A. 
General description. The following is a list of key considerations governing the subdivision of land.
(1) 
Subdivisions. Subdivisions proposed for the Town of Geneva will be considered either as major or minor subdivisions.
(2) 
Resubdivisions. Any change to an existing plat is considered a "resubdivision" and thus requires approval of the Planning Board and may be deemed by the Planning Board as a major or minor subdivision.
(3) 
Surety. The Planning Board can require that appropriate surety be posted to assure the project is constructed as designed or to assure that conditions of approval are met.
(4) 
Clustering. The Planning Board will consider any proposal for a clustered project, but that Board reserves the right to require clustering to protect environmentally sensitive areas or to preserve open space.
(5) 
Environmental quality review. All proposals require appropriate environmental reviews in accordance with the state environmental quality review procedures.
(6) 
Subdivision phasing. Any development proposed to be constructed in phases must include an overall master site plan for the proposed development. The master site plan shall include a timeline for development of the site. The master site plan shall be subject to the requirements for major or minor subdivision preliminary site plat review, as applicable, and each phase/element shall be subject to the requirements for major or minor subdivision final plat review, as applicable. Additionally, the master site plan and the site plan for each individual phase of the subdivision, shall be subject to all provisions of Chapter 123 of the Code of the Town of Geneva.
[Added 8-9-2011 by L.L. No. 1-2011]
(7) 
All proposals for both major and minor subdivisions shall be subject to review under this chapter and shall further be subject to review as site plans under Chapter 123 of the Code of the Town of Geneva.
[Added 8-9-2011 by L.L. No. 1-2011]
(8) 
For both major and minor subdivisions, the approved, final site plan, whether approval is conditional or otherwise, of the subdivision shall be subject to all provisions of Chapter 123 of the Code of the Town of Geneva.
[Added 8-9-2011 by L.L. No. 1-2011]
(9) 
If the Planning Board has given final subdivision approval to any subdivision prior to the date this subsection takes effect, and if the Planning Board has not also given final site plan approval to such subdivision, and if substantial construction of improvements for the subdivision as a whole (including but not limited to, roads, curbs, drainage systems, water systems, sewer systems and utility installations), if applicable, and substantial construction on one or more lots within the subdivision have not been completed within three years from the date the Planning Board issued its decision granting final subdivision approval, whether approval is conditional or otherwise, then site plan approval and a site plan permit shall be obtained, pursuant to Chapter 123 of the Code of the Town of Geneva, prior to the commencement of any work on the subject property.
[Added 8-9-2011 by L.L. No. 1-2011]
B. 
General procedure. Minor subdivisions of land are considered to be less complex projects and require a one-step process for approval. Major subdivisions are considered complex divisions of land and require a three-step process for approval.
C. 
Subdivisions involving only the moving of a lot line.
[Added 8-13-2013 by L.L. No. 4-2013]
(1) 
The regulations of this chapter setting forth the procedure for approval of major and minor subdivisions shall not apply to any subdivision whose sole purpose is to move a lot line between two adjacent parcels and where:
(a) 
The lot line adjustment will not affect the location of:
[1] 
Curb cuts or access to either parcel;
[2] 
Drainage, drainage channels or drainage ditches; nor
[3] 
Any buildings situate on either parcel; and
(b) 
The proposed subdivision is not subject to any other review under the Town of Geneva Zoning Law (Chapter 165); and
(c) 
Both parcels shown on the proposed subdivision application and all the buildings thereon meet all applicable Town regulations pertaining to lot size, lot coverage, frontage, width, depth, area, setback, use, and number of primary uses; and
(d) 
If applicable, the lot line adjustment will not make either parcel's well or septic system fall out of compliance with the New York State Department of Health regulations pertaining to such systems' distances from parcel boundaries.
(2) 
Any applicant proposing a subdivision whose sole purpose is to move a lot line between two adjacent parcels and wanting to invoke this Subsection C must submit to the Town Code Enforcement Officer the following:
(a) 
A subdivision map sealed and signed by a licensed surveyor reflecting both existing and proposed parcel boundaries, existing buildings and structures, wells for potable water, and septic system locations, if any; and
(b) 
A written purchase contract between the two parcel owners evidencing that the portion of the parcel being subdivided will be conveyed following the filing of the subdivision map.
(3) 
The Code Enforcement Officer shall approve subdivisions involving only the moving of a lot line between two adjacent parcels that are in compliance with this Subsection C by signing the subdivision map(s) for filing with the County Clerk's office.
(4) 
If, within 60 days of the date the Code Enforcement Officer signs the subdivision map, the approved subdivision map is not filed with the County Clerk's office and, within the same sixty-day period, the respective deed between the parcel owners evidencing transfer of title to the land that is the subject of the lot line adjustment is not recorded in the County Clerk's office, the approval of the subdivision pursuant to this Subsection C shall become null and void as though it had never been approved.
(5) 
Any approval by the Code Enforcement Officer under this Subsection C shall contain a condition that the applicant who is acquiring additional land shall, within 60 days of the filing of the subdivision map in the County Clerk's office, combine or merge the existing parcel with the land to be acquired from the adjacent parcel so that there exists only one tax map for the revised parcel to which land is being added.
(6) 
In the event that the Code Enforcement Office does not approve the lot line adjustment pursuant to this Subsection C, the subdivision application must be submitted to the Town of Geneva Planning Board for approval which shall follow the regulations and procedures of this chapter and shall have the option to waive procedures at its discretion.
D. 
Subdivisions creating only one new one-family dwelling lot.
