[Amended at time of adoption of Code (see Ch. 1, General
Provisions, Art. IV)]
Water mains may be extended under the following circumstances:
A. Building must be in the water and/or sewer district
whichever applies.
(1) Property must be in the water and/or sewer district,
whichever applies to the type of main being applied for.
(2) This requirement limits the Town's responsibility
to only that property within the district and is consistent to all
laws, policies and past practices of the Town of Fallsburg.
B. Physical main must be greater than 100 feet from property
line.
(1) Physical existing Town mains must be greater than
100 feet from the property line.
(2) This requirement is consistent to Town laws establishing
accessibility of units; it also eliminates small extensions that are
not cost-prohibitive for property owners to pay.
C. All main extensions must be on Town-owned property.
(1) All proposed main extensions must be on existing Town
land, roads or easements.
(2) This requirement restricts landlocked properties and
keeps future Town-owned mains within accessible rights-of-way. It
avoids land disputes and requires dedication of small easements to
the Town.
D. Main extensions to property, existing at the time
of district formation only. (Subdivision of land does not apply.)
(1) Main extensions to properties existing at the time
of district formation; any subdivision of property does not apply.
(2) Although phrasing of the above requirement may be
incorrect, in general this requirement prevents the Town from paying
for subdivision mains or the distances created by subdivision of land.
(3) Property must be accessible by gravity for sewer and
property must be at proper elevation for water. The above requirement
specifies that property requiring pump stations or booster stations
do not apply.
E. Property must be accessible by gravity sewer to existing
mains.
F. Property must have proper elevation for water.
(1) Property must be accessible by gravity for sewer and
property must be at proper elevation for water. The above requirement
specifies that property requiring pump stations or booster stations
do not apply.
[Amended at time of adoption of Code (see Ch. 1, General
Provisions, Art. IV)]
The Town shall be responsible for paying for
all material for the construction of the mains, including:
[Amended at time of adoption of Code (see Ch. 1, General
Provisions, Art. IV)]
The property owner shall be responsible for
obtaining all permits and approvals, including Department of Environmental
Conservation, Town of Fallsburg, Department of Health, Department
of Transportation. engineering plans, inspection costs, labor for
installation, blasting, insurance, restoration of Town property and
all other costs except actual material costs.
A. Permits: Department of Environmental Conservation;
Department of Health; Town of Fallsburg Department of Transportation;
other.
G. One-hundred-percent restoration (other than material).