A. 
Pursuant to § 62.1-44.15:54 of the Code of Virginia, Mathews County hereby establishes a VESCP program and adopts the regulations promulgated by the Board for the effective control of soil erosion and sediment deposition to prevent the unreasonable degradation of properties, stream channels, waters and other natural resources. In accordance with § 62.1-44.15:52 of the Code of Virginia, any plan approved prior to July 1, 2014, that provides for stormwater management that addresses any flow rate capacity and velocity requirements for natural or man-made channels shall satisfy the flow rate capacity and velocity requirements for natural or man-made channels if the practices are designed to i) detain the water quality volume and to release it over 48 hours; ii) detain and release over a twenty-four-hour period the expected rainfall resulting from the one year, twenty-four-hour storm; and iii) reduce the allowable peak flow rate resulting from the 1.5-, two-, and ten-year, twenty-four-hour storms to a level that is less than or equal to the peak flow rate from the site assuming it was in a good forested condition, achieved through multiplication of the forested peak flow rate by a reduction factor that is equal to the runoff volume from the site when it was in a good forested condition divided by the runoff volume from the site in its proposed condition, and shall be exempt from any flow rate capacity and velocity requirements for natural or man-made channels.
B. 
For plans approved on and after July 1, 2014, the flow rate capacity and velocity requirements for natural and man-made channels shall be satisfied by compliance with water quantity requirements specified in § 62.1-44.15:28 of the Stormwater Management Act and 9VAC25-870-66 of the Virginia Stormwater Management Program (VSMP) Regulations, unless such land-disturbing activities are in accordance with the grandfathering provisions of the Virginia Stormwater Management Program (VSMP) Regulations.
Before adopting or revising regulations, the County shall give due notice and conduct a public hearing on the proposed or revised regulations, except that a public hearing shall not be required when the County is amending its program to conform to revisions in the state program. However, a public hearing shall be held if the County proposes or revises regulations that are more stringent than the minimums of the state program.
Pursuant to § 62.1-44.15:53 of the Code of Virginia, an erosion control plan shall not be approved until it is reviewed by a certified plan reviewer. Inspections of land-disturbing activities shall be conducted by a certified inspector. The Erosion Control Program of the County shall contain a certified program administrator, a certified plan reviewer, and a certified inspector, who may be the same person.
The County hereby designates the Department of Planning and Zoning as the plan approving authority for the Virginia Erosion and Sediment Control Program.
At a minimum, the program and regulations provided for in this chapter shall be made available for public inspection at the office of the Department of Planning and Zoning and the Clerk of the Court. This chapter and related regulatory documents will also be made available at the Mathews County Memorial Library.