[Adopted 5-18-1972; last amended 9-19-2004]
Rules and regulations of the Walpole Board of
Health and Title 5 of the Massachusetts Environmental Code require
that no individual sewage disposal system shall be located, constructed
or installed until a permit for its location, construction or installation
shall have been issued by the approving authority.
Applications for disposal works construction
permits are available in the Board of Health office. A fee is charged
for the issuance of the permit, payable at the time application is
made.
The above rules, regulations and procedure for
septic construction permits were adopted at a regular meeting of the Board of Health on May 18, 1972, and revised as listed
below.
January 18, 1983
|
December 27, 1983
|
February 14, 1989
|
March 15, 1990
|
November 24, 1992
|
December 1, 1994
|
August 15, 1995
|
January 13, 1998
|
September 19, 2004
|