Exciting enhancements are coming soon to eCode360! Learn more 🡪
Township of Washington, NJ
Warren County
By using eCode360 you agree to be legally bound by the Terms of Use. If you do not agree to the Terms of Use, please do not use eCode360.
Table of Contents
Table of Contents
A. 
An informal submission is optional. An informal discussion may be held at a meeting of the approving authority with reference to an informally prepared plat of sufficient accuracy to be used for the purpose of discussion. The purpose of such a discussion will be to review overall development concepts in order to assist the applicant in the preparation of subsequent plans. No decisions will be made and no formal action taken on an informal discussion. Discussion and recommendations shall be informal and shall not be binding on the approving authority. The approving authority shall have the right to limit and control the extent, length and scope of such informal discussion, to regulate when it may occur, to require prior notice of a request for it and to conclude it in the interests of expediting other business or if the matters being presented, in the judgment of the approving authority, should be presented formally.
B. 
The data included on an informal submission of a site plan shall include sufficient basic data to enable the approving authority and the applicant to comment upon design concepts, such as building location, ingress and egress, parking, major natural features that will have to be recognized or may influence certain design criteria and the applicant's basic intent for water, sewerage and storm drainage facilities. Informal submissions should be sketches to scale of possible plan(s) for development. They are not binding on the municipality or upon the developer. Accurate engineered drawings are not necessary.
[Amended 6-10-1987 by Ord. No. 87-10]
A. 
An applicant for subdivision or site plan approval shall, prior to or at the time of filing any application for subdivision or site plan approval, file an application for classification with the Secretary of the Land Use Board. Such application shall be filed at least three weeks prior to the meeting of the municipal agency to which it is submitted. The application for classification shall include all copies of the application and supporting filings required by the checklist.[1]
[Amended 12-28-1989 by Ord. No. 89-15; 3-20-2001 by Ord. No. 01-2]
[1]
Editor's Note: Said checklist is included in Appendix II of this chapter, which is included at the end of this chapter.
B. 
The municipal agency to which the application for classification is submitted shall review the application for its completeness as a submission for classification. If the application is complete, the municipal agency shall classify the development described therein as involving the major or minor subdivision or site plan review procedure under this chapter no later than its first regular meeting following the three-week period if the municipal agency with which the application for classification has been filed would be the proper approving authority under such review procedure. If the application is incomplete or if the nature of the development requested cannot be discerned sufficiently enough from the application to determine the proper review procedure or if another municipal agency would be the proper approving authority under the review procedure involved, then the municipal agency shall reject the application, decline to classify the development and state its reasons for such action. No action on an application for classification shall be construed to be approval of an application for development, nor shall any action on an application for classification be construed as prohibiting later rejection of an application for approval, if subsequently submitted information discloses that the application has been improperly classified.
[Amended 11-8-1978; 6-10-1987 by Ord. No. 87-10]
Approval of a minor subdivision shall be granted by the approving authority as follows:
A. 
The following shall be required prior to approval of a minor subdivision:
(1) 
The applicant shall have submitted at least three weeks prior to the meeting of the approving authority all copies of the application and supporting filings as required by the checklist.[1] Copies of the sketch plat submitted with an application for classification may be counted toward the number of sketch plat copies required for application for minor subdivision.
[Amended 12-28-1989 by Ord. No. 89-15]
[1]
Editor's Note: Said checklist is included in Appendix II of this chapter, which is included at the end of this chapter.
(2) 
The development shall have been classified as a minor subdivision by the approving authority following the submission of a completed application for classification to it. Such classification shall be made by the approving authority at or prior to the time minor subdivision approval is granted.
(3) 
The approving authority shall have determined that the proposed subdivision meets the requirements of this chapter and the definition herein of a minor subdivision.
B. 
