area that discharges at a given point.
F. 
Drainage of sites located partially in release rate category area and partially in no detention area. For proposed development sites located partially within a release rate category area and partially within a provisional no detention area, in no event shall a significant portion of the site area subject to the release rate control be drained to the discharge point(s) located in the no detention area.
G. 
Individual lots within a subdivision. When a site is proposed to be subdivided for the sale and development of lots on an individual basis, either by the subdividing party or other party, the subdividing party shall, as part of the subdivision proposal, show all provisions for stormwater control, in accordance with the requirements of this ordinance.
H. 
Regional or subregional detention alternatives. For certain regions within the watershed, it may be more cost effective to provide one control facility for an entire subarea, group of subareas or portion of a subarea incorporating more than one development site than to provide an individual control facility for each development site. The initiative and funding for any regional or subregional runoff control alternatives are the responsibility of prospective developers. The design of any regional control basins must incorporate reasonable development of the entire upstream watershed. The peak outflow of a regional basin would be determined on a case-by-case basis using the hydrologic model of the watershed consistent with protection of the downstream watershed areas. "Hydrologic model" refers to the calibrated Stony Creek/Saw Mill Run version of the Penn State Runoff Model as developed for the stormwater management plan.
I. 
Capacity improvements. In certain instances, primarily within the provisional no detention and provisional 100 percent release rate category areas, local drainage conditions may dictate more stringent levels of runoff control than those based upon protection of the entire watershed. In these instances, if the developer could prove that it would be feasible to provide capacity improvements to relieve the capacity deficiency in the local drainage network, then the capacity improvements could be provided by the developer in lieu of development controls on the development site. Any capacity improvements would be designed based upon development of all areas tributary to the proposed improvement and the capacity criteria specified in Section 303.2C. In addition, all new development upstream of a proposed capacity improvement shall be assumed to implement the applicable runoff controls consistent with this ordinance, except that all new development within the entire subarea(s) within which the proposed development site is located shall be assumed to implement the developer's proposed discharge control, if any.
Capacity improvements may also be provided as necessary to implement any regional or subregional detention alternatives or to implement a modified "no harm" option which proposes specific capacity improvements to document the validity of a less stringent discharge control that would not create any harm downstream.
J. 
Runoff control based on minimum additional impervious cover waiver. Any proposed regulated activity, except those defined in Sections 105.8 and 105.9, which would create 5,000 square feet or less of additional impervious cover would be exempt from meeting the runoff control provisions of this ordinance. For developments that are to take place in stages, the entire development plan must be used in determining conformance to these criteria. Additional impervious cover shall include, but not be limited to, any roof, parking or driveway areas, and any new streets and sidewalks constructed as a part of or for the proposed development. Any areas that may be designed initially to be semipervious (e.g., gravel, crushed stone, etc.) shall be considered impervious areas for the purposes of waiver evaluations.
No waiver shall be provided for any regulated activities as defined in Sections 105.8 and 105.9.
[Ord. No. 1598, 3-9-2015]
A. 
Methods of calculating runoff. Stormwater runoff from all development sites shall be calculated using either the Rational Method or a soil cover complex methodology.
B. 
Verification of design of detention basin. The design of any detention basin intended to meet the requirements of this ordinance shall be verified by routing the design storm hydrograph through the proposed basin. For basins designed using the modified rational method technique, the detention volume shall, at minimum, equal the volume derived from the approximate routing process as contained in SCS Technical Release Number 55 (TR 55).
C. 
Minimum freeboard. All stormwater detention facilities shall provide a minimum one foot freeboard above the maximum pool elevation associated with the two- through 25-year runoff events. An emergency spillway shall be designed to pass the 100-year runoff event with a minimum one foot freeboard.
D. 
Calculations using Soil Cover Complex Method. All calculations using the Soil Cover Complex Method shall use the Soil Conservation Service Type II 24-hour rainfall distribution. The 24-hour rainfall depths for various return periods to be used consistent with this ordinance are taken from the PennDOT Intensity-Duration-Frequency Field Manual (May 1986) for Region 5, as follows:
Return Period
24-Hour Rainfall Depth
2 year
3.3 inches
5 year
4.2 inches
10 year
5.0 inches
25 year
5.8 inches
50 year
6.4 inches
100 year
7.2 inches
E. 
Calculations using Rational Method. All calculations using the Rational Method shall use rainfall intensities consistent with appropriate times of concentration and return periods and the intensity-duration-frequency curves.
F. 
Runoff curve numbers. Runoff curve numbers (CNs) to be used in the Soil Cover Complex Method shall be based upon the matrix presented in the plan.
