Prior to the granting of final approval, the subdivider shall have installed or shall have furnished adequate bond for the ultimate installation of the improvements set out in this article.
Capped monuments shall be placed at all block corners, lot corners, angle points, points of curves in streets and at intermediate points as shall be required by the Town Council.
All streets shall be paved in accordance with applicable minimum construction standards of the Town. Such construction shall be subject to inspection and approval by the Town Engineer or some other person designated by the Town Council for that purpose. The Town Council may, in its discretion, cause the subdivider to make appropriate changes in street construction prior to approval of the plat.
Curbs, gutters, drainage and drainage structures shall be provided in accordance with applicable minimum construction standards of the Town. Such construction shall be subject to the inspection and approval of the Town Engineer or some other person designated by the Town Council for that purpose. The Town Council may in its discretion cause the subdivider to make appropriate changes in the construction of curbs, gutters, drainage and drainage structures prior to approval of the plat.
Sidewalks shall be constructed along at least one side of every minor street shown on the plat in accordance with applicable minimum construction standards of the Town, and sidewalks shall be constructed along both sides of all arterial and collector streets in accordance with applicable minimum construction standards of the Town; provided, however, that where it is impracticable to construct sidewalks, the Town Council may waive this requirement. Sidewalk construction shall be subject to the inspection and approval of the Engineer or some other person designated by the Town Council for that purpose. The Town Council may in its discretion cause the subdivider to make appropriate changes in sidewalk construction prior to approval of the plat.
Street name signs shall be placed at all street intersections within or abutting the subdivision. Such signs shall be of a type approved by the Town and shall be placed in accordance with the standards of the Town. Traffic-control devices, pedestrian-control devices, signs, lights and flashing lights, which the Town in its discretion deems necessary to carry out the provisions of state law or Town ordinances or to regulate, warn or guide vehicular, bicycle and pedestrian traffic, shall be installed in the subdivision at the subdivider's expense and placed in accordance with the dictates and requirements of the Town Council.
Streetlighting facilities and equipment must be approved by the Town Engineer or some other person designated by the Town Council for that purpose. The Town Council may in its discretion cause the subdivider to make appropriate changes in streetlighting facilities and equipment prior to approval of the plat.
Each lot within the subdivision area shall be provided with a connection to the public water supply system. All water systems, equipment and connections shall be subject to the inspection and approval of the Town Engineer or some other person designated by the Town Council for that purpose and shall be in accordance with the minimum construction standards of the Town. The Town Council may, in its discretion, cause the subdivider to make appropriate changes in the construction of water systems, equipment and connections prior to approval of the plat. No person other than the Town Water Commissioner shall disturb, tamper with or make hookups or connections to Town water lines.
Fire hydrants shall be installed in all subdivisions in accordance with the applicable minimum construction standards of the Town. Such construction shall be subject to the inspection and approval of the Town Engineer or by some other person designated by the Town Council for that purpose. The Town Council may in its discretion cause the subdivider to make appropriate changes in such construction prior to the approval of the plat.
Each lot within the subdivided area shall be provided with a connection to the public sanitary sewer. Sanitary sewer systems, equipment and connections shall be constructed and installed in accordance with the Town minimum construction standards. Such construction shall be subject to the approval of the Town Engineer or some other person designated by the Town Council for that purpose. The Town Council may, in its discretion, cause the subdivider to make appropriate changes in the construction of sewer systems prior to approval of the plat. No person other than the Town Water Commissioner shall disturb, tamper with or make hookups or connections to Town sewer lines.
In subdivisions beyond the Town limits where a public water system is not reasonably accessible but where plans for the installation of a public water system in the vicinity of a subdivision have been prepared by the Town Engineer, the subdivider may be required to install water systems in conformity with such plans.
In subdivisions beyond the Town limits where a public water system does not extend to the boundary of the subdivision, the Town Council may require, as a condition to the approval of the plat, that the subdivider pay for all or part of the cost of constructing and installing the necessary extensions, expansions and connections of and to existing public water systems and lines to the boundary of the subdivision. All such extensions, expansions and connections shall be completed in accordance with the Town's minimum construction standards, this chapter and such other specifications as the Town Council shall in its discretion deem necessary.
All such construction shall be subject to the inspection and approval of the Town Engineer or some other person designated by the Town Council for that purpose. No person other than the Town Water Commissioner shall disturb, tamper with or make hookups or connections to existing Town water lines. The Town Council may in its discretion cause the subdivider to make appropriate changes in such construction prior to approval of the plat.