The approving authority shall review the submission for minor subdivision approval for its completeness and take action on accepting or rejecting the submission as a complete application for minor subdivision approval following the three-week review period and within 45 days of the submission. Since a complete application for classification is part of the application for minor subdivision approval, no submission shall be deemed complete without a complete application for classification having been submitted to the approving authority. If incomplete, the application shall be rejected, and the approving authority shall state its reason for such rejection. If complete, the approving authority is authorized to waive notice and public hearing on the application for approval and shall approve or deny the application or approve it conditionally on terms ensuring the provision of improvements required by this chapter. Approval as a minor subdivision shall be deemed final approval of the subdivision, provided that the approving authority may condition such approval upon terms ensuring the provision of improvements as stated above.
C. 
Approval of a minor subdivision shall expire 190 days from the date of municipal approval unless, within such period, a plat in conformity with such approval and the provisions of the Map Filing Law[2] or a deed clearly describing the approved minor subdivision is filed by the developer with the county recording officer, the Township Engineer and the Township Tax Assessor. Any such plat or deed accepted for such filing shall have been signed by the Chairman and Secretary of the approving authority or the Vice Chairman or Assistant Secretary in their absence, respectively. All conditions upon which approval is granted shall be adequately noted on the plat or described in the deed prior to signing by such approving authority officials. In reviewing the application for development for a proposed minor subdivision, the approving authority may accept a plat not in conformity with the Map Filing Law, provided that if the developer chooses to file the minor subdivision plat as provided herein rather than record a deed therefor, such plat shall conform with the provisions of said Act.
[2]
Editor's Note: See N.J.S.A. 46:23-9.9 et seq.
D. 
The zoning requirements and general terms and conditions, whether conditional or otherwise, upon which minor subdivision approval was granted shall not be changed for a period of two years after the date of minor subdivision approval, provided that the approved minor subdivision shall have been duly recorded.
[Amended 11-8-1978; 6-11-1980; 6-10-1987 by Ord. No. 87-10]
With respect to all proposed development requiring subdivision (other than minor subdivision) or site plan approval hereunder, the following shall apply:
A. 
Preliminary approval. Preliminary subdivision and/or site plan approval shall be obtained at or prior to the time final subdivision and/or site plan approval is obtained, as follows:
(1) 
The applicant shall, at least three weeks prior to the meeting of the approving authority at which preliminary approval is sought, have submitted to the Secretary all copies of the application and supporting filings as required by the checklist.[1] In addition, if the development is situated within the Carbonate Rock District, described in Chapter 55 of this Code, the applicant shall at the same time make the checklist submissions required by Chapter 55.
[Amended 12-28-1989 by Ord. No. 89-15; 3-18-1997 by Ord. No. 97-4]
[1]
Editor's Note: Said checklist is included in Appendix II of this chapter, which is included at the end of this chapter.
(2) 
The proposed development shall have been classified as the type of development requiring site plan or major subdivision review procedure by the approving authority following the submission of a completed application for classification. Such classification shall have been made at or prior to the time preliminary subdivision or site plan approval is granted.
(3) 
The approving authority shall review the submission for preliminary approval for its completeness and shall take action on accepting or rejecting the submission as a complete application for such approval following the three-week review period and within 45 days of the submission. Since a complete application for classification is part of the application for preliminary approval, no submission shall be deemed complete without a complete application for classification having been submitted to the approving authority. If incomplete, the application shall be rejected, and the approving authority shall state its reason for such rejection, and the approving authority or its Secretary shall notify the developer in writing of the deficiencies in the application within 45 days of the submission of such application, or it shall be deemed to be properly submitted. If accepted as a complete application for preliminary approval, a public hearing date shall be set and notice given as required by this chapter, unless the proposed development involves only a minor site plan, in which case public hearing and notice shall not be required.
