Exciting enhancements are coming soon to eCode360! Learn more 🡪
Township of East Manchester, PA
York County
By using eCode360 you agree to be legally bound by the Terms of Use. If you do not agree to the Terms of Use, please do not use eCode360.
Table of Contents
Table of Contents
The work covered by this specification consists of furnishing all plant, labor, equipment, appliances and materials, and in performing all operations in connection with clearing and grubbing, rough grading and street paving, complete, in accordance with the specifications, applicable drawings and contract documents.
A. 
All equipment, materials and construction methods employed on this work shall conform to the Pennsylvania Department of Transportation Specifications, (hereinafter referred to as Form 408) latest revision, unless specifically modified herein.
B. 
For the purpose of emphasis and simplicity, a brief summary of the most applicable section of Form 408 are presented herein. However, the absence of any provisions of Form 408 from these specifications shall in no way release this contractor from full compliance therewith. In the event of specific contradiction between these specifications and Form 408, the provisions of these specifications shall be binding.
A. 
All cement, reinforcement, ready-mix concrete, and all miscellaneous materials employed on this work shall conform to the applicable provisions of PennDOT Form 408, latest revision.
B. 
Bituminous paving materials shall be PennDOT approved mixes from certified batching plants.
C. 
Stone shall be PennDOT approved sizes and grades from certified quarries.
A. 
Clearing and grubbing. All objectionable materials, including trees, stumps, brush, rubbish, and all organic or inorganic material not suitable for fill shall be removed from the project area. All root mats shall be removed to a depth of not less than one foot below subgrade.
B. 
Rough grading: excavation and fill.
(1) 
Rough grading shall consist of excavation or fill to the established grades, lines, and limits.
(2) 
Topsoil shall be stripped and stockpiled outside of the proposed street right-of-way.
(3) 
Rock, if encountered, shall be removed to a depth of not less than four inches below the established subgrade.
(4) 
Fill shall consist of clean earth; stone or such nonorganic material as may be approved by the Township Engineer. Fill shall be placed in layers not exceeding eight inches loose and compacted until the density per cubic foot is not less than 97% of the dry-weight density. Compaction shall be accomplished by utilizing a tractor and scoop, ten-ton roller, vibrating compactor or other method as approved by the Township Engineer. Compaction tests may be required by the Township Engineer.
C. 
Fine grading; preparation of subbase. Final grading shall consist of preparation of the subgrade for construction of street paving. The subgrade shall be carefully shaped using a patrol grader and compacted using a three-wheel roller weighing not less than 10 tons to not less than 100% of the dry weight density. Compaction tests may be required by the Township Engineer. In case satisfactory subgrade stability cannot be obtained, unsuitable material shall be removed and replaced with suitable material.
A. 
Crushed stone base course (standard street design).
(1) 
Where crushed stone base course is required, construction methods and materials shall be in accordance with PennDOT Form 408, latest revision.
(2) 
On a properly prepared subgrade, an initial layer of fine material, meeting the requirements for PennDOT No. 2A Aggregate, shall be spread to a depth of two inches. This initial layer of fine material shall not be placed on a wet, frozen or unsuitable subgrade.
(3) 
Course material shall be spread uniformly on the initial layer of fine material to the required depth. Coarse material shall meet the requirements for PennDOT No. 4 Aggregate. Particular attention is called to the requirements of Form 408 regarding compaction. If compaction is obtained by the use of rollers only (Method 1), base course more than eight inches in compacted depth shall be constructed in two or more layers. If approved vibratory equipment is used (Method 2), base course up to 10 inches in compacted thickness may be constructed in one course, used (Method 2), base course up to 10 inches in compacted thickness may be constructed in one course.
(4) 
After the coarse material has been satisfactorily compacted, fine material shall be spread uniformly over the surface with approved mechanical equipment. Immediately following this operation, fine material shall be broomed and rolled until the voids in the coarse material are completely filled. The spreading and rolling of the fine material shall be carried out in sections of not less than 150 feet nor more than 1,000 feet in length. Each section shall be completely bound and compacted before beginning another.
(5) 
After the completion of the application and rolling of the fine material, the surface shall be sprinkled with water and rolled. This operation shall continue, and additional fine material added, until all voids in the coarse material are filled and a slight wave of grout forms in front the roller wheels. Brooms, attached to the roller and hand brooms, shall be utilized to spread the grout uniformly and unfilled voids. After the wave of grout has been produced over the entire section of base coarse, this section shall be left to dry. The surface shall be sprinkled and rerolled on succeeding days, as required to bond it thoroughly and to secure a satisfactory surface.
(6) 
After completion of the fine material, a second layer of fine material, meeting the requirements for PennDOT No. 2A Aggregate, shall be spread to a depth of two inches. This second layer of fine material shall not be placed on a wet, frozen or unsuitable surface.
A. 
Bituminous surface course superpave (standard street design).
