Exciting enhancements are coming soon to eCode360! Learn more 🡪
Town of Belchertown, MA
Hampshire County
By using eCode360 you agree to be legally bound by the Terms of Use. If you do not agree to the Terms of Use, please do not use eCode360.
Table of Contents
Table of Contents
A. 
Pipe and fittings to be used in the work shall be either cement-lined cast or ductile iron, polyvinyl chloride (PVC) or Acrylonitrite-Butadiene-Styrene (ABS) composite or solid wall pipe of approved strength and with approved joints. Pipe shall be a minimum of four inches in diameter for a single-family home and a minimum of six inches in diameter for all other building categories.
B. 
Joints for cement-lined cast iron, PVC or ABS shall conform to the manufacturer's specifications and are subject to approval by the town or its designated agent.
The size, slope, alignment, jointing of pipe, materials of construction, etc., for sewer system extensions, including construction methods, excavation and backfill for sewer system extensions, shall be subject to approval by the Board of Selectmen or its designated agent. Detailed plans and specifications shall be submitted for the town's approval prior to construction. Leakage testing and deflection testing will be performed on all sewer system extensions (as appropriate).
Leakage testing will be performed on all town sewer extensions and may be performed on industrial or commercial connections, depending on waste composition, at the discretion of the Board of Selectmen in accordance with these regulations. Leakage tests shall be made in accordance with the town's standard method for sanitary sewer testing. No building shall be connected to a newly installed sewer until such time as the sewer has been satisfactorily tested. Testing shall be carried out by the contractor for a minimum of four hours under the supervision of the town or its designated agent.
A. 
The maximum acceptable loss, through either infiltration or exfiltration, shall not exceed 200 gallons per mile per 24 hours per inch of diameter of the pipe tested. When two or more pipeline sections are tested at the same time, the allowable loss is for the entire length being tested. Losses through manholes shall be included in determining the loss in a line.
B. 
In case leakage exceeds the above-specified amount, the contractor shall locate the leaks and shall repair them at the owner's expense. Method of repair, if necessary, shall be subject to approval by the town.
C. 
After repairs have been made, the line shall be retested and the process of repairing and retesting shall be repeated until results within the above-specified limits are obtained.
Deflection tests will be performed on all PVC and ABS sewer extensions and may be performed on PVC and ABS building connections at the direction of the Board of Selectmen. The test will consist of a five-percent GO, NO-GO deflection test after the pipe to be tested has been in the ground at least 90 days. The deflection test shall be done with an instrument provided for by the pipe manufacturer, approved by the Board of Selectmen or its authorized agent, and conducted in the presence of the town's authorized agent. Any system which fails the five-percent deflection test may, at the discretion of the Board of Selectmen, be ordered to be excavated, replaced and retested.
A. 
In general, sewer services will not be allowed to have more than two angle points or a total angular deviation of 180°. Cleanouts shall be installed at each deflection.
B. 
All services shall be laid in an envelope of sand or other approved material, depending on soil conditions, with not less than six inches of said material well compacted under and all around the barrel of the pipe.
C. 
All pipe and fittings shall be laid to a minimum slope of 1/4 inch per foot.
D. 
In general, the trenches shall be excavated from the end of the existing sewer service to its point of connection to the building plumbing outlet before backfilling any pipe beyond the sand envelope.
E. 
Services in excess of 100 feet in length are subject to special review by the Board of Selectmen or its authorized representative and such other requirements as may be found necessary to assure a functional connection.
F. 
In new construction, and where practicable in existing building when the common sewer is sufficiently deep, service shall be laid directly, without deflections from the house plumbing vent stack to the connection provided at the public sewer.
G. 
Tunneling will not be allowed unless special permission for the same is given.
H. 
Connection made to the building plumbing system shall be upstream of any septic tanks or cesspools.
I. 
Upon connection to the sanitary sewer, any septic tanks, cesspools or similar private septic disposal facilities shall be demolished or abandoned and filled with suitable material by the drainlayer.
J. 
Pipe and fittings shall not be backfilled beyond the sand envelope until the work is inspected and approved by the Board of Selectmen or its designated agent.
K. 
The licensed drainlayer shall be responsible for all defects in materials and workmanship for a period of one year following completion of the sewer service installation.
L. 
When ledge is encountered in the excavations, a permit must be obtained from the Fire Chief for the use of explosives.
M. 
All blasting shall be done in accordance with the requirements of the Massachusetts Department of Public Safety and such other requirements as imposed by the Fire Chief. All blasting must be done by a person licensed by the Department of Public Safety for this purpose.