(4) 
Upon submission of a preliminary plat and before approval of such plat, the applicant shall submit one copy of the plat and supporting data to the County Land Use Board, and the approving authority Secretary shall submit one copy of such materials to the Township Environmental Commission and any other agency or person as directed by the approving authority for their review and action. Each shall have 30 days from receipt of the plat to report to the approving authority. Any such report shall state the reasons for any unfavorable recommendation. The preliminary approval application shall not be delayed because any agency or person fails to report to the approving authority within the thirty-day period. However, upon mutual agreement between the County Land Use Board and the approving authority, with approval of the applicant, the thirty-day period for a County Land Use Board report may be extended for an additional period of time, and any extension shall so extend the time within which the approving authority is required to act.
(5) 
If the approving authority requires any substantial amendment in the layout of improvements in either a site plan or subdivision proposed by the developer that has been the subject of a hearing, an amended application for development shall be submitted and proceeded upon, as in the case of the original application for development.
(6) 
If the submission to the approving authority is complete, following the required hearing, the approving authority may approve, disapprove or approve with conditions the application for preliminary approval. If the approving authority grants preliminary approval, its Chairman and Secretary (or the Vice Chairman or Assistant Secretary in their absence, respectively) and the Township Engineer shall sign the plat indicating the approval.
B. 
Preliminary approval rights. Preliminary approval shall, except as provided in Subsection B(4) below, confer upon the applicant the following rights for a three-year period from the date of the preliminary approval:
(1) 
That the general terms and conditions on which preliminary approval was granted shall not be changed, including but not limited to use requirements; layout and design standards for streets, curbs and sidewalks; lot size; yard dimensions and off-tract improvements; and any requirements peculiar to site plan approval, except that nothing herein shall be construed to prevent the Township from modifying by ordinance such general terms and conditions of preliminary approval as relate to the public health and safety.
(2) 
That the applicant may submit for final approval on or before the expiration date of preliminary approval the whole or a section or sections of the preliminary plat.
(3) 
That the applicant may apply for and the approving authority may grant extensions on such preliminary approval for additional periods of at least one year but not to exceed a total extension of two years, provided that, if the design standards have been revised by ordinance, such revised standards may govern.
(4) 
In the case of a subdivision of or site plan for an area of 50 acres or more, the approving authority may grant the rights referred to in Subsection B(1), (2) and (3) above for such period of time longer than three years as shall be determined by the approving authority to be reasonable, taking into consideration the number of dwelling units and the nonresidential floor area permissible under preliminary approval, economic conditions and the comprehensiveness of the development. The applicant may thereafter apply for and the approving authority may thereafter grant an extension to preliminary approval for such additional period of time as shall be determined by the approving authority to be reasonable, taking into consideration the number of dwelling units and the nonresidential floor area permissible under preliminary approval and the potential number of dwelling units and the nonresidential floor area of the section or sections awaiting final approval, economic conditions and the comprehensiveness of the development, provided that if the design standards have been revised, such revised standards may govern.
C. 
Final approval. Final subdivision or site plan approval shall not be granted until or after the grant of preliminary approval for a proposed development. Final subdivision and/or site plan approval shall be obtained as follows:
(1) 
The applicant shall, at least three weeks prior to the meeting of the approving authority at which final approval is sought, have submitted to the Secretary thereof all copies of the application and supporting filings as required by the checklists.[2] One Mylar and two cloth prints of any final plat which is to be filed with the county recording officer shall also be submitted at least by the meeting at which final approval is granted.
[Amended 12-28-1989 by Ord. No. 89-15]
[2]
Editor's Note: Said checklists are included in Appendix II of this chapter, which is included at the end of this chapter.
(2) 
As to any utilities proposed or required for the development for which final approval is sought, the final plat shall be accompanied by letters directed to the Chairman of the approving authority and signed by a responsible officer of the water and sewer company or authority and the utility which provides gas, telephone and electricity that has jurisdiction in the area. Such letters shall approve each proposed utility installation design and state who will construct the facility.