[Added 8-13-2013 by L.L. No. 4-2013]
(1) 
The regulations of this chapter setting forth the procedure for approval of major and minor subdivisions shall not apply to any subdivision whose sole purpose is to create only one new one-family dwelling lot, in addition to the remaining parent parcel, in an A Agriculture District, an R-1 Residence District or an R-2 Residence District and where:
(a) 
The subdivision will not affect the location of:
[1] 
Curb cuts or access to either parcel;
[2] 
Drainage, drainage channels or drainage ditches; or
[3] 
Any buildings situate on either parcel; and
(b) 
The proposed subdivision is not subject to any other review under the Town of Geneva Zoning Law (Chapter 165); and
(c) 
Both parcels shown on the proposed subdivision application and all the buildings thereon meet all applicable Town regulations pertaining to lot size, lot coverage, frontage, width, depth, area, setback, use, and number of primary uses; and
(d) 
If applicable, the subdivision will not make either parcel's well or septic system fall out of compliance with the New York State Department of Health regulations pertaining to such systems' distances from parcel boundaries.
(2) 
Any applicant proposing a subdivision whose sole purpose is create only one new one-family dwelling lot and wanting to invoke this Subsection D must submit to the Town Code Enforcement Officer the following:
(a) 
A subdivision map sealed and signed by a licensed surveyor reflecting both existing and proposed parcel boundaries, existing buildings and structures, wells for potable water, and septic system locations, if any.
(3) 
The Code Enforcement Officer shall approve subdivisions involving the creating of only one new one-family dwelling lot that are in compliance with this Subsection D by signing the subdivision map(s) for filing with the County Clerk's office.
(4) 
If, within 60 days of the date the Code Enforcement Officer signs the subdivision map, the approved subdivision map is not filed with the County Clerk's office, the approval of the subdivision pursuant to this Subsection D shall become null and void as though it had never been approved.
(5) 
In the event that the Code Enforcement Office does not approve the subdivision pursuant to this Subsection D, the subdivision application must be submitted to the Town of Geneva Planning Board for approval which shall follow the regulations and procedures of this chapter and shall have the option to waive procedures at its discretion.
(6) 
The approval process for a subdivision involving the creating of only one new one-family dwelling lot pursuant to this Subsection D can be used only once every three years per parent parcel.
All related application forms are available from the Building Department.
Preapplication conferences with the Chairperson of the Planning Board and/or the Code Enforcement Officer are encouraged and serve the following functions:
A. 
To review application requirements;
B. 
To identify any potential area of environmental concern;
C. 
To discuss preliminary design of the project;
D. 
To set a probable timetable for review; and
E. 
To review town policies concerning development.
A. 
All applications for subdivision approval shall be accompanied by a fee to be established by resolution of the Town Board. This fee shall be used to cover part of the cost of the subdivision review process, including such administrative costs as public hearing notices, inspections, communications, etc.
B. 
Whenever the Code Enforcement Officer, any other officer of the Town of Geneva or any board of the Town of Geneva shall determine that Chapter 136, Subdivision of Land, of the Code of the Town of Geneva shall be required to be complied with and/or enforced, the costs incurred by said officer, by the Town of Geneva Planning Board or by any officer of the Town of Geneva on behalf of the Town for consultation fees with engineers, attorneys or other professionals or costs incurred in enforcing or complying with this Code, including but not limited to the costs of meeting the requirements of Article 6 of the Environmental Conservation Law (SEQRA), shall be reimbursed by the real property owner before a building permit, certificate of occupancy or other permit may be issued. If the real property owner fails to fully reimburse such costs, then said reimbursement costs levied pursuant to this chapter shall constitute a lien and charge on the real property that was the subject of review until paid or otherwise satisfied or discharged; and, if the same are not paid within 30 days after they shall be deemed payable, they shall be collected and enforced in the same manner and at the same time as other Town taxes and charges are permitted to be collected.
[Added 7-12-2001 by L.L. No. 7-2001 amended; 6-11-2013 by L.L. No. 3-2013]
All major subdivision proposals require a public hearing before the Planning Board. Notice will be sent by the Secretary to the Planning Board to all owners of property located within 500 feet of the parcel proposed for subdivision. The public hearing is held to permit the public to learn details of the proposed subdivision. Free and open discussion of the project and its impacts will be encouraged during the hearing.
Plats for proposed subdivisions will be referred to the Planning Board for review and recommendations. The Planning Board will consider the probable environmental impacts of the proposed subdivision. In most cases, the Planning Board will be the lead agency for the purpose of making a significant determination pursuant to SEQR.
All subdivisions are referred to all affected local, state and federal agencies. Every subdivision plat must undergo review by the Engineer for the town who will also ascertain that civil engineering standards are met. All comments received from reviewing agencies shall become a part of the permanent record of the project.
Timetables for decisions shall commence on the date of the first Planning Board meeting subsequent to the filing of a completed application.
The Chairperson of the Planning Board shall, where required by § 239-n of the General Municipal Law, or as may be requested by resolution of the Planning Board, submit the plat to the County Planning Board for review and recommendation. No final decision will be rendered prior to the receipt of such recommendation when the plat is referred pursuant to § 239-n.
If, during the course of review, a plat is determined not to be in compliance with town zoning standards, review of the plat will be tabled and the matter referred to the Zoning Board of Appeals for resolution.
A minor subdivision plat shall be prepared and submitted to the Planning Board for all proposed minor subdivisions. The requirements and procedures of this process are as follows:
A. 
Requirements.
(1) 
Nine copies of the minor subdivision plat, a completed application and a fee shall be submitted to the Chairperson of the Planning Board. Copies will be used for the following purposes:
(a) 
One copy shall be returned to the subdivider with notification of decision.
(b) 
One copy shall be retained by the Planning Board.
(c) 
One copy shall be retained by the Building Department.