G. 
Runoff coefficients. Runoff coefficients for use in the Rational Method shall be based upon the table presented in the plan.
H. 
Manning Equation. The Manning Equation shall be used to calculate the capacity of watercourses. Manning 'n' values used in the calculations shall be consistent with the table presented in the plan. Pipe capacities shall be determined by methods acceptable to the Township Engineer.
I. 
Design of detention basins requiring dam safety permits. Any detention basin intended to meet the requirements of this ordinance which requires a dam safety permit from DEP shall be designed consistent with the provisions of the Dam Safety and Encroachments Act[1] and the DEP Chapter 105 rules and regulations.
[1]
Editor's Note: See 32 P.S. § 693.1 et seq.
J. 
Design criteria: refer to Article V of the Plymouth Township SALDO.[2]
[2]
Editor's Note: See Appendix C, Subdivision and Land Development.
[Ord. No. 1598, 3-9-2015]
Volume controls will mitigate increased runoff impacts, protect stream channel morphology, maintain groundwater recharge, and contribute to water quality improvements. Stormwater runoff volume control methods are based on the net change in runoff volume for the two-year storm event.
Volume controls shall be implemented using the Design Storm Method in Subsection A or the Simplified Method in Subsection B below. For regulated activities equal to or less than one (1) acre, this Ordinance establishes no preference for either methodology; therefore, the applicant may select either methodology on the basis of economic considerations, the intrinsic limitations of the procedures associated with each methodology, and other factors. All regulated activities greater than one (1) acre must use the Design Storm Method.
A. 
Design Storm Method (any regulated activity): This method requires detailed modeling based on site conditions. For modeling assumptions refer to Section 305A.
1. 
Postdevelopment total runoff should not be increased from predevelopment total runoff for all storms equal to or less than the 2-year 24-hour duration precipitation.
2. 
The following applies in order to estimate the increased volume of runoff for the 2-year 24-hour duration precipitation event:
To calculate the runoff volume (cubic feet) for existing site conditions (predevelopment) and for the proposed developed site conditions (postdevelopment), it is recommended to use the Soil Cover Complex Method as shown on the following page. Table B-3 in Ordinance Appendix B[1] is available to guide a qualified professional and/or an applicant to calculate the stormwater runoff volume. The calculated volume shall be either reused, evapotranspired, or infiltrated through structural or nonstructural means.
Soil Cover Complex Method:
Step 1: Runoff (in) = Q = (P - 0.2S) 2/(P + 0.8S) where P = 2-year Rainfall (in)
S = (1000 / CN) - 10, the potential maximum retention (including initial abstraction, Ia)
Step 2: Runoff Volume (Cubic Feet) = Q x Area x 1/12Q = Runoff (in)
Area = SWM Area (sq ft)
[1]
Editor's Note: Appendix B is included as an attachment to this appendix.
B. 
Simplified Method (regulated activities less than or equal to 1 acre):
1. 
Stormwater facilities shall capture the runoff volume from at least the first two inches (2") of runoff from all new impervious surfaces.
Volume (cubic feet) = (2" runoff/12 inches) * impervious surface (sq ft)
2. 
At least the first inch (1") of runoff volume from the new impervious surfaces shall be permanently removed from the runoff flow — i.e., it shall not be released into the surface waters of the commonwealth. The calculated volume shall be either reused, evapotranspired or infiltrated through structural or nonstructural means.
Volume (cubic feet) = (1" runoff/12 inches) * impervious surface (sq ft)
3. 
Infiltration facilities should be designed to accommodate the first half inch (0.5") of the permanently removed runoff.
4. 
No more than one inch (1") of runoff volume from impervious surfaces shall be released from the site. The release time must be over 24 to 72 hours.
C. 
Stormwater control measures. The applicant must demonstrate how the required volume is controlled through stormwater best management practices (BMPs) which shall provide the means necessary to capture, reuse, evaporate, transpire or infiltrate the total runoff volume.
1. 
If natural resources exist on the site and a SWM site plan submission is required for the regulated activity, the applicant shall determine and display the total acreage of protected area where no disturbance is proposed on the plan. The acreage of the protected area should be subtracted from the total site area and not included in the stormwater management site area acreage used in determining the volume controls.
Stormwater Management Site Area = {Total Site Area (for both pre and post development conditions) - Protected Area}
Natural resource areas should be calculated based upon the municipality's own natural resource protection ordinance. If no ordinance exists, see Table B-2 in Ordinance Appendix B[2] for guidance to assess the total protected area. For additional reference see Chapter 5, Section 5.4.1, of the PA BMP Manual.