(3) 
The final plat shall be accompanied by a statement by the Municipal Engineer that he is in receipt of a map showing all utilities and other improvements (both in the development and off-tract improvements) in exact location and elevation and identifying those portions of any improvements already installed; that he has examined the drainage, erosion, stormwater control and excavation plans and found that the interests of the Township and of nearby properties are fully protected; and that the developer has either installed all improvements in accordance with the requirements of this chapter and the preliminary plat approval and posted a maintenance guaranty with the final plat, or posted a performance guaranty in accordance with this chapter and the preliminary plat approval, for all partially completed improvements or improvements not yet initiated, and posted a maintenance guaranty. Any necessary performance and maintenance guaranty shall be approved by the proper Township officials prior to final approval.
(4) 
The approving authority shall grant final approval if the detailed drawings, specifications and estimates of the application for final approval conform to the standards established by this chapter for final approval, the conditions of preliminary approval and, in the case of a major subdivision, the standards prescribed by the Map Filing Law.[3]
[3]
Editor's Note: See N.J.S.A. 46:23-9.9 et seq.
(5) 
An approved final plat shall be signed by the Chairman and Secretary of the approving authority or the Vice Chairman or Assistant Secretary in their absence, respectively.
D. 
Final approval rights.
(1) 
As provided by N.J.S.A. 40:55D-52, the zoning requirements applicable to the preliminary approval first granted and all other rights conferred upon the developer pursuant to N.J.S.A. 40:55D-37, whether conditionally or otherwise, shall not be changed for a period of two years after the date of final approval, provided that, in the case of a major subdivision, the rights conferred by N.J.S.A. 40:55D-52 shall expire if the plat has not been duly recorded as hereinafter provided. If the developer has followed the standards prescribed for final approval and, in the case of a subdivision, has duly recorded the plat as provided below, the approving authority may extend such period of protection for extensions of one year, but not to exceed three extensions. The granting of final approval terminates the time period of preliminary approval under Subsection B hereof for the section of the development granted final approval.
(2) 
In the case of a conventional subdivision or site plan of 150 acres or more, the approving authority may grant the rights referred to in Subsection D(1) above for such period of time longer than two years as shall be determined by the approving authority to be reasonable, taking into consideration the number of dwelling units and the nonresidential floor area permissible under final approval, the economic conditions and the comprehensiveness of the development. The developer may thereafter apply for and the approving authority may thereafter grant an extension of final approval for such additional period of time as shall be determined by the approving authority to be reasonable, taking into consideration the number of dwelling units and the nonresidential floor area permissible under final approval, the number of dwelling units and the nonresidential floor area remaining to be developed, the economic conditions and the comprehensiveness of the development.
(3) 
Final approval of a major subdivision shall expire 95 days from the date of signing of the plat unless, within such period, the plat shall have been duly filed by the developer with the county recording officer. The approving authority may, for good cause shown, extend the period for recording for an additional period not to exceed 190 days from the date of signing of the plat. No subdivision plat shall be accepted for filing by the county recording officer until it has been approved by the approving authority, as indicated on the instrument by the signature of the Chairman and Secretary of the approving authority, or a certificate has been issued as to the failure of the approving authority to act within the required time. The signatures of the Chairman and Secretary shall not be affixed until the developer has posted the required guaranties.
A. 
Conditional use approval shall be obtained under the provisions of this chapter, particularly the provisions of § 64-16, Conditional uses, and as provided by any rules and regulations adopted by the approving authority which are consistent with this chapter and the Municipal Land Use Law.[1]
[1]
Editor's Note: See N.J.S.A. 40:55D-1 et seq.
B. 
Variances and directions for issuance of a permit for a building or structure in the bed of a mapped street, public drainageway, flood control basin or reserved public area, or not related to a street, shall be obtained under the provisions of this chapter and as provided by any rules and regulations adopted by the approving authority which are consistent with this chapter and the Municipal Land Use Law.
A. 
An approving authority shall grant or deny an application for development of the types referred to below within the number of days specified following the submission to the proper official of the approving authority of a complete application or applications for such development:
[Amended 6-11-1980; 3-20-2001 by Ord. No. 01-2]
(1) 
As to an application for minor subdivision approval: 45 days.
