A.
Zoning Administration Officer. The Town Board shall appoint a Zoning Administrative Officer who shall be charged with the administration of this chapter.
B.
Building permits.
(1)
No building or structure shall be excavated for, erected, added to or structurally altered until a permit therefor has been issued by the Zoning Administrative Officer. Except upon a written order of the Board of Appeals, no such zoning permit, nor a certificate of occupancy, shall be issued for any building where said construction, addition or alteration or use thereof would not conform with the provisions of this chapter.
(2)
There shall be submitted with all applications for zoning permits, two copies of a site plan showing the actual dimensions of the lot to be built upon, the actual size and location on the lot of the building and accessory buildings to be erected and such other information as may be necessary to determine and provide for the enforcement of this chapter.
(3)
One copy of such plan shall be returned when approved by the Zoning Administrative Officer together with such zoning permit to the applicant upon payment of a fee as set by the Town Board.
C.
Certificate of occupancy.
(1)
After the effective date of this chapter, no land or building shall be used until a certificate of occupancy shall have been issued by the Zoning Administrative Officer stating that the building or proposed use thereof is valid under the provisions of this chapter.
(2)
All certificates of occupancy shall be applied for coincident with the application for a zoning permit. Said certificate shall be issued within 10 days after the erection or alteration shall have been approved as complying with the provisions of this chapter.
(3)
The Zoning Administrative Officer shall maintain a record of all certificates of occupancy and copies shall be furnished, upon request, to any person having a proprietary or tenancy interest in the building affected.
(4)
Pending the issuance of a regular certificate of occupancy, a temporary certificate of occupancy may be issued for a period not to exceed six months. Temporary certificates of occupancy may be renewed for additional six-month periods; such renewals shall not exceed a total of three in number. Such temporary certificates of occupancy shall only be issued in cases of emergency or hardship and only for the following purposes: temporary use of a building or a mobile dwelling as a dwelling while a permanent dwelling is under construction or alteration or the use of an uncompleted dwelling under construction. A building shall be considered under construction and uncompleted until there is a complete exterior of a story other than a basement.