No person shall be permitted to connect or cause to be connected any service pipe for conveying water from any of the main or distributing pipes to any house, building, or factory, for any purposes whatsoever, without the written permission of the Water Commission or its designee. Nor shall any addition to, or alteration of, any water pipe be made without such written permission. A connection fee will be charged.
B. 
Water connection and related fee as of April 2006 = $2,000 per unit. No service connection will be made until the applicant has paid the required connection fee.
A. 
Connection requirements: domestic service (one inch).
(1) 
All applicable forms must be filled out by the property owner and/or contractor and returned to the Department of Public Works before any work or inspection will be allowed.
(2) 
The applicant shall arrange with a private contractor to complete all excavation (minimum five-foot depth), tap the street main (road opening permit will be required), installation of tapping strap (saddle), corporation stop, tubing, curb stop, curb box to and through the basement of the building.
(3) 
The applicant shall bear all costs for labor and materials not specifically provided by the Department.
(4) 
The Water Department will provide the water meter and associated materials, installation of the water meter and inspection of all work prior to backfilling the trench.
(5) 
Backfill material will be approved by the Water Department.
(6) 
All work must be guaranteed for a minimum of one year after completion.
(7) 
Replacement of pavement shall be done with bituminous blacktop or with matching material approved by the DPW Superintendent or his/her designee.
(8) 
Any damage to the drains or other Town property shall be the responsibility of the property owner.
(9) 
All water lines must be a minimum of 10 feet apart from a sewer main and 20 feet from a septic system.
(10) 
Any contractor working on Town of Barre property is required to have a minimum of $500,000 in general liability insurance. This must include comprehensive premises-operations, underground and completed operation hazard. A certificate of insurance must be on file with the Water Department.
(11) 
If digging on Town of Barre property, the contractor is required to contract Dig Safe and file such findings (with Dig Safe number) to the Water Department prior to excavation.
(12) 
All plumbing must be done in accordance with the State of Massachusetts Plumbing Codes.
B. 
Connection requirements: commercial and industrial service (one inch or larger).
(1) 
Services larger than one inch will be handled on an individual basis.
(2) 
Any contractor working on Town of Barre property is required to have a minimum of $500,000 in general liability insurance. This must include comprehensive premises-operations, underground and completed operation hazard. A certificate of insurance must be on file with the Water Department.
The permit is valid for one year from date of issuance (copy of Chapter 165, Section 1C, attached).[1]
[1]
Editor's Note: Said Ch. 165, Section 1C, is on file in the Town offices.
A. 
A one-inch connection fee will be charged.
B. 
The applicant shall arrange with a private contractor to:
(1) 
Complete all excavation (minimum five-foot depth).
(2) 
Tap the street main (road opening permit will be required).
(3) 
Install tapping strap (saddle), corporation stop, tubing, curb stop, curb box to and through the basement of the building.
(4) 
Any and/or all other requirements set forth by the Department.
(5) 
The applicant shall bear all costs for labor and materials not specifically provided by the Department.
C. 
The Water Department will provide the following:
(1) 
Water meter and associated materials.
(2) 
Installation of the water meter.
(3) 
Inspection of all completed work before the trench is backfilled.
Services larger than one inch will be handled on an individual basis. A meeting with the Water Commissioners, DPW Superintendent and/or the Chief Operator is required.
A. 
Single-family home.
(1) 
Saddle: double strapped.
(a) 
Body: ductile Iron, meeting ASTM A-536.
(b) 
CC (AWWA).
(c) 
Ten mils of fusion applied nylon.
(d) 
Straps/bolts, washers: stainless steel type 304 (18-8).
(e) 
Gaskets: virgin NBR compounded for water.
(2) 
The following fittings must be McDonald's brass or equivalent (300 psi working):
(a) 
Tapping corporation.
(b) 
Street curb.
(c) 
Inside ball valve.
B. 
Approved materials:
(1) 
All CPPJ connections must have a one-inch stainless steel insert.
(2) 
Service box: Erie style with plug cover and extension rod.
(3) 
Plastic tubing: must be HDPE, 200 psi.
(4) 
Marking tape: must be one foot above pipe.
C. 
Multifamily dwelling: Each unit must have its own connection meeting the requirements.