(2) 
As to a preliminary major subdivision application for 10 or fewer lots: 45 days.
(3) 
As to a preliminary major subdivision application for more than 10 lots: 95 days.
(4) 
As to preliminary site plan application for 10 acres of land or less and 10 dwelling units or less: 45 days.
(5) 
As to preliminary site plan application for more than 10 acres of land and more than 10 dwelling units: 95 days.
(6) 
As to an application for final major subdivision or final site plan approval: 45 days.
(7) 
As to application for a conditional use permit: 95 days.
(8) 
As to combined applications:
(a) 
For a conditional use permit and site plan approval: 95 days.
(b) 
For subdivision approval and/or conditional use permit and/or site plan approval: the longest period of time for action by the Land Use Board, whether it be for subdivision, conditional use or site plan approval.
(c) 
For subdivision, site plan or conditional use approval and zoning variances or direction pursuant to N.J.S.A. 40:55D-60b or 55D-60c: 95 days.
(9) 
As to an appeal from the decision of an administrative officer, an application for subdivision, site plan, conditional use permit or variance or for direction pursuant to N.J.S.A. 40:55D-76a, or a combination of these: 120 days.
B. 
Notwithstanding the foregoing, the applicant may consent to further time within which decision on an application may be rendered, in which case, decision on the application shall be rendered within such additional time. Furthermore, conditional approval may be given an application pursuant to the provisions of § 64-9, Conditional approval.
C. 
Failure of the approving authority to act within the time period prescribed above, including further time consented to by the applicant, shall:
(1) 
In the case of subdivision or conditional use application, constitute subdivision approval of the sort applied for or conditional use approval, as the case may be; and, in the case of a minor subdivision, final major subdivision or conditional use application, a certificate of the Secretary of the approving authority as to the failure of the approving authority to act shall be sufficient in lieu of the written endorsement or other evidence of approval required by the Municipal Land Use Law[1] and shall be so accepted by the county recording officer for purposes of filing subdivision plats.
[1]
Editor's Note: See N.J.S.A. 40:55D-1 et seq.
(2) 
In the case of applications for variances, appeals from the decision of an administrative officer or requests for direction pursuant to N.J.S.A. 40:55D-60b or 55D-60c or N.J.S.A. 40:55D-76, constitute a decision favorable to the applicant.
[Amended 3-20-2001 by Ord. No. 01-2]
A. 
Plat conformity.
(1) 
No application for subdivision or site plan approval shall be accepted unless submitted in plat form. Those aspects of the preparation of a plat (except a sketch plat submitted for classification only) which involve the practice of land surveying as defined by N.J.S.A. 45:8 shall be performed and certified by a New Jersey licensed land surveyor, and those which involve the design of streets, utilities and other engineering practice as defined by such statute shall be designed and certified by a New Jersey licensed professional engineer.
(2) 
Where a percolation test result is part of the plat requirement, such test shall be made pursuant to state standards by a licensed professional engineer or other person qualified to make such test under state regulations, and the result shall be noted on the plat. Such test shall be made in the probable location of a septic disposal system field on such lot if, under the circumstances, it can reasonably be foreseen at the time where such location would be. Reports shall be furnished to the approving authority indicating the results of each percolation test in minutes per inch, the date of the test, the number of preliminary tests made to determine apparent saturation, the type or types of soil encountered, together with the thickness of each layer to a minimum depth of 10 feet and all other features affecting the design of a future septic disposal system. The approving authority may waive the requirements for such percolation test where the sanitary sewage disposal system of any structure which is or may be erected on said lot having such system would be required to be connected to an approved central system of sanitary sewers or where the new lot of a minor subdivision is not to be used as a building lot.
[Amended 11-8-1978]
B. 
