Exciting enhancements are coming soon to eCode360! Learn more 🡪
Town of New Windsor, MD
Carroll County
By using eCode360 you agree to be legally bound by the Terms of Use. If you do not agree to the Terms of Use, please do not use eCode360.
It shall be the duty of every person owning or constructing any drain, soil pipe, passage or connection between a sewer and any ground, building or establishment served thereby, as well as every person owning or in control or in possession of any such ground, building or establishment, to cause and require such drain, soil pipe, passage or connection to be adequate for its purpose and such that all material entering the same shall at all times pass freely through the same.
A. 
General. The service line from the curbline to the building shall be laid at the expense of the property owner, but shall be subject at all times to the inspection and approval of the Town or its duly authorized representatives who shall have supervision and control over the same.
B. 
Size. Service lines shall be not less than four inches in diameter. Where multiple homes are permitted to be served with a common service line because the sewage facilities are not separated for each home, double homes may be served with a four-inch line, and other multiple home units must be served larger lines as required by the Town.
C. 
Material.
(1) 
Extra-heavy or medium-weight cast-iron pipe. This pipe shall be bell-and-spigot-type pipe with caulked joints packed firmly with oakum or hemp and filled with molten lead not less than three-fourths of an inch deep and extending not less than one-eighth of an inch below rim or hub.
(2) 
Standard-strength vitrified clay pipe. Standard-strength vitrified pipe shall have either joints packed with hemp and poured with hot bituminous compound in one pour or shall have preformed joints as may be approved by the Plumbing Inspector. Vitrified clay pipe shall be used in trenches which provide good support and shall have a minimum cover of two feet.
(3) 
Asbestos-cement nonpressure pipe. Asbestos-cement nonpressure pipe shall conform to the requirements of Federal Specification 1500, having a minimum crushing strength for applied loads of 1,500 pounds per linear foot. Joints shall be made of couplings of the same strength and material as the pipe with the necessary rubber sealing rings or gaskets to provide a watertight connection.
D. 
Slope. Service lines shall be laid on a grade of not less than one-fourth of an inch per foot for four-inch pipes and one-eighth of an inch per foot for six-inch pipes or larger.
E. 
Installation. Service lines must be as direct as possible. Changes in direction must be made with Y's, combination Y-and-eighth bends or half Y's or one-eighth bend. Changes in size where the lateral or house drain is connected to the service line shall be made only with fittings. Ditches shall be promptly backfilled after inspection and approval by the Plumbing Inspector. Care shall be taken to prevent damage to the pipe in backfilling and to secure a well-compacted and firm trench.
On existing construction, as distinguished from new buildings erected after passage of this Part 3, it is permitted to vent, trap and clean out the house drain by providing these services beyond the building and installing them on the service line.
A. 
Vents. A vent shall be placed as close to the house as possible. In case there is an existing septic tank or cesspool, the vent may be placed in a position immediately after these facilities are bypassed. However, subject to the approval of the Plumbing Inspector, the house-trap cleanout opening may be used to serve as a part of the vent. Vent risers shall extend a minimum of 12 inches above the ground surface and shall be capped with a dome or double bend. Vents shall be at least four inches in diameter.
B. 
Cleanouts. Cleanouts shall be spaced a maximum distance of 45 feet apart, except that existing lines need not be disturbed to provide this maximum spacing. The cleanout shall consist of a Y-branch, with an inclined riser reaching above the surface, where it is to be securely capped and provided with a leaded-in ferrule for cleaning purposes.
A. 
Rock. Where rock is encountered, pipes are to be laid on a six-inch deep cushion of earth.
B. 
Shoring. Ditches are to be shored in accordance with the rules and regulations of the Maryland Department of Health and all other state or local regulatory bodies having jurisdiction over this type of work. Ditches which are 30 inches in width and over six feet in depth must be shored. Twenty-inch-wide ditches in excess of 4 1/2 feet in depth must likewise be shored.
C. 
Excavate for bells. The subgrade upon which pipes are laid shall be excavated to receive bells and couplings in order to ensure a uniform and even bearing for the entire length of the barrel of the pipe. The subgrade shall be finished off by hand and evenly tamped and compacted true to the line and grade of the finished pipe.