[2]
Editor's Note: Appendix B is included as an attachment to this appendix.
2. 
Calculate the volume controls provided through nonstructural BMPs. Table B-5 in Ordinance Appendix B is recommended as guidance.[3]
[3]
Editor's Note: Appendix B is included as an attachment to this appendix.
3. 
Volume controls provided through nonstructural BMPs should be subtracted from the required volume to determine the necessary structural BMPs.
Required Volume Control (ft3) - Nonstructural Volume Control (ft3) = Structural Volume Requirement (ft3)
4. 
Calculate the volume controls provided through structural BMPs. Table B-6 in Ordinance Appendix B[4] is recommended as guidance. See PA BMP Manual Chapter 6 for description of the BMPs.
[4]
Editor's Note: Appendix B is included as an attachment to this appendix.
5. 
Infiltration BMPs intended to receive runoff from developed areas shall be selected based on the suitability of soils and site conditions (see Table B-6 in Ordinance Appendix B for a list of infiltration BMPs).[5] Infiltration BMPs shall be constructed on soils that have the following characteristics:
a. 
A minimum soil depth of twenty-four inches (24") between the bottom of the infiltration BMPs and the top of bedrock or seasonally high water table.
b. 
An infiltration rate sufficient to accept the additional stormwater load and dewater completely as determined by field tests. A minimum of 0.2 inches/hour (in/hr) should be utilized and for acceptable rates a safety factor of 50% should be applied for design purposes (e.g., for soil which measured 0.4 in/hr, the BMP design should use 0.2 in/hr to insure safe infiltration rates after construction).
c. 
All open-air infiltration facilities shall be designed to completely infiltrate runoff volume within three (3) days (72 hours) from the start of the design storm.
[5]
Editor's Note: Appendix B is included as an attachment to this appendix.
6. 
Soils. A soils evaluation of the project site shall be required to determine the suitability of infiltration facilities. All regulated activities are required to perform a detailed soils evaluation by a qualified design professional which at a minimum address soil permeability, depth to bedrock, and subgrade stability. The general process for designing the infiltration BMP shall be:
a. 
Analyze hydrologic soil groups as well as natural and man-made features within the site to determine general areas of suitability for infiltration practices. In areas where development on fill material is under consideration, conduct geotechnical investigations of subgrade stability; infiltration may not be ruled out without conducting these tests.
b. 
Provide field tests such as double ring infiltrometer or hydraulic conductivity tests (at the level of the proposed infiltration surface) to determine the appropriate hydraulic conductivity rate. Percolation tests are not recommended for design purposes.
c. 
Design the infiltration structure based on field-determined capacity at the level of the proposed infiltration surface and based on the safety factor of 50%.
d. 
If on-lot infiltration structures are proposed, it must be demonstrated to the municipality that the soils are conducive to infiltrate on the lots identified.
e. 
An impermeable liner will be required in detention basins where the possibility of groundwater contamination exists. A detailed hydrogeologic investigation may be required by the municipality.
[Ord. No. 1598, 3-9-2015]
A. 
The following criteria shall be used for runoff calculations:
1. 
For development sites not considered redevelopment, the ground cover used to determine the existing conditions runoff volume and flow rate shall be as follows:
a. 
Wooded sites shall use a ground cover of "woods in good condition." A site is classified as wooded if a continuous canopy of trees exists over a 1/4 acre.
b. 
The undeveloped portion of the site including agriculture, bare earth, and fallow ground shall be considered as "meadow in good condition," unless the natural ground cover generates a lower curve number (CN) or Rational "c" value (i.e., woods) as listed in Tables B-4 or B-7 in Appendix B of this Ordinance.[1]
[1]
Editor's Note: Appendix B is included as an attachment to this appendix.
2. 
For development and redevelopment sites, the ground cover used to determine the existing conditions runoff volume and flow rate for the developed portion of the site shall be based upon actual land cover conditions. If the developed site contains impervious surfaces, 20 percent of the impervious surface area shall be considered meadow in the model for existing conditions.
B. 
Stormwater runoff peak discharges from all development sites with a drainage area equal to or greater than 200 acres shall be calculated using a generally accepted calculation technique that is based on the NRCS Soil Cover Complex Method. Table 305.1 summarizes acceptable computation methods. The method selected by the design professional shall be based on the individual limitations and suitability of each method for a particular site. The municipality may allow the use of the Rational Method (Q=CIA) to estimate peak discharges from drainage areas that contain less than 200 acres.