(d) 
Six copies shall be used for necessary coordination with and referral to other agencies and consultants.
(2) 
Additional copies may be required to be submitted to the Chairperson of the Planning Board who may determine that other officials, agencies or consultants need to be informed about the project.
(3) 
The minor subdivision plat shall comply with the requirements set forth by the Building Department of the Town of Geneva. This document is available from the Town Clerk of the Town of Geneva.
B. 
Procedures for review and approval.
[Amended 12-23-1997 by L.L. No. 5-1997]
(1) 
Completed application. Upon the receipt of an application for a minor subdivision, the Chairperson of the Planning Board shall review the application submitted to determine whether it is complete in accordance with the standards of this chapter. The Chairperson shall place the matter on the agenda of the next available Planning Board meeting for discussion purposes. The Chairperson also may distribute the plat to affected agencies, including the Engineer for the town and the Building Department, for review and comment.
(2) 
Before the Planning Board takes any other action on an application submitted as a minor subdivision, the Planning Board shall make a determination, based on the factors set forth in the definition of "Subdivision, Minor" in § 136-9 of this chapter, whether the application shall proceed under the process in this chapter for reviewing and approving a minor subdivision or under the process in this chapter for reviewing and approving a major subdivision.
[Added 8-9-2011 by L.L. No. 1-2011[1]]
[1]
Editor's Note: This local law also provided for the renumbering of Subsection B(2) through (7) as B(3) through (8), respectively.
(3) 
A final minor subdivision plat shall not be considered complete until a negative declaration has been filed or until a notice of completion of the draft environmental impact statement has been filed in accordance with the provisions of the of the State Environmental Quality Review Act. The time periods for review of such plat shall begin upon the filing of such negative declaration of such notice of completion.
(4) 
Procedure for review and approval of minor subdivision plat.
(a) 
Planning Board as lead agency; public hearing; notice; decision.
[1] 
Public hearing on final minor subdivision plats. The time within which the Planning Board shall hold a public hearing on such final minor subdivision plat shall be coordinated with any hearings the Planning Board may schedule pursuant to the State Environmental Quality Review Act, as follows:
[a] 
If the Planning Board determines that the preparation of an environmental impact statement is not required, the public hearing shall be held within 62 days after the receipt of a complete final plat by the Clerk of the Planning Board; or
[b] 
If the Planning Board determines that an environmental impact statement is required, and a public hearing on the draft environmental impact statement is held, the public hearing on the draft environmental impact statement shall be held jointly within 62 days after the filing of the notice of completion of such draft environmental impact statement in accordance with the provisions of the State Environmental Quality Review Act. If no public hearing is held on the draft environmental statement, the public hearing on the final plat shall be held within 62 days following filing of the notice of completion.
[2] 
Public hearing; notice; length. The hearing on the final plat shall be advertised at least once in a newspaper of general circulation in the town at least five days before such a hearing, if no hearing is held on the draft environmental impact statement, or 14 days before a hearing held jointly therewith. The Planning Board may provide that the hearing be further advertised in such manner as it deems most appropriate for full public consideration of such final minor subdivision plat. The hearing on the final plat shall be closed upon motion of the Planning Board within 120 days after it has been opened.
[3] 
Decision. The Planning Board shall make its decision on the final minor subdivision plat as follows:
[a] 
If the Planning Board determines that the preparation of an environmental impact statement on the final minor subdivision plat is not required, the Planning Board shall, by resolution, conditionally approve, with or without modification, disapprove or grant final approval and authorize the signing of such plat within 62 days after the date of the public hearing; or
[b] 
If the Planning Board determines that an environmental impact statement is required and a public hearing is held on the draft environmental impact statement, the final environmental impact statement shall be filed within 45 days following the close of such public hearing in accordance with the provisions of the State Environmental Quality Review Act. If no public hearing is held on the draft environmental impact statement, the final environmental impact statement shall be filed within 45 days following the close of the public hearing on the final plat. Within 30 days of the filing of the final environmental impact statement, the Planning Board shall issue findings on such final environmental impact statement and shall, by resolution, conditionally approve, with or without modification, disapprove or grant final approval and authorize the signing of such plat.
[4] 
Grounds for decision. The grounds for a modification, if any, or the grounds for disapproval shall be stated upon the records of the Planning Board.
(b) 
Planning Board not as lead agency; public hearing; notice; decision.
[1] 
Public hearing. The Planning Board shall, with the agreement of the lead agency, hold the public hearing on the final minor subdivision plat jointly with the lead agency's hearing on the draft environmental impact statement. Failing such agreement or if no public hearing is held on the draft environmental impact statement, the Planning Board shall hold the public hearing on the final minor subdivision plat within 62 days after the receipt of a complete final plat by the Clerk of the Planning Board.
[2] 
Public hearing; notice; length. The hearing on the final plat shall be advertised at least once in a newspaper of general circulation in the town at least five days before such hearing, if held independently of the hearing on the draft environmental impact statement, or 14 days before a hearing held jointly therewith. The Planning Board may provide that the hearing be further advertised in such manner as it deems most appropriate for full public consideration of such final plat. The hearing on the final plat shall be closed upon motion of the Planning Board within 120 days after it has been opened.
[3] 
Decision. The Planning Board shall, by resolution, conditionally approve, with or without modification, disapprove or grant final approval and authorize the signing of such plat as follows:
[a] 
If the preparation of an environmental impact statement on the final minor subdivision plat is not required, the Planning Board shall make its decision within 62 days after the close of the public hearing on the final plat.