(1) 
Where new crushed stone base course is to be covered with superpave surface course, it shall consist of two courses, binder course and wearing course of hot-mixed, hot-laid binder asphaltic concrete, having a total thickness after final compaction of four inches, two-and-one-half-inch binder course (PG 64-22 19 MM 0.3 to three million ESAL'S, SRL-M), and an one-and-one-half-inch wearing course (PG 64-22 9.5 MM 0.3 to three million ESAL'S, SRL-M) for residential streets and 5 1/2 inches, four-inch binder course (PG 64-22 25 MM 0.3 to three million ESAL'S, SRL-M), and one-and-one-half-inch wearing course (PG 64-22 9.5 MM 0.3 to three million ESALs, SRL-M), for industrial streets. It shall be composed of materials and constructed entirely in accordance with PennDOT Form 408, latest revision. Bituminous pavers shall be self-contained, power-propelled units, provided with an activated screed or strike-off assembly, heated if necessary, and capable of spreading and finishing courses of bituminous plant mix material in land widths applicable to the specified typical section shown on the drawings. The paver shall be capable of being operated at forward speeds consistent with mechanical finishing equipment is not practical, material may be spread and finished by hand, if so directed by the Township Engineer.
(2) 
Breakdown rolling shall be performed with a three-wheel or tandem roller. Intermediate rolling shall be performed with a pneumatic tire roller. Finish rolling shall be performed with a tandem roller. Roller weight shall be sufficient to achieve not less than 95% of the density requirement established by the Marshall method at the time of approval of the mixture. Finish rolling shall continue until all roller marks are eliminated. In no case shall vibratory equipment be permitted on bituminous surface course.
(3) 
Particular attention is directed to Form 408 regarding weather limitations for placing bituminous material. Bituminous materials shall not be placed on wet surfaces, nor when the air temperature is less than 40° F., nor when the temperature of the subbase is less than 40° F.
Adjusting rings. The use of brick adjustments shall not be permitted. All manholes shall be adjusted to finished grades utilizing no more than two, two-inch thick concrete adjusting rings (four inches maximum thickness). Concrete adjusting rings shall be one piece, no split rings will be allowed. Joints between cone section, adjustment rings and frame shall be sealed with RAM-NEK or Rub'R-Nek material to provide a watertight seal. If the proper adjustment cannot be achieved by the use of two rings, the cone section shall be removed and the proper barrel section inserted. The elevation of the manhole frame and cover in new Township streets shall be set 1/8 inch to 1/4 inch below the binder course until the wearing course is constructed. At the time of wearing course construction the frame and cover shall be adjusted to finished grade by the use of concrete adjusting rings.
A. 
General.
(1) 
Description.
(a) 
The work of this section includes installation of conduits for:
[1] 
Underground electrical power transmission.
[2] 
Underground telephone and cable TV.
[3] 
Natural gas transmission.
(2) 
Quality assurance.
(a) 
American Society for Testing and Materials (ASTM):
D1785
Specifications for Poly (Vinyl Chloride) (PVC) Plastic Pipe, Schedules 40, 80, and 120
D2241
Specifications for Poly (Vinyl Chloride) (PVC) Plastic Pipe (SDR-PR)
D2321
Recommended Practice for Underground Installation of Flexible Thermoplastic Sewer Pipe
D2564
Specification for Solvent Cements for Poly (Vinyl Chloride) (PVC) Plastic Pipe and Fittings
D2855
Recommended Practice for Making Solvent-Cemented Joints with Poly (Vinyl Chloride) (PVC) Pipe and Fittings
D2729
Standard Specification for Poly (Vinyl Chloride) (PVC) Sewer Pipe and Fittings
(b) 
Materials contaminated with gasoline, lubricating oil, liquid or gaseous fuel, aromatic compounds; paint solvents, paint thinner, or acid solder will be rejected.
B. 
Products.
(1) 
Poly (Vinyl Chloride) (PVC) utility conduit.
(a) 
Natural gas:
[1] 
Main line conduits: three-inch diameter and larger shall meet the requirements of ASTM D2729. Joints shall be solvent cement.
[2] 
Service line conduits: two-and-one-half-inch diameter and smaller shall meet the requirements of ASTM D-1785 (Schedule 40). Joints shall be solvent cement.
(b) 
Telephone, electric and cable TV:
[1] 
Main line conduits: three-inch diameter and larger shall meet the requirement of ASTM D2729. Joints shall be solvent cement.
C. 
Excavation.
(1) 
Preparation.
(a) 
Natural gas lines:
[1] 
Excavate main line trenches to a minimum depth of 36 inches. Grade for the invert of the conduit plus that excavation necessary for placement of bedding material. During street construction, prior to installation of the stone base course, conduits shall be installed at all proposed crossings. Conduits shall extend a minimum of two feet beyond the curbline where curbs are proposed or a minimum of five feet beyond the paving where no curbs are proposed to be installed.
[2] 
Excavation for service lines shall be as nearly perpendicular to the street center line as possible and shall be a minimum 24 inches deep plus that excavation necessary for placement of bedding material. A minimum of two feet beyond the curbline where curbs are proposed or a minimum of five feet beyond the paving where no curbs are proposed to be installed.
(b) 
Electric conduits:
[1] 
Excavate main line trenches to a minimum depth of 24 inches plus that excavation necessary for placement of bedding material. During street construction, prior to installation of the stone base course, conduits shall be installed at all proposed crossings. Conduits shall extend a minimum of two feet beyond the curbline where curbs are proposed or a minimum to five feet beyond the paving where no curbs are proposed to be installed.
(c) 
Telephone and cable TV:
[1] 
Excavate main line trenches to a minimum depth of 24 inches plus that excavation necessary for placement of pipe bedding material. During street construction, prior to installation of the stone base course, conduits shall be installed at all proposed crossings. Conduit shall extend a minimum of two feet beyond the curbline where curbs are proposed or a minimum of five feet beyond the paving where no curbs are proposed to be installed.
(d) 
Where unsuitable bearing material is encountered in the trench bottom, continue excavation until the unsuitable material is removed, solid bearing is obtained or can be established, or concrete cradle can be placed. If no concrete cradle is to be installed, refill the trench bottom to required conduit grade, minus six inches for bedding, with PA No. 2RC aggregate.
(2) 
Width of excavation:
(a) 
Excavate main line and service trenches to a maximum width of 24 inches.
(3) 
Lay conduit to a true uniform line with a barrel of the conduit resting solidly in bedding material throughout its length. Excavate recesses in bedding material to accommodate joints. Do not subject the conduit to a blow or shock to achieve solid bearing or grade.
(4) 
Lay section of conduit in such a manner as to form a closed concentric joint with the adjoining section and to avoid offsets in the conduit.
(5) 
Clean and inspect each section of the conduit before joining. Assemble to provide tight, flexible joints that permit movement caused by expansion, contraction, and ground movement. If unusual joining resistance is encountered or if the conduit cannot be fully inserted into the bell, disassemble joint, inspect for damage, reclean joint components, and reassemble joint.
(6) 
Assemble joint in accordance with recommendations of the manufacturer.
(a) 
Solvent cemented joints:
[1] 
Camfer and deburr conduit. Clean socket and plain end. Measure and mark the socket depth on the outside of the conduit.
[2] 
Apply primer to inside socket surface using a scrubbing motion to ensure penetration. Repeated application may be necessary. Soften surface of male end of conduit to depth of fitting socket.
[3] 
Repeat application of primer to inside socket surface, then apply cement to conduit while surfaces are still wet with primer. Apply cement uniformly taking care to keep excess cement out of socket.
[4] 
Immediately after applying the last coat of cement to the conduit, and while both the inside socket surface and outside conduit surface are soft and wet, forcefully seat the conduit into the socket. Turn the conduit 1/4 turn during assembly to distribute the cement evenly. Assembly should be completed within 20 seconds after the last application of cement. Insert conduit with a steady, even motion. Do not use hammer blows.
[5] 
Hold joint in place until cement has set. Wipe excess cement from the conduit.
(7) 
Place sufficient compacted bedding and backfill on each section of conduit, as it is laid, to hold firmly in place.
(8) 
Keep trenches and excavations free from water during construction.
(9) 
When work is not in progress, at the end of each day, and at the end of each conduit run, securely plug open ends of conduit to prevent trench water, earth, and other substances from entering the conduit.
D. 
Conduit bedding backfill.
(1) 
All conduits must be surrounded with a minimum of six inches of stone dust on top, bottom and each side.
E. 
Detectable warning tape for electric and natural gas conduits.
(1) 
The contractor shall furnish and install a metallic warning tape in all electric and natural gas conduit trenches to assist in locating these underground facilities in the future. This detectable identifying tape shall be a color that is easily detected, two inches wide minimum, and be imprinted as follows: "CAUTION BURIED UTILITY LINE BELOW" of similar wording. The warning tape shall be installed 12 inches below the finished ground or street surface. Warning tape shall be Terra Tape "D" as manufactured by the Griffolyn Company, Inc., of Houston Texas or Seton Detention Tape as manufactured by Seton Name Plate Corporation, New Haven, CT 06506, or an approved equal. Materials shall meet ASTM D-2564 standards.
A. 
Notch. Where specified, the edge of the overlay shall be saw cut to a depth of 1 1/2 inches for the entire length of the joint and the detached material removed to a minimum notch width of 12 inches. A cold planer may be used. The vertical face must be painted with E-6, E-8 or the same asphalt material used in mix design [Publication 408, Section 401.2(J)].
B. 
Sealing. All joints to be sealed with hot bituminous material using PG 64-22. When wearing course is placed adjacent to curb to form bituminous gutter, seal with hot bituminous material of the class and type designated for wearing course and extend to eight inches from the curb, applied evenly. The use of Class E-6 or E-8 may be permitted in place of hot bituminous material [Publication 408, Section 401.3(G), (J)]. Streets that are to be in place for more than one year with the binder course only shall be sealed immediately following the installation of the binder course as discussed above prior to the placement of the wearing course or prior to street adoption.
A. 
Fabric. Where specified, the developer may install a geotextile fabric in addition to the base course and bituminous surface course to increase stability of the subgrade. The fabric should be a polypropylene nonwoven fabric with a tensile strength of 200 pounds for local roads and 400 pounds for collector and industrial roads. All geotextile fabrics must be approved by the Township Engineer prior to installation.