Q = Peak flow rate, cubic feet per second (CFS)
C = Runoff coefficient, dependent on land use/cover
I = Design rainfall intensity, inches per hour
A = Drainage Area, acres.
C. 
All calculations consistent with this ordinance using the Soil Cover Complex Method shall use the appropriate design rainfall depths for the various return period storms according to the National Oceanic and Atmospheric Administration (NOAA) Atlas 14 rain data corresponding to the rain gage, seen in Table B-1 in Ordinance Appendix B.[2] The SCS Type II rainfall curve from NOAA is found on Figure B-1 in Ordinance Appendix B. This data may also be directly retrieved from the NOAA Atlas 14 website: hdsc.nws.noaa.gov/hdsc/pfds/orb/pa_pfds.html. If a hydrologic computer model such as PSRM or HEC-1/HEC-HMS is used for stormwater runoff calculations, then the duration of rainfall shall be 24 hours.
Table 305.1
Acceptable Computation Methodologies For Stormwater Management Plans
Method
Method Developed By
Applicability
TR-20 (or commercial computer package based on TR-20)
USDA NRCS
Applicable where use of full hydrology computer model is desirable or necessary.
TR-55 (or commercial computer package based on TR-55)
USDA NRCS
Applicable for land development plans within limitations described in TR-55.
HEC-1/HEC-HMS
US Army Corps of Engineers
Applicable where use of full hydrologic computer model is desirable or necessary.
PSRM
Penn State University
Applicable where use of a hydrologic computer model is desirable or necessary; simpler than TR-20 or HEC-1.
Rational Method (or commercial computer package based on Rational Method)
Emil Kuichling (1889)
For sites less than 200 acres, or as approved by the municipality and/or Municipal Engineer.
Other methods
Varies
Other computation methodologies approved by the municipality and/or Municipal Engineer.
[2]
Editor's Note: Appendix B is included as an attachment to this appendix.
D. 
All calculations using the Rational Method shall use rainfall intensities consistent with appropriate times-of-concentration for overland flow and return periods from NOAA Atlas 14, Volume 2, Version 2.1. Times-of-concentration for overland flow shall be calculated using the methodology presented in Chapter 3 of Urban Hydrology for Small Watersheds, NRCS, TR-55 (as amended or replaced from time to time by NRCS). Times-of-concentration for channel and pipe flow shall be computed using Manning's Equation.
E. 
Runoff curve numbers (CN) for both existing and proposed conditions to be used in the Soil Cover Complex Method shall be based on Table B-4 in Ordinance Appendix B.[3]
[3]
Editor's Note: Appendix B is included as an attachment to this appendix.
F. 
Runoff coefficients (C) for both existing and proposed conditions for use in the Rational Method shall be consistent with Table B-4 in Ordinance Appendix B.
G. 
Runoff from proposed sites graded to the subsoil will not have the same runoff conditions as the site under existing conditions because of soil compaction, even after top-soiling or seeding. The proposed condition "CN" or "C" shall increase by 5% to better reflect proposed soil conditions.
H. 
The Manning Equation is preferred for one-dimensional, gradually varied, open-channel flow. In other cases, appropriate, applicable methods should be applied, however, early coordination with the municipality is necessary.
I. 
Outlet structures for stormwater management facilities shall be designed to meet the performance standards of this Ordinance using the generally accepted hydraulic analysis technique or method of the municipality.
J. 
The design of any stormwater detention facilities intended to meet the performance standards of this Ordinance shall be verified by routing the design storm hydrograph through these facilities using the Storage-Indication Method. For drainage areas greater than 200 acres in size, the design storm hydrograph shall be computed using a calculation method that produces a full hydrograph. The municipality may approve the use of any generally accepted full hydrograph approximation technique that shall use a total runoff volume that is consistent with the volume from a method that produces a full hydrograph.
[Ord. No. 1598, 3-9-2015]
A. 
Hot spots.
1. 
The use of infiltration BMPs is prohibited on hot spot land use areas. Examples of hot spots are listed in Ordinance Appendix D.[1]
[1]
Editor's Note: Appendix D is included as an attachment to this appendix.
2. 
Stormwater runoff from hot spot land uses shall be pretreated. In no case may the same BMP be employed consecutively to meet this requirement. Guidance regarding acceptable methods of pretreatment is located in Appendix D.
B. 
West Nile guidance requirements. All wet basin designs shall incorporate biologic controls consistent with the West Nile Guidance found in Appendix E.[2]
[2]
Editor's Note: Appendix E is included as an attachment to this appendix.