All plats and applications submitted pursuant to this chapter or Chapter 123 of the Township Code of the Township of Washington shall contain such details and conform to the requirements of the checklist or checklists appropriate thereto, as set forth in Appendix II to this chapter.[1]
[Amended 7-13-1984; 4-8-1987 by Ord. No. 87-6; 12-28-1989 by Ord. No. 89-15]
[1]
Editor's Note: Appendix II is included at the end of this chapter.
C. 
Preliminary subdivision plat.
(1) 
The preliminary subdivision plat shall be designed, drawn and signed by a professional person who is duly licensed by the State Board of Professional Engineers and Land Surveyors in accordance with N.J.S.A. 45:8. The preliminary plat and any engineering documents to be submitted may be in tentative form for discussion purposes for preliminary approval.
(2) 
The preliminary plat shall be clearly and legibly drawn at a scale of not less than one inch equals 100 feet and shall be shown or be accompanied by the following information:
(a) 
A key map showing the entire subdivision and its relation to the surrounding areas.
(b) 
The tract name, block and lot number, if available, date, reference meridian, graphic scale and the following names and addresses:
[1] 
The name and address of the record owner or owners.
[2] 
The name and address of the subdivider.
[3] 
The name and address of the person who prepared the map.
(c) 
The acreage of the tract to be subdivided to the nearest tenth of an acre.
(d) 
Sufficient elevations or contours to determine the general slope and natural drainage of the land and the high and low points and to meet any applicable requirements regarding modified lot or tract area calculations for areas with steep slopes and tentative cross sections and center-line profiles for all proposed new streets.
[Amended 4-8-1987 by Ord. No. 87-6]
(e) 
The location of existing and proposed property lines, streets, buildings, watercourses, railroads, bridges, culverts, drainpipes and any natural features such as wooded areas and rock formations.
(f) 
Plans of proposed utility layouts (sewers, storm drains, water, gas and electricity) showing feasible connections to existing or any proposed utility system. When a public sewage disposal system is not available, the developer shall have percolation tests made and shall submit the results with the preliminary plat. Any subdivision or part thereof which does not meet the established requirements of this chapter or other applicable regulations shall not be approved. Any remedy proposed to overcome such a situation shall first be approved by the appropriate local county or state public health agency.
(g) 
A copy of any protective covenants or deed restrictions applying to the land being subdivided shall be submitted with the preliminary plat.
(h) 
The number for each block and lot and, when a Tax Map is adopted, the Tax Map sheet number. Prior to submission of a preliminary plat to the approving authority, the subdivider shall furnish the Township Engineer with two black-and-white prints of the plat, upon which the Engineer will designate the appropriate block and lot numbers.
(i) 
Location of any recorded right-of-way or easement on the subdivision or within 200 feet of its boundaries, with identification of such easement.
(j) 
Location of marshes, ponds, streams and land subject to periodic or occasional flooding or similar conditions on the tract and within 200 feet of its boundaries; and flood hazard areas.
(k) 
All required design data supporting the adequacy of existing and proposed facilities, including a copy of drainage computations, together with a marked-up plan showing the associated and contributing watersheds.
(l) 
A certificate from the Township Tax Collector that all taxes on the involved tract are paid to date.
[Added 7-13-1983]
(3) 
The design of the preliminary plat shall comply with the provisions of this article and shall show the improvements required by Article IV of this chapter, including the following:
(a) 
All streets and turnabouts to be constructed on the tract, including location, proposed street names, widths of rights-of-way, widths of paving, tentative center-line elevations at intersections and other critical points and center-line gradients shown in percent of slope.
(b) 
Lot layout showing the lot lines and dimensions to the nearest foot, the street frontage of each lot in feet and dashed or dotted lines showing the front, side and rear setbacks.
(c) 
Stormwater drainage system plan showing the location of inlets and manholes; invert elevations and gradients; and sizes, types and materials of pipes to be installed.
D. 
Final subdivision plat.