All pipes are to be backfilled by hand for a distance of six inches over the top of the bell using approved loose soil. The sides of the pipe are to be tamped at the haunches. The hand fill over the pipe is to be compacted thoroughly by tamping with approved tampers. Above the band tamping, the fill must be placed carefully so as not to injure the pipe. Where pipes are laid in drilled holes rather than in dug trenches, fine-stone backfill is to be blown into the holes and securely packed from both ends.
Abandoned cesspools must be left in a safe condition, preferably by filling with compacted material. Where service lines pass over cesspools, they shall be bridged with a full length of cast-iron pipe (not less than 16 feet), consisting of Class 150 AWWA-Specification. The ends of the pipe are to be firmly bedded on both sides of the cesspool to secure firm bearing in order to develop the full flexural strength of the pipe.
Upon completion of each service installation and/or house drain, the Town office is to be notified and an appointment made for inspection. Inspections should be arranged for as soon as the work is completed in order to minimize the chance of cave-ins. Where they do occur, all caved-in material must be removed and required repairs, if any, made to the pipe. All pipes and pipe joints must be visible and accessible to the Plumbing Inspector. If the work is satisfactory, the permit, which must be on hand at the time of the inspection, will be endorsed and returned to the owner.
For new construction, the following regulations shall apply:
A. 
Materials.
(1) 
Soil and waste piping for a drainage system within a building shall be of extra-heavy or medium-weight cast iron galvanized steel or copper tubing (Type L).
(2) 
Drains within buildings, when underground, shall be of cast-iron soil pipe. For buildings four stories in height, the pipe may be of medium weight. For buildings five stories or more in height, the pipe shall be of extra-heavy weight.
(3) 
Fittings on the drainage system shall conform to the type of piping used. Fittings on screwed pipe shall be of the recessed drainage type. Fittings for copper tubing shall be of the drainage type.
(4) 
Calked points for cast iron bell-and-spigot soil pipe shall be firmly packed with oakum or hemp and filled with molten lead not less than three-fourths deep and not more than one-eighth inch below the rim of the hub when firmly caulked.
(5) 
Threaded joints shall be made with a standard tapered pipe thread with pipe joint compound applied to the male thread before assembly.
(6) 
Soldered or sweat joints for tubing shall be made with drainage fittings with male and female fittings cleaned bright. The joints shall be properly fluxed and made with 50-50 grade solder.
B. 
Drainage piping installation.
(1) 
Horizontal drainage piping shall be installed at a uniform slope, but at slopes not less than the following:
(a) 
Horizontal drainage piping of three inches diameter and less shall be installed with a fall of not less than one-fourth-inch per foot.
(b) 
Horizontal piping of larger than three inches diameter shall be installed with a fall of not less one-eighth-inch.
(2) 
Cleanouts.
(a) 
A Y-branch cleanout shall be installed immediately inside or outside the building wall to provide access to the service line on the downstream side of the house trap.
(b) 
A Y-branch cleanout shall be provided at the base of each stack where it empties into an underground line. Where lines run above ground, a cleanout may be placed at the end of the house drain. Where the house drain is more than 45 feet long, an additional Y-branch cleanout shall be provided for each additional forty-five-foot run. All cleanouts shall be of full size pipe and shall be provided with a plug which shall be watertight. All plugs shall be removable for servicing access to the drain line.
(3) 
Backwater valves. Where the lowest drain in a building is six feet or less from the top of the public sewer main, a backwater valve shall be installed on the downstream side of all waste lines or drains which empty into the house drain. The exception to this rule will be where the backwater valve can be placed on a drain line which carries waste from drains on a higher level. Provisions shall be made to service the backwater valve in the future.
(4) 
Fresh air vent. A fresh air vent shall be installed either on the vent fitting of the house trap or on a T-fitting immediately adjacent to the house trap on the upstream side. The vent shall be of cast iron. It shall lead to 12 inches above the surface of the ground and shall be provided with a gooseneck or mushroom-type vent. The vent shall be no less than three inches for four-inch house drains and no less than four inches for five-inch and six-inch drains.
(5) 
Changes in direction.
(a) 
When changing from vertical to horizontal in lines three inches and larger, a short sweep or 90° long-turn drainage elbow may be used.
(b) 
When changing from horizontal to vertical in lines three inches and larger, a quarter-bend or a 90° short-turn drainage elbow may be used.
(c) 
When changing from vertical to horizontal in lines less than three inches, a long sweep or an extra-long-turn drainage elbow must be used.