[b] 
If the preparation of an environmental impact statement is required, the Planning Board shall make its own findings and its decision on the final minor subdivision plat within 62 days after the close of the public hearing on such final plat or within 62 days after the close of the public hearing on such final minor subdivision plat or within 30 days after the adoption of findings by the lead agency, whichever period is longer. The grounds for a modification, if any, or the grounds for disapproval shall be stated upon the records of the Planning Board.
(5) 
Approval and certification of final minor subdivision plat.
(a) 
Within five business days of the adoption of the resolution granting conditional or final approval of the final minor subdivision plat, such plat shall be certified by the authorized officer of the Planning Board as having been granted conditional or final approval, and a copy of such resolution and plat shall be filed in both the office of the Clerk of the Planning Board and the Town Clerk. A copy of the resolution shall be mailed to the owner. In the case of a conditionally approved plat, such resolution shall include a statement of the requirements which, when completed, will authorize the signing thereof. Upon completion of such requirements, the plat shall be signed by the duly authorized officer of the Planning Board, and a copy of such signed plat shall be filed in the office of the Clerk of the Planning Board.
(b) 
Conditional approval. Conditional approval of the final minor subdivision plat shall expire within 180 days after the date of the resolution granting conditional approval unless all such requirements stated in the resolution granting conditional approval have been certified as being completed. This period may be extended by the Planning Board for up to two additional ninety-day periods beyond the 180 days.
(6) 
Default approval of minor subdivision plat. The time periods prescribed herein within which the Planning Board must take action on a minor subdivision plat are specifically intended to provide the Planning Board and the public adequate time for review and to minimize delays in the processing of subdivision applications. Such periods may be extended only by mutual consent of the owner and the Planning Board. In the event that the Planning Board fails to take action on a minor subdivision plat within the time prescribed therefor after completion of all requirements under the Environmental Quality Review Act, or within such extended period as may have been established as provided above, such minor subdivision plat shall be deemed granted approval. The certificate of the Town Clerk as to the date of submission of the minor subdivision plat and the failure of the Planning Board to take action within the prescribed time shall be issued upon demand and shall be sufficient in lieu of written endorsement or other evidence of approval herein required.
(7) 
Expiration of approval. An approved plat shall be filed in the Ontario County Clerk's office within 62 days from the date of signature of the duly authorized officer of the Planning Board or certification of no action by the Planning Board. Failure to file the plat within this period shall constitute expiration of approval.
(8) 
Issuance of permits restricted. No site improvements within the subdivision shall be installed until the plat has received final approval by the Planning Board and surety has been posted pursuant to this chapter. No building permits shall be issued within the proposed subdivision until the plat has been filed in the Ontario County Clerk's office and notification of the filing has been received by the Chairperson of the Planning Board and the Building Department.
Major subdivisions are a three-step process consisting of a sketch plat, a preliminary site plat approval process and the final approval of the plat proposed for subdivision as follows:
A. 
A "sketch plat" is a concept plat which has limited information about the proposed subdivision and is used for discussion purposes.
B. 
A "preliminary site plat" is a subdivision map which is a more detailed refinement of the plats and is considered the major design phase of the project.
C. 
A "final subdivision plat" is a refinement of the project into its final acceptable form.
A. 
Purpose. The purpose of the sketch plat review is to provide the subdivider with an opportunity to consult early and informally with the Planning Board in order to save time and money and to come to agreement as to the most desirable design given the site constraints and the development requirements of the town.
B. 
Requirements.
(1) 
Nine copies of a proposed sketch plat, a completed application and a fee shall be submitted to the Chairperson of the Planning Board within 14 days of a Planning Board meeting. Copies will be used for the following purposes:
(a) 
One copy shall be returned to the subdivider with notification of decision.
(b) 
One copy shall be retained by the Planning Board.
(c) 
One copy shall be retained by the Building Department.
(d) 
Six copies shall be used for necessary coordination with and referral to other agencies and consultants.
(2) 
Additional copies may be required to be submitted to the Chairperson of the Planning Board who may determine that other officials, agencies or consultants need to be informed about the project.
(3) 
The sketch plat shall comply with the specifications of the Building Department.
C. 
Procedures.
(1) 
Completed application. Upon the receipt of an application for a sketch plat review, the Secretary to the Planning Board shall review the application submitted to determine whether it is complete in accordance with the standards of this chapter. The Secretary shall place the matter on the agenda of the next available Planning Board meeting for discussion purposes. The Chairperson also will distribute the sketch plat to the affected agencies, including the Engineer of the town and the Building Department, for review and comment.
(2) 
The Planning Board will review the sketch plat and the comments from the agencies to which the plat was referred. The Board then may refer the subdivider to appropriate officials or agencies to resolve any issues of design or legal requirements of the respective agencies.
(3) 
Action on sketch plat. The Planning Board shall study the sketch plat of a proposed subdivision in relation to existing and potential development of the adjacent area, compliance with zoning, environmentally sensitive areas and general development patterns of the town. A decision will be made as to the desirability of the proposed development and the appropriateness of the proposed design.
(4) 
Notification of result. Not later than 62 days following the receipt of a complete sketch plat, as certified by the Chairperson to the Planning Board, the Planning Board shall convey a written report to the subdivider. The report shall contain the Board's findings of fact and its comments concerning the design of the proposed subdivision, as well as any suggestions as to coordination with the design of adjacent subdivisions or compliance with requirements of other affected public agencies. Copies of minutes of the relevant meetings shall be considered a sufficient written report.
[Amended 12-23-1997 by L.L. No. 5-1997]
(5) 
Expiration of approval. Approval of a sketch plat application shall expire six months from the date of approval if no application for preliminary plat approval is submitted within such period. The applicant may make a written request to the Planning Board for an extension of this requirement. This period may be extended by the Planning Board for up to two ninety-day periods at the discretion of the Planning Board.
