Exciting enhancements are coming soon to eCode360! Learn more 🡪
Village of Montgomery, NY
Orange County
By using eCode360 you agree to be legally bound by the Terms of Use. If you do not agree to the Terms of Use, please do not use eCode360.
Table of Contents
Table of Contents
The inspection, handling, storage, installation and testing of all piping and appurtenances shall conform to AWWA C600 Specification for any typical installation details which may pertain to the public water main.
Special care in handling shall be exercised during delivery and distribution of pipe and appurtenances to avoid damage. Damaged materials shall be rejected and replaced at the contractor's expense. The pipe shall be stored prior to use in such a manner as to prevent damage and keep the interior free from dirt and foreign matter. Any pipe that becomes contaminated shall be hand-cleaned and washed before it is incorporated in the work. It must be stressed that contamination in the line will prolong and impede the disinfection operation. Flushing cannot be too heavily relied upon for cleaning due to the low velocity of water flow.
Each length of pipe shall be marked in accordance with ANSI Specification A21.51 (AWWA C151) as to manufacturer and class.
A. 
All water mains are to be installed within the public way. Trenching and excavation in public roadway must be done in accordance with the specifications of the governmental authority having jurisdiction over the roadway.
B. 
All excavations shall be made in such manner and to such widths as will provide ample room for properly installing the pipe and to permit thorough compacting of backfill around the pipe. Enlargements of the trench shall be made to give ample space for operations and pipe joints. The depth of trench in general shall be such as to provide four feet of cover over the pipe, but this depth shall be increased or, if approved by the Village Engineer, decreased as required to avoid obstructions, to cross under streams and to make connections. The contractor shall not use excavating equipment which requires the trench to be excavated to an excessive width.
C. 
The trench shall be excavated to the required alignment, depth and width and in conformance with all federal, state and local regulations for the protection of the workmen and public and private property. Trees, shrubs, fences and all other property and surface structures shall be protected during construction. Temporary support, adequate protection and maintenance of all underground and surface structures, drains, sewers and other obstructions encountered in the progress of the work shall be furnished by the contractor.
D. 
Pipe embedment material shall be placed where shown or ordered and used for pipe bedding, haunching and initial backfill. Such embedment material shall conform to AASHTO M43, Size 78, meeting the following gradation:
[Amended 1-19-1999 by L.L. No. 2-1999]
Size
WT Percent Passing
1 inch
100
3/4 inch
90-100
1/2 inch
90-100
3/8 inch
20-55
No. 4
0-10
No. 8
0-5
E. 
Where excavation is in rock, the rock shall be removed to a depth of at least eight inches below the pipe barrel. The trench shall be refilled to grade with gravel or crushed stone fill, firmly compacted to provide proper bedding to the mid-diameter of the pipe.
A. 
Installation of piping and appurtenances shall conform to AWWA C600.
B. 
Proper and suitable tools and appliances for the safe and convenient handling and laying of pipe and fittings shall be used and shall in general agree with the manufacturer's recommendations. Deflections, however, shall not exceed 75% of the maximum amounts recommended by the manufacturer. Care shall be taken to prevent the bell and cement lining from being damaged.
C. 
When it is necessary to cut ductile-iron pipe in the field, such cuts shall be made carefully in a neat workmanlike manner using approved methods to produce a clean square cut. The outside edge of the cut end shall be conditioned for use by filing or grinding a small taper at an angle of about 30°.
D. 
At the close of work each day, the end of the pipeline shall be tightly sealed with a cap or plug so that no water, dirt or other foreign substance may enter the pipeline, and this plug shall be kept in place until the pipelaying is resumed.
E. 
No street or public place shall be opened by any person for the purpose of installing water mains, pipes or fixtures unless permission shall have been granted by the authority having jurisdiction. All surfaces must be restored to their original condition at the completion of work, or in conformance with the conditions of any highway work permit issued for the work, as appropriate.
A. 
Single-rubber gasket joints.
(1) 
The single-rubber-type joint shall be made with an elongated grooved rubber gasket which fits into a socket in the bell of the pipe. The gasket shall be wiped clean, flexed and then placed in the socket. Any bulges in the gasket which might interfere with the entry of the plain end to the pipe shall be removed. A thin film of lubricant shall be applied to the gasket surface which will come into contact with the spigot end of the pipe. The lubricant shall be as furnished by the pipe manufacturer.
(2) 
The plain end of the pipe, which is tapered for ease of assembly, shall be wiped clean and a thin film of lubricