Roads shall be laid out and staked by a surveyor or engineer registered in New York State. Grade stakes shall be spaced no more than 50 feet apart and at all changes of line or grade. Each stake shall be clearly marked to show station and final grade. Stakes shall be located away from construction areas and maintained in correct position during construction and until work is approved. A field-adjusted profile shall be run immediately after rough-grading of the road and prior to final forming of the subgrade for approval by the Town Engineer.
A. 
The subdivider shall provide competent personnel to supervise the work necessary to complete the work in accordance with these specifications and standards.
B. 
Upon completion of the work, it shall be required that a licensed engineer or surveyor shall certify to the Town of Somers that roads have been constructed generally in accordance with the approved plans. An as-built improvement plan shall be submitted to the Planning Board prior to acceptance of the roads by the town.
A. 
The Town Engineer, Road Inspector, Superintendent of Highways and members of the Planning Board or Town Board shall have access to all parts of the work area while under construction at all times.
B. 
Certain inspections by the Town Engineer or his authorized representative are mandatory in order to obtain acceptance of the road by the town. The conditions and timing for those inspections are as follows:
(1) 
Prior to the start of work to review the implementation of erosion control measures.
(2) 
Prior to the spreading of Item 4, after shaping of subgrade.
(3) 
During excavation and before construction of embankment or subgrade when soft and unstable material is encountered or when the water table is exposed.
(4) 
When excavations are ready for placing foundations and when pipe trenches are shaped and prepared for laying pipe and/or underground utility lines.
(5) 
Before and after Item 4 base is spread and compacted and before pavement binder course is started. The contractor should secure approval of the Item 4 material in the bank before spreading since unsatisfactory material could result in rejection of the completed base.
(6) 
When placing and rolling of binder and top pavement course is started to determine that the proper crown height has been established and that the surface texture is void of unacceptable depressions and/or high spots. The binder layer must successfully pass through a winter season prior to the installment of the asphalt top.
(7) 
Preacceptance inspection after the basic work is completed may be requested in order to ascertain the conditions and requirements for recommendation for final approval.
(a) 
Following each inspection, written reports will be made by the Town Engineer placing the completed work in one of the following classifications:
[1] 
Work approved and the next operation authorized.
[2] 
Work approved conditionally with requirements for correction defined.
[3] 
Work disapproved with corrective measures defined.
[4] 
Recommendation that cease and desist order be issued.
(b) 
Copies of inspection reports shall be distributed to the Planning Board and the subdivider.