[Added 8-9-2011 by L.L. No. 1-2011]
A. 
Purpose. This step provides detailed information about the site so the Planning Board can make decisions about the design of the project. Some important considerations include, but are not limited to:
(1) 
Site improvements and lot design.
(2) 
Easement requirements.
(3) 
Environmental review.
(4) 
Underground utilities and drainage design.
(5) 
An outline of the phases of the project.
B. 
Requirements.
(1) 
Nine copies of the preliminary plat and construction detail of proposed improvements, a completed application and a fee shall be submitted to the Chairperson of the Planning Board within 14 days of a Planning Board meeting. This must occur within six months of the date of the resolution approving the sketch plat. The Planning Board may, by resolution, authorize an extension beyond the six-month limit. The nine copies will be used for the following purposes:
(a) 
One copy shall be returned to the subdivider with notification of decision.
(b) 
One copy shall be retained by the Planning Board.
(c) 
One copy shall be retained by the Building Department.
(d) 
Six copies shall be used for necessary coordination with and referral to other agencies and consultants.
(2) 
Additional copies may be required to be submitted to the Chairperson of the Planning Board who may determine that other officials, agencies or consultants need to be informed about the project.
C. 
Procedures for review and decision.
(1) 
Completed application. Upon receipt of an application for a preliminary plat review, the Chairperson to the Planning Board shall review the application submitted to determine whether it is complete in accordance with the standards of this chapter. The Chairperson also will distribute the preliminary plat to the affected agencies, including the Engineer of the town and the Building Department, for review and comment. Accompanying the preliminary plat shall be all documents showing construction details of proposed improvements, any supporting materials or engineering reports and a completed environmental review form.
(2) 
Review of the preliminary plat is a two-step process conducted in parallel and consisting of an environmental review and a review conducted by the Planning Board.
(a) 
Environmental review. The environmental review is an information-gathering effort. The project is reviewed to determine if any design modifications are needed to lessen potential adverse impacts on the physical or natural environment. Unless overriding circumstances exist, the Planning Board shall be the lead agency on all subdivision proposals. The time periods for review which follow shall be used in all instances with the Planning Board as lead agency; should another agency be designated as lead agency, the procedures of Town Law § 276, Subdivision 5(e), shall prevail.
[Amended 12-23-1997 by L.L. No. 5-1997]
(b) 
The Planning Board will review the preliminary plat and the comments from the agencies to which the plat was referred. The Board then may refer the subdivider to appropriate officials or agencies to resolve any issues of design or legal requirements of the respective agencies.
(c) 
Public hearing required. The Planning Board will set an appropriate date for the public hearing.
[1] 
The Planning Board will review the completed application and the plat taking into account the comments of the affected agencies. Receipt of the completed environmental review forms is a condition of a completed application.
[2] 
The time within which the public hearing must be held shall be coordinated with any hearings which may be required pursuant to the State Environmental Quality Review Act.
[Amended 12-23-1997 by L.L. No. 5-1997]
[a] 
If the Planning Board determines that the preparation of an environmental impact statement on the preliminary plat is not required, the public hearing on such preliminary plat shall be held within 62 days after the receipt of a completed preliminary plat by the Clerk of the Planning Board.
[b] 
If the Planning Board determines that an environmental impact statement is required, and a public hearing on the draft environmental impact statement is held, the public hearing on the preliminary plat and the draft environmental impact statement shall be held jointly within 62 days after the filing of the notice of completion of such draft environmental impact statement in accordance with the provisions of the State Environmental Quality Review Act. If no public hearing is held on the draft environmental impact statement, the public hearing on the preliminary plat shall be held within 62 days of filing the notice of completion.
[3] 
Public hearing; notice, length. The hearing on the preliminary plat shall be advertised at least once in a newspaper of general circulation in the town at least five days before such a hearing if no hearing is held on the draft environmental impact statement, or fourteen days before a hearing held jointly therewith. The Planning Board may provide that the hearing be further advertised in such a manner as it deems most appropriate for full public consideration of such preliminary plat. The hearing on the preliminary plat shall be closed upon the motion of the Planning Board within 120 days after it has been opened.
[Amended 12-23-1997 by L.L. No. 5-1997]
(d) 
Action on preliminary subdivision plat.
[Amended 12-23-1997 by L.L. No. 5-1997]
[1] 
Decision. The Planning Board shall approve, with or without modifications, or disapprove such preliminary plat as follows:
[a] 
If the Planning Board determines that the preparation of an environmental impact statement on the preliminary plat is not required such Board shall make its own decision within 62 days after the close of the public hearing; or
[b] 
If the Planning Board determines that an environmental impact statement is required, and a public hearing is held on the draft environmental impact statement, the final environmental impact statement shall be filed within 45 days following the close of such public hearing in accordance with the provisions of the environmental quality review act. If no public hearing is held on the draft environmental impact statement, the final environmental impact statement shall be filed within 45 days following the close of the public hearing on the preliminary plat. Within 30 days of the filing such environmental impact statement, the Planning Board shall issue findings on the final environmental impact statement and make its decision on the preliminary plat.
[2] 
Grounds for decision. The grounds for decision for a modification, if any, or the grounds for disapproval shall be stated upon the records of the Planning Board. When so approving a preliminary plat, the Planning Board shall state, in writing, any modifications it deems necessary for submission for the plat in final form.