(1) 
The final plat shall be drawn in ink on tracing cloth at a scale of not less than one inch equals 100 feet and in compliance with all the provisions of the Map Filing Law.[2] One copy of the final plat reproduced on Mylar or other drafting film to a scale of one inch equals 200 feet shall be submitted to the Township Engineer.
[2]
Editor's Note: See N.J.S.A. 46:23-9.9 et seq.
(2) 
The final plat shall show or be accompanied by all of the information herein required for a preliminary plat and shall also show or be accompanied by:
(a) 
The date, name and location of the subdivision, name of the owner, graphic scale and reference meridian.
(b) 
Tract boundary lines, right-of-way lines of streets, street names, easements and other rights-of-way, land to be reserved or dedicated to public use and other site lines, with accurate dimensions, bearings or deflections, angles and radii, arcs and central angles of all curves.
(c) 
The purpose of any easement or land reserved or dedicated to public use shall be designated, and the proposed use of sites other than residential shall be noted.
(d) 
Each block shall be numbered, and the lots within each block shall be numbered consecutively beginning with number one.
(e) 
Minimum building setback line on all lots and other sites.
(f) 
Location and description of all monuments.
(g) 
Names of the owners of adjoining unsubdivided lands.
(h) 
Certificates by an engineer or the surveyor as to the accuracy of the details of the plat.
(i) 
Certification that the applicant is the agent or owner of the land or that the owner has given consent under a written agreement.
(j) 
When approval of a plat is required by any body or officer of such a municipality, county or state, such approval shall be certified on the plat.
(k) 
Cross sections and profiles of streets, approved by the Municipal Engineer, shall be required to accompany the final plat.
(l) 
Contours at five-foot intervals for slopes averaging 10% or greater and at two-foot intervals for land of lesser slope.
(m) 
Plans and profiles of storm and sanitary sewers and water mains.
(n) 
Certificates from the Tax Collector that all taxes are paid to date.
(o) 
Any changes or modifications required by the approving authority as a condition to approval of the preliminary plat; and any clarification or correction of the accuracy and description of physical data made possible through the acquisition of additional information.
(p) 
Certification that either the required improvements have been installed or a performance guaranty has been filed, and, if improvements have been installed, certification that the maintenance guaranty required by this chapter has been filed.
E. 
Site plan sketch plat for classification. A site plan sketch plat for classification shall include the same data as required for a preliminary site plan plat, except that the graphic scale shall be of one inch equals 100 feet or less and the plat need not be prepared by or certified by a New Jersey licensed architect or engineer. With the application for classification, there shall be submitted, at least in brief and, where applicable, in scaled sketch form, preliminary information called for in the appropriate preliminary site plan plat.
F. 
Preliminary site plan plat. Every preliminary site plan plat required hereunder shall be prepared and shall contain information in conformity with § 123-25 of the Washington Township Zoning Ordinance (1977).[3] Preliminary plat engineering documents to be submitted may be in tentative form for discussion purposes only for preliminary approval. Submission of the preliminary site plan plat required under this subsection shall be to the Land Use Board. A preliminary site plan plat shall be accompanied by a certificate from the Township Tax Collector that all taxes on the involved tract are paid to date.
[Amended 7-13-1983; 3-20-2001 by Ord. No. 01-2]
[3]
Editor's Note: See Ch. 123, Zoning.
G. 
Final site plan plat.
(1) 
The final site plan plat shall include all data required on the preliminary site plan plat drawn to incorporate all changes required as a condition of preliminary approval and drawn by persons and to specifications as required for a preliminary plat. Legal documentation to support the granting of all easements over adjoining property shall be provided.
(2) 
In addition such plat shall include:
(a) 
Any clarification or correction of the accuracy and description of physical or other data made possible through the acquisition of additional information.
(b) 
Certification by the professional person, licensed in accordance with N.J.S.A. 45:8, who prepared the plat as to the accuracy of its details insofar as they are in the area of his professional competence.
(3) 
Also there shall be submitted a certificate from the Tax Collector that all taxes are paid in full to date.