Requests for inspection of sewer service connections to be installed
shall be made 48 hours before the proposed date of installation. Requests
shall be made at the Board of Selectmen's office between the hours of
9:00 a.m. and 4:30 p.m. All connections must be inspected and approved by
the Board of Selectmen or its designated agent before the trench is backfilled.
A. Inspections will be made only during the normal working
hours of the Board of Selectmen or its designated agent.
B. A charge in the amount of the actual cost to the town will be made for any inspections made outside these normal working hours (Subsection
A) and/or for any additional inspections required as a result of faulty workmanship or nonconformance with the requirements contained herein. An additional charge based on actual costs will also be assessed for inspection of leakage tests.