[3] 
Notification. Notification of action shall be filed in the Town Clerk's office within five days working days of the date of Planning Board action. In the case of disapproval of a proposed plat, the Planning Board shall state its reasons for disapproval in its minutes. A letter stating the reasons for denial shall be sent by the Planning Board to the applicant. Failure of the Planning Board to act within the required time period shall constitute approval. The certificate of the Town Clerk as to the date of submission and/or hearing and the failure to take action within such prescribed time shall be issued on demand and shall be sufficient in lieu of written approval. Notwithstanding these provisions, the time in which the Board must take action may be extended by mutual consent.
[4] 
Expiration of approval. Approval of a preliminary plat application shall expire six months from the date of approval if no application for final plat approval is submitted within such period. The applicant may make a written request to the Planning Board for an extension of this requirement. This period may be extended by the Planning Board for up to two ninety-day periods at the discretion of the Planning Board.
[Added 8-9-2011 by L.L. No. 1-2011]
A. 
Purpose. This step provides for a refinement of information submitted in the preliminary plat review procedure, submission of additional information about site design and improvements. This information permits the Planning Board, the Building Department and the Engineer for the town to make decisions concerning the appropriateness of the proposed subdivision. Some important considerations include, but are not limited to:
(1) 
Conditions of the preliminary plat approval.
(2) 
Mitigating measures resulting from environmental review.
(3) 
Offers of dedication.
(4) 
Requirements of outside agencies.
(5) 
Requirements to create or extend special districts.
(6) 
Drainage considerations.
(7) 
Monumentation of the proposed subdivision.
(8) 
Water metering during construction.
(9) 
Phasing of the proposed project.
(10) 
Erosion and conservation measures.
(11) 
Surety.
B. 
Requirements.
(1) 
Ten copies of the final plat and construction detail of proposed improvements must be submitted within six months of the date of the resolution approving the preliminary plat. The Planning Board may, by resolution, authorize an extension beyond the six-month limit.
(2) 
Accompanying each of these copies of the final plat and construction detail must be a final drainage report and applications for the creation or extension of proposed special districts. A completed application and a fee also must be submitted, together with these to the Chairperson of the Planning Board, within 14 days of a Planning Board meeting. Copies will be used for the following purposes:
(a) 
One copy shall be returned to the subdivider with notification of decision.
(b) 
One copy shall be retained by the Planning Board.
(c) 
One copy shall be retained by the Building Department.
(d) 
Seven copies shall be used for necessary coordination with and referral to other agencies and consultants.
(3) 
Additional copies may be required to be submitted to the Chairperson of the Planning Board who may determine that other officials, agencies or consultants need to be informed about the project.
(4) 
The final plat shall conform substantially to the preliminary plat as approved by the Planning Board. It shall incorporate any modifications or other features recommended by the Planning Board at the preliminary plat stage, and all such compliances shall be clearly indicated by the subdivider on the appropriate submission.
(5) 
The final plat shall be clearly marked "final subdivision plat" and shall satisfy the requirement for such plats as described in the Building Department regulations.
(6) 
If the subdivider wishes to develop the subdivision in phases, a subdivision plat covering a portion of the area encompassed by the preliminary plat must be submitted, provided that the proposed development phases were generally indicated on the preliminary plat approved by the Planning Board. However, no more than one individual phase shall be in process or under construction at any one time.
C. 
Procedures.
(1) 
Completed application. Upon receipt of an application for a final plat review, the Chairperson to the Planning Board shall review the application submitted to determine whether it is complete in accordance with the standards of this chapter. The Chairperson also will distribute the final plat to the affected agencies, including the Engineer for the town and the Building Department, for review and comment. Accompanying the final plat shall be all documents showing final construction details of proposed improvements and any supporting materials and the final engineering reports.
(2) 
The Chairperson to the Planning Board at this time also shall process any requests for formation or extension of special districts.
(3) 
Procedure for review and approval of final major subdivision plat.
[Amended 12-23-1997 by L.L. No. 5-1997]
(a) 
Planning Board as lead agency; public hearing; notice; decision.
[1] 
Public hearing on final major subdivision plats. The time within which the Planning Board shall hold a public hearing on such final major subdivision plat shall be coordinated with any hearings the Planning Board may schedule pursuant to the State Environmental Quality Review Act, as follows:
[a] 
If the Planning Board determines that the preparation of an environmental impact statement is not required, the public hearing shall be held within 62 days after the receipt of a complete final plat by the Clerk of the Planning Board; or
[b] 
If the Planning Board determines that an environmental impact statement is required, and a public hearing on the draft environmental impact statement is held, the public hearing on the draft environmental impact statement shall be held jointly within 62 days after the filing of the notice of completion of such draft environmental impact statement in accordance with the provisions of the State Environmental Quality Review Act. If no public hearing is held on the draft environmental statement, the public hearing on the final plat shall be held within 62 days following filing of the notice of completion.
[2] 
Public hearing; notice; length. The hearing on the final plat shall be advertised at least once in a newspaper of general circulation in the town at least five days before such a hearing, if no hearing is held on the draft environmental impact statement, or 14 days before a hearing held jointly therewith. The Planning Board may provide that the hearing be further advertised in such manner as it deems most appropriate for full public consideration of such final major subdivision plat. The hearing on the final plat shall be closed upon motion of the Planning Board within 120 days after it has been opened.
[3] 
Decision. The Planning Board shall make its decision on the final major subdivision plat as follows:
[a] 
If the Planning Board determines that the preparation of an environmental impact statement on the final major subdivision plat is not required, the Planning Board shall, by resolution, conditionally approve, with or without modification, disapprove or grant final approval and authorize the signing of such plat within 62 days after the date of the public hearing; or
[b] 
If the Planning Board determines that an environmental impact statement is required and a public hearing is held on the draft environmental impact statement, the final environmental impact statement shall be filed within 45 days following the close of such public hearing in accordance with the provisions of the State Environmental Quality Review Act. If no public hearing is held on the draft environmental impact statement, the final environmental impact statement shall be filed within 45 days following the close of the public hearing on the final plat. Within 30 days of the filing of the final environmental impact statement, the Planning Board shall issue findings on such final environmental impact statement and shall, by resolution, conditionally approve, with or without modification, disapprove or grant final approval and authorize the signing of such plat.
