[Ord. 7-98, 9/1/1998, § 501]
1. 
The Township Engineer or his designee shall inspect all phases of development of the site including, but not limited to:
A. 
Completion of preliminary site preparation including stripping of vegetation, stockpiling of topsoil, and construction of temporary stormwater management and erosion control facilities.
B. 
Completion of rough grading, but prior to placing top soil, permanent drainage or other site development improvements and ground covers.
C. 
During construction of the permanent stormwater facilities at such times as specified by the Township Engineer.
D. 
Upon completion of permanent stormwater management facilities, including established ground covers and plantings.
E. 
Upon completion of any final grading, vegetative control measures or other site restoration work done in accordance with the approved plan and permit.
2. 
No work shall begin on a subsequent stage until the preceding stage has been inspected and approved by the Township Engineer.
3. 
It is the responsibility of the permittee to notify the Township Engineer 48 hours in advance of the completion of each identified phase of development.
4. 
Any portion of the work which does not comply with the approved plan must be corrected by the permittee within 72 hours. No work may proceed on any subsequent phase of the stormwater management plan, the subdivision or land development or building construction until the required corrections have been made.
5. 
If at any stage of the work the Township Engineer determines that the soil or other conditions are not as stated or shown in the approved application, he may refuse to approve further work and Richmond Township may revoke existing permits until a revised plan is submitted and approved, as required by § 26-306 of this chapter.
[Ord. 7-98, 9/1/1998, § 502]
Land disturbance permit fees covering costs to Richmond Township for plan reviews, permit issuance and inspections shall be in an amount as established by resolution of the Board of Supervisors. No permit to begin any work on the project shall be issued until the requisite fees have been paid.
[Ord. 7-98, 9/1/1998, § 503]
If it is determined that a modification to the existing stormwater management plan is required under § 26-306 of this chapter, a new land disturbance permit shall not be issued until the additional fees have been paid by the applicant.
[Ord. 7-98, 9/1/1998, § 504]
1. 
The fees payable by an applicant shall at a minimum cover:
A. 
The review of the stormwater management plan.
B. 
The site inspection.
C. 
The inspection of required controls and improvements during construction.
D. 
The final inspection upon completion of the controls and improvements required in the plan.
E. 
Any additional work required to enforce the permit provisions, correct violations and assure the completion of stipulated remedial actions.