(d) 
When changing from horizontal to vertical in lines less than three inches, a quarter-bend or a 90° short-turn drainage elbow may be used.
(e) 
For venting in any direction and for any size line, a quarter-bend or a 90° short-turn fitting may be used.
(f) 
When changing direction of horizontal lines, only long-sweep, 1/8 bends or 1/16 bends shall be used.
(g) 
A heel- or side-inlet quarter bend shall not be used as a vent unless the inlet is placed in the vertical position. All side inlets may be used as branch waste connections in any position.
(h) 
Branch lines shall enter a horizontal drainage line by using a wye or combination Y-and-one-eighth-bend fitting.
(i) 
Floor flanges shall be provided for water closets or similar connections.
(j) 
A closet bend or 1/4 bend may be used directly beneath a closet.
C. 
Venting and plumbing fixtures.
(1) 
On all new constructions, plumbing fixtures shall be properly vented in accordance with the following minimum standards. Where deviations are required, they shall be made to conform to the minimum standards of the National Plumbing Code and be subject to the approval of the Plumbing Inspector.
(a) 
Extensions or vent pipes through a roof shall be terminated at least six inches above the roof.
(b) 
Where a roof is to be used for any purpose other than weather protection, the vent extensions shall be run at least five feet above the roof.
(c) 
No vent terminal from a drainage system shall be directly beneath any door or window or other ventilating opening of the building.
(d) 
Traps serving sinks which are part of the equipment of bars, soda fountains and counters need not be vented when the location and construction of such bars, soda fountains and counters are such as to make it impossible to do so. When such conditions exist, such sinks shall discharge into a safe waste receptacle which is properly trapped and vented.
(e) 
Two fixtures set back-to-back within the distance allowed between a trap and its vent may be served with one continuous soil or waste vent pipe, provided that each fixture wastes separately into an approved double fitting having inlet openings at the same level. Fixtures set side-by-side will be treated the same as back-to-back.
(f) 
Trap to vent table.
[1] 
The following table shows the permitted distance from trap to vent. Drain lines between trap and vent shall be limited to one-fourth-inch per foot to give a lower flow rate and reduce the possibility of self-siphoning of the trap.
Fixture Size
(inches)
Distance of Drain Line Between Trap and Vent
(feet)
1 1/4
2 1/2
1 1/2
3 1/2
2
5
3
6
4
10
[2] 
The horizontal drain from a fixture may enter a vertical drain line through a sanitary T or Y-and-one-eighth-bend combination.
(2) 
Sizes and lengths of vents.
(a) 
The following table shows the size vent required for certain fixtures and fixture groups and the maximum developed length of each vent. Twenty percent of the total length of a vent may be installed in a horizontal position. All horizontal vent lines shall have a minimum grade toward the drain line of one-half-inch per foot.
Individual Fixture or Group
Fixture Units
Trap Size
(inches)
Vent Size
(inches)
Vent Length
(feet)
Lavatory
1
1 1/4
1 1/4
30
Bathtub
2
1 1/2
1 1/4
30
Bathtub
3
2
1 1/4
30
Tank closet
4
3
1 1/2
30
Valve closet
8
3
1 1/2
20
Sink, double and single
2
1 1/2
1 1/2
30
Dishwasher
2
1 1/2
1 1/2
30
Sink with disposal
3
1 1/2
1 1/2
30
Shower stall
2
2
1 1/4
30
Urinal
4
2
1 1/2
30
Automatic washer
-
-
1 1/2
30
Closet, lavatory, tub
-
-
2
15
Closet and lavatory
-
-
2
20
Closet, 2 lavatories, tub
-
-
2
15
Sink and dishwasher
-
-
1 1/2
20
Sink, dishwasher, automatic washer
-
-
2
20
Sink and automatic washer
-
-
2
20
Laundry tray
-
-
1 1/2
30
Floor drains
-
-
None
(b) 
Where distance from trap to stack is greater than shown in the table in Subsection C(2)(a) of this section, the fixture shall be back-vented. Where back-venting is required, the vent shall enter stack above overflow of highest fixture on stack.
(c) 
Vent on sink and automatic washer combination may be run 1 1/2 inches if the drain line is increased to two inches.
(d) 
Where more than one bathroom group vent into a common stack, the vent stack shall be a minimum of three-inch-pipe.