The short title by which this chapter shall be known shall be the "Off-Tract Improvement Ordinance of the Borough of Eatontown."
Where the Planning Board determines that off-tract improvements are necessary for the proper development and utilization of the proposed site or subdivision and the surrounding area, it may require either that such off-tract improvements be installed or that the developer contribute to the installation of such off-tract improvements. Where the Planning Board has determined that off-tract improvements are required, it shall be a condition of the granting of final approval that such improvements be constructed or that the developer shall make payments toward the ultimate installation of off-tract gutters, sidewalks, water mains, sanitary sewers, storm sewers, culverts, retention basins, monuments and streetlights, all in accordance with the specifications governing on-tract improvements.
A. 
If the Planning Board determines that the developer may contribute toward required off-tract improvements in lieu of such improvements being installed, the Planning Board shall allocate the cost of said off-tract improvements in accordance with the standards hereinafter set forth. The improvement of a stream and/or the widening of or the construction of drainage or other improvements in a street or road fronting on the tract to be subdivided and/or developed shall not constitute an off-tract improvement, and the cost of said improvement shall not be allocated.
B. 
The allocation of the cost of off-tract improvements shall be determined in accordance with the following:
(1) 
The Planning Board may consider the total cost of the off-tract improvements, the benefits conferred upon the site or subdivision, the needs created by the site or subdivision, population and land use projects for the general areas of the site or subdivision and other areas to be served by the off-tract improvements the estimated times of construction of off-tract improvements and the condition and periods of usefulness, which periods may be based upon the criteria of N.J.S.A. 40:2-22. The Planning Board may further consider the criteria set forth below.
(2) 
Road, curb, gutter and sidewalk improvements may be based upon the anticipated increase of traffic generated by the site or subdivision. In determining such traffic increase, the Planning Board may consider traffic counts, existing and projected traffic patterns, quality of roads and sidewalks in the area and the other factors related to the need created by the site or subdivision and anticipated thereto.
(3) 
Drainage facilities may be based upon the percentage relationship between the site or subdivision acreage and the acreage of the total drainage basins involved or upon calculations developing the percentage contribution that the storm runoff from a particular site or subdivision bears to the total design capacity of any improvement, the particular methods to be selected in each instance by the Borough Engineer.
(4) 
Sewage facilities shall be based upon a proportion as determined by the current rules and regulations of the Eatontown Sewerage Authority.
(5) 
Water supply and distribution facilities may be based upon the current rules and regulations governing the particular utility supplying water service.
C. 
All moneys received by the municipality in accordance with the provisions of this section shall be paid to the Municipal Treasurer, who shall provide for a suitable depository therefor. Such funds shall be used only for the improvements for which they are deposited or improvements serving the same purposes unless such improvements are not initiated for a period of five years from the date of payment, after which time said funds shall be transferred to the capital improvement fund of the municipality.
D. 
The apportionment of costs shall be determined by the Planning Board. The developer shall be afforded an opportunity before said Board to present evidence relative thereto.
Nothing in this section of the chapter shall preclude the municipality from assessing any property benefiting from installation of any off-tract improvements, as provided in this section, pursuant to the provisions of the Revised Statutes of New Jersey, an allowance being made to the respective parcels of realty for payments herein.
Before any developer effectively assigns any of his interest in any preliminary or final approval he must notify the Administrative Secretary and supply detailed information with regard to the name, address, principals, type of organization, competency, experience and past performance of the assignee, transferee or agent. Notice of such assignment or transfer shall be given no later than 10 days after its effective date. The assignee must be made acquainted with all the conditions of approval and the developer shall so certify.
A. 
No contractor, builder, developer or subcontractor shall engage any personnel in any of the work on constructing any improvements unless they are continually supervised by a competent, English-speaking supervisor acceptable to the Borough Engineer.
B. 
No less than five days prior to commencing construction of any improvements on the site, the developer or his agent shall provide the Borough Engineer with the names, addresses, phone numbers and emergency phone numbers of the subdivider and/or a representative empowered to act for the developer and/or each contractor and their supervisor in charge of the construction, setting forth the aspect of construction for which each is responsible.
C. 
The developer may retain throughout the course of construction a registered New Jersey professional engineer to supervise the implementation of the approved subdivision or site design and to make periodic reports to the Borough as well as to the developer regarding conformance of the construction with the requirements of final approval.
D. 
If the developer proposes to retain someone other than the engineer who prepared the final plat to supervise construction, he shall notify the Borough Engineer and the Planning Board of the name, address and license number of the engineer retained. If at any time during the course of construction the developer elects or is required to replace the responsible engineer and/or employ additional engineers, he shall likewise notify the Borough Engineer and the Planning Board.
E. 
The supervising engineer shall immediately notify the Borough Engineer of any deviation, observed or proposed, from the requirements of final approval and/or this chapter.
F. 
At regular intervals during the course of construction, but not less often than at monthly intervals, the supervising engineer shall submit to the Borough Engineer a report listing his observations of the work undertaken during the reporting period, specifically noting any deviation from the requirements of final approval and/or this chapter and listing those improvements expected to be undertaken during the next reporting period. The developer shall accompany any request for acceptance of public improvements and/or release of performance guaranties with a certification by the responsible supervising engineer attesting to the completion of the improvements in full conformance with the requirements of final approval and this chapter and/or specifically noting any deviation there from.