A.
The installation of all required improvements in the
land development shall be inspected by the Township Engineer during
the course of installation.
B.
The subdivider shall give the Township Engineer no
less than 48 hours' notice of the commencement of construction of
improvements, such as street paving, curbs, sidewalks, drainage pipes
and structures, sanitary sewer lines and structures, hydrants, street
signs and streetlighting.
C.
To facilitate inspections of improvements by the Township
Engineer, the subdivider shall deliver to the Township Engineer two
sets of as-built plans, consisting of drawings on a maximum twenty-four-by-thirty-six-inch
reproducible sheet at a scale not smaller than 100 feet to an inch.
Transparencies of the original tracing may serve as as-built plans,
provided that alterations and changes made during field construction
are clearly shown thereon.
(1)
As-built plans of waterlines shall show the diameter,
length and type of main; the points of connection with individual
service lines; the depth of the main as measured below the surface
of the street; the size and type of fittings; the size and type of
valves; the size and type of hydrants; the location of the main with
reference to the distance from curblines, expressed in feet measured
to the nearest 1/10 of a foot, in order that the main may be relocated
at a future date a minimum of two distances to each gate valve measured
from the center line of the nearest intersecting street and from a
curbline; and the location of hydrants.
(2)
As-built plans of sanitary sewers shall show the length,
size and type of main, the depth of house laterals and the length
of lateral and deep-cut connections with the height of the same, and
profiles shall be submitted showing the depth of the main. The elevation
of the inverts and the slope of the pipe shall be shown on both said
plans and profiles. The locations of all manholes, measured from the
center line of the nearest intersections and distances between manholes
shall be shown. The plans and/or profiles shall also show the location
of each manhole not in the center line of the street, measured from
the side of the street and from the curbline; the depth of each manhole,
measured to the nearest 1/10 of a foot; and the location of Ys and
house connections from the nearest lowest manhole indicating whether
on the right side or the left side.
(3)
As-built plans of storm sewers and under drains shall
show the same information, where applicable, as as-built plans and
profiles required above for sanitary sewers.
A.
No certificate for the occupancy of any dwelling unit
in a subdivision shall be issued prior to the installation of the
base course of the street or streets and sidewalk and curbs designed
to serve the unit, the installation of the drainage system to ensure
proper drainage of the lot, the installation of water supply and sewage
disposal systems and the installation of all streetlighting designed
to serve the dwelling unit.
B.
Any variation from the requirements of the preceding
subsection must be upon approval of the governing body after favorable
recommendation from the Planning Board, by virtue of reasons of undue
hardship to the subdivider or his grantee brought about by exceptional
and unusual circumstances and where the occupancy shall not be detrimental
to the subdivision plan and to the public interest.
C.
Any change of use or occupancy within Greenwich Township
will void the previously issued certificate of occupancy and require
the issuance of a new one.
[Added 12-28-2000 by Ord. No. 34-2000]