[4] 
Grounds for decision. The grounds for a modification, if any, or the grounds for disapproval shall be stated upon the records of the Planning Board.
(b) 
Planning Board not as lead agency; public hearing; notice; decision.
[1] 
Public hearing. The Planning Board shall, with the agreement of the lead agency, hold the public hearing on the final major subdivision plat jointly with the lead agency's hearing on the draft environmental impact statement. Failing such agreement or if no public hearing is held on the draft environmental impact statement, the Planning Board shall hold the public hearing on the final major subdivision plat within 62 days after the receipt of a complete final plat by the Clerk of the Planning Board.
[2] 
Public hearing; notice; length. The hearing on the final plat shall be advertised at least once in a newspaper of general circulation in the town at least five days before such hearing, if held independently of the hearing on the draft environmental impact statement, or 14 days before a hearing held jointly therewith. The Planning Board may provide that the hearing be further advertised in such manner as it deems most appropriate for full public consideration of such final plat. The hearing on the final plat shall be closed upon motion of the Planning Board within 120 days after it has been opened.
[3] 
Decision. The Planning Board shall, by resolution, conditionally approve, with or without modification, disapprove or grant final approval and authorize the signing of such plat as follows:
[a] 
If the preparation of an environmental impact statement on the final major subdivision plat is not required, the Planning Board shall make its decision within 62 days after the close of the public hearing on the final plat.
[b] 
If the preparation of an environmental impact statement is required, the Planning Board shall make its own findings and its decision on the final major subdivision plat within 62 days after the close of the public hearing on such final plat or within 62 days after the close of the public hearing on such final major subdivision plat or within 30 days after the adoption of findings by the lead agency, whichever period is longer. The grounds for a modification, if any, or the grounds for disapproval shall be stated upon the records of the Planning Board.
(4) 
Notification of action shall be filed in the Town Clerk's office within five working days of the date of Planning Board action. In the case of disapproval of a proposed plat, the Planning Board shall state its reasons for denial in its minutes. A letter stating the reasons for denial shall be sent by the Planning Board to the applicant. Failure to act within the required time period shall constitute approval. The certificate of the Town Clerk as to the date of submission and/or hearing and the failure to take action within such prescribed time shall be issued on demand and shall be sufficient in lieu of written approval.
[Amended 8-9-2011 by L.L. No. 1-2011]
(5) 
Conditional approval. Upon resolution of conditional approval, the Planning Board shall empower a duly authorized officer to sign the plat subject to completion of such requirements as may be stated in the resolution. Conditional approval shall expire within 180 days after the date of the resolution granting conditional approval unless all such requirements are completed. This period may be extended by the Planning Board for up to two ninety-day periods beyond the one-hundred-eighty-day initial period.
(6) 
Subdivision approval expiration. An approved plat shall be filed in the Ontario County Clerk's office within 62 days from the date of signature of the duly authorized officer of the Planning Board or certification of no action by the Planning Board. Failure to file the plat within this period shall constitute expiration of approval.
[Added 8-9-2011 by L.L. No. 1-2011]
D. 
Issuance of permits restricted.
(1) 
No building permits shall be issued within the proposed subdivision until the final plat has been signed by the duly authorized officer of the Planning Board and filed with the County Clerk. Notification of such filing also must be received by the Chairperson of the Planning Board and by the Building Department prior to the issuance of permits. When a certificate of occupancy is requested for a new building in a subdivision prior to the completion of all improvements shown on the approved subdivision plat, the utilities and streets serving the building shall be completed to a degree satisfactory to the Engineer of the town. The decision of the Engineer shall be based upon the following considerations:
(a) 
Adequate vehicular access for the prospective occupant and emergency vehicles.
(b) 
Services adequate or completed, including water systems and an approved means to dispose of sanitary wastes.
(c) 
Structure completed to the satisfaction of the Code Enforcement Officer who shall utilize standards set forth in the New York State Uniform Fire Prevention and Building Code.
(2) 
Where such certificate of occupancy has been issued, the streets and utilities proposed for dedication shall be maintained in a suitable condition by the subdivider at his or her expense and liability until such time as it is accepted by the town.
A. 
Completion of improvements. The developer shall complete all improvements in accordance with the approved final subdivision plats. The quality of the improvements must be in accordance with final subdivision plats. Their quality also must be acceptable to the Engineer of the town, the Water Department, the Building Department or any other agency having jurisdiction.
B. 
Waiver. The Planning Board may waive, subject to appropriate conditions and guaranties, for such period as it may determine, the provision of any or all such improvements or processes as, in its judgment of the special circumstances of a particular plat or plats, are not requisite in the interest of the public health, safety and general welfare or which in its judgment are inappropriate because of inadequacy or lack of connecting facilities adjacent or in proximity to the subdivision.
C. 
Certificates of subdivision completion. Upon completion of improvements in accordance with the approved final subdivision plat, an inspection shall be made of the project by municipal officials who have jurisdiction over the various improvements installed. Upon satisfactory review, a certificate of subdivision completion shall be issued by the Building Department. Acceptance of offers of dedication and release of final performance bond shall be prerequisites to the issuance of the certificate.
The provisions of this section are administered as provided in § 277 of the Town Law of the New York State statutes.
A. 