In subdivisions beyond the Town limits where a public sanitary sewer system is not reasonably accessible but where plans for the installation of sanitary sewers in the vicinity of a subdivision have been prepared by the Town Engineer, the subdivider may be required to install sewers in conformity with such plans.
In subdivisions beyond the Town limits where a public sanitary sewer system does not extend to the boundary of the subdivision, the Town Council may require, as a condition to the approval of the plat, that the subdivider pay for all or part of the cost of constructing and installing the necessary extensions, expansions and connections of and to existing public sanitary sewer systems and lines to the boundary of the subdivision. All such extensions, expansions and connections shall be completed in accordance with the Town minimum construction standards, this chapter and such other specifications as the Town Council shall in its discretion deem necessary.
All such construction as is provided for in §§ 400-95 and 400-96 shall be subject to the inspection and approval of the Town Engineer or some other person designated by the Town Council for that purpose. No person other than the Town Water Commissioner shall disturb, tamper with or make hookups or connections to existing Town sewer lines. The Town Council may in its discretion cause the subdivider to make appropriate changes in such construction prior to approval of the plat.
All trench excavation and backfill shall be in accordance with the applicable minimum construction standards of the Town.
All trench excavation and backfill shall be subject to the inspection and approval of the Town Engineer or some other person designated by the Town Council for that purpose. No person shall commence any backfilling without first contacting the Town Engineer or the person designated by the Town Council to inspect trench excavation and backfill and without first receiving permission from the Town representative to commence the specific backfilling requested.
If any person shall backfill in violation of § 400-99, the subdivider shall, upon the request of the Town Engineer or the person designated by the Town Council to inspect trench excavation and backfill, forthwith and at the subdivider's expense remove all such backfill to allow for all necessary inspections by the Town representative.
The Town Council may, in its discretion, cause the subdivider to make appropriate changes in trench excavation and backfill prior to approval of the plat.
All testing of materials and workmanship required by this chapter, the Town minimum construction standards or by the Town Engineer shall be performed by the subdivider and at the expense of the subdivider. If the Town Engineer or a person designated by the Town Council to inspect any phase of construction gives notice to the subdivider that the Town representative desires to be present to observe any testing, the subdivider shall not commence the testing until the Town representative is present. If testing is commenced without or prior to the attendance of the Town representative when such notice has been given, the subdivider shall at the subdivider's expense redo all such tests in the presence of the Town representative.
The Town Engineer or a person designated by the Town Council to inspect any phase of construction may require the subdivider to certify that each required test was performed and that the same was done in accordance with this chapter, the Town minimum construction standards and as specified by the Town Engineer. The certificate may be required either in lieu of or in addition to the attendance of a Town representative as provided in § 400-102.
If the Town Council is not satisfied with the testing of materials and workmanship performed by the subdivider, or if the Town Council believes that additional testing is necessary, the Town Council may in its discretion cause the subdivider, at the subdivider's expense, to redo tests or perform additional tests prior to approval of the plat.
All of the Town minimum construction standards then in effect shall be obligatory and applicable to subdivisions whether or not any particular minimum construction standard is mentioned in this chapter. This chapter is in addition to, and does not repeal, Town ordinances relating to building permits and occupancy permits.
[Amended 1980 by Ord. No. 57C]
The Town shall assign an inspector to inspect materials and workmanship at construction sites, on a part-time or full-time basis, and the expense of such a Town inspector shall be borne by the subdivider. Payment of the inspection fees shall be an absolute condition precedent to approval of the subdivision.
[Amended 1980 by Ord. No. 57C]
A. 
Connections to the public water supply system, connections to the public sanitary sewer system, and all trench excavation and backfill, during frozen ground conditions, are prohibited. The Town Engineer shall have the authority to determine that frozen ground conditions exist. Once the Town Engineer has determined that frozen ground conditions exist, notice of that fact shall be posted at the Town Hall.
B. 
Frozen ground conditions shall, after the determination mentioned in Subsection A of this section, be in effect until the Town Engineer determines that frozen ground conditions no longer exist and that fact is posted at the Town Hall. Nothing contained in this section shall prohibit emergency repairs to water or sewer lines made with the consent of the Town.
C. 
Any person making connections to the public water supply system, connections to the public sanitary sewer system, or performing any trench excavation or backfill, during frozen ground conditions, is guilty of a misdemeanor and, upon conviction thereof, shall be fined up to $200 or imprisoned in jail for up to 90 days. In addition thereto, such violation shall be considered sufficient grounds for the revocation of the applicable building permit, temporary occupancy permit and/or occupancy permit.