Final site plan review and approval shall be required of all site plans approved at the preliminary submission stage, in accordance with N.J.S.A. 40:55D-46.1, as amended and/or supplemented from time to time.
Within three years (plus any extensions granted by the Board) the applicant shall submit to the Zoning Official 15 copies of the final plan and application form along with the applicable fees per § 345-24 of this chapter. The submission must also include all details as stipulated in § 345-50 of this chapter, submission of all additional details required at the time of preliminary approval, written proof that all taxes or assessments for local improvements on the premises have been paid and submission of all applicable application and escrow fees. The fees shall be paid in cash or by check payable to the Borough of Stone Harbor. All documents and fees shall be submitted simultaneously.
Within 45 days of receipt of the application package, the Planning or Zoning Board or its authorized committee or designee shall review the application for administrative completeness to verify that all information as required by this chapter is included. If the application is deemed complete, the applicant shall be notified and assigned a hearing date at an upcoming Board meeting. If the application is deemed incomplete, the applicant shall be notified in writing of the deficiencies of the application. The application shall be deemed incomplete if any of the required items noted in § 345-52 are not included. Should the application not be certified complete within 45 days of its receipt, it shall be deemed complete, subject to the exceptions set forth in N.J.S.A. 40:55D-10.3, as amended and/or supplemented from time to time.