Purpose. For the purpose of ensuring compliance with proper installation of facilities and utilities being offered for dedication and to protect future property owners, the town requires a letter of credit or other acceptable surety to be filed with the town prior to commencement of construction of the facilities.
B. 
Approval of plats. After final approval of the subdivision plats, the developer will offer a proposed surety which indicates the estimated costs of facilities which will be offered for dedication or other such improvements required by the Planning Board. The Planning Board will review this proposed surety and, after seeking the advice of the Engineer for the town, Attorney for the town or other appropriate officials, shall submit a recommendation to the Town Board. The Town Board may, by resolution, accept or reject the proposed value.
C. 
Approval of surety. When the Town Board is satisfied with the form and value of the proposed surety and is in receipt of the surety documents, the Town Board, by resolution, will accept the surety and submit it to the Town Clerk who is charged with authorizing releases on behalf of the Town Board. The Town Clerk will authorize releases from the surety only after receiving instructions from the Town Board regarding the amount of the release, the date and the parties who will be named in the release.
D. 
Inspections. All improvements covered under a performance surety must be inspected during construction. Costs of the required inspections may be estimated by the Engineer for the town and shall be born by the developer and will be included in the initial value of the surety.
(1) 
The inspection procedure is designed to determine compliance with the approved plats.
(2) 
For inspections purposes, the contractor will notify the town when construction will be undertaken on proposed improvements. Reasonable notice is required. Normally, 24 hours' notice is considered to be reasonable.
(3) 
Inspections are the responsibility of the Engineer for the town or a designee of the Planning Board. Subcontracting of inspections on behalf of the Engineer for the town may be done only with the prior approval of the Town Board. Should the inspector find improvements are not being installed in compliance with approved plats, the Building Department shall immediately be notified. The Building Department will take all necessary and proper steps to rectify the situation.
E. 
The process for release of surety will be initiated when a request is made by the contractor for partial or total release and is submitted to the Town Board for approval. The request will be submitted to the Engineer for the town who shall compare the request with the inspection record. The Engineer's determination will be forwarded to the Town Board with a recommendation for action. At that time, the Town Board will decide, by resolution, whether to honor the request and will determine the dollar value of the release. The Town Clerk will be instructed to issue the release in the amount determined by the Town Board.
F. 
Upon completion of improvements, the Planning Board may honor a request for final release of funds.
(1) 
This process begins when the developer submits a request for release to the Town Board. Inspection by town officials of the improvements is required to assure improvements have been properly accomplished. A report of this inspection is submitted to the Planning Board which will make recommendations concerning release to the Town Board.
(2) 
The Town Board will decide whether to accept dedication. If a road is offered for dedication, the Highway Superintendent will decide whether to accept dedication. Upon acceptance of dedication, the Town Board will require a retainage fee. The Town Board will then release the developer from the former surety.
(3) 
In cases of unusually large developments or in cases of where several contractors are involved in the construction of the project or other extraordinary circumstances, phased releases may be requested by the developer. The Town Board has the right to specify the manner of issuing the releases and to whom the releases are issued.
G. 
All releases under surety are subject to retainage. Each time release occurs under a surety, 10% of the amount of the release is retained in the letter of credit until the facilities are dedicated. Upon dedication, the entire amount of the letter of credit will be released upon the filing of a suitable form of performance surety in the amount of 10% of the actual construction costs incurred. The surety shall be held for a period of one year following dedication to assure correction of any work that may be found to be defective.
H. 
Surety can be waived in instances where the subdivider installs all improvements prior to the final plat being signed by a duly authorized officer of the town.
A. 
Purpose. For the purpose of providing certain utilities and services on an equitable basis and also to assure a means of ongoing maintenance of those utilities and services, the Town of Geneva will create or extend special districts. These districts shall be formed in conformance to the provisions of New York State Town Law and as also set forth in these regulations. The formation of these special districts is accomplished to assure that only those who benefit from the installation of those utilities and services are responsible for paying for their installation and maintenance.
B. 
Requirements.
(1) 
Requirements to create or extend districts are set forth in Article 12 of New York State Town Law.
(2) 
Applications to create or extend a district must be accompanied by the required fee, a metes and bounds description of the district and a description of any easements or other information required to form the type of district requested. One copy of any application and accompanying materials, to be presented to a state agency whenever necessary, is required as part of the process of obtaining final plat approval.
C. 
Procedures. an application for the formation of a district is processed as follows:
(1) 
Applications for state approval shall be submitted to the Town Supervisor who will review and sign them and return them to the developer for submission to the appropriate state agencies.
(2) 
The Town Supervisor is responsible for taking the following actions:
(a) 
The documents shall be forwarded to the Engineer for the town who will prepare the maps and plats for the creation or extension of the district.
(b) 
The Attorney for the town shall receive and reviews all documents to assure that all provisions of Article 12 of the New York State Town Law and all other legal requirements are met. If all matters are in compliance, the attorney for the town will prepare:
[1] 
The petition for creation of the district.
[2] 
The notice for public hearing.
[3] 
The resolution creating or extending the district.
(3) 
Public hearing. Upon the receipt of a completed application for the district and recommendation of the Attorney for the town, the Town Board shall schedule and hold a public hearing on the proposed district or extension of a district. The purpose of the public hearing is to permit free and open discussion of the proposed district. Notice of the public hearing shall be published in accordance with the provisions of New York State Law. If the Town Board determines the proposal meets all state and local requirements, the district shall be created or extended by resolution of the Town Board.
(4) 
Notification. Notification of the decision shall be the responsibility of the Town Clerk and shall be performed in accordance with all provisions of state law. Final documentation concerning the creation or extension of the district shall become a part of the permanent public record of the subdivision and distributed by the Town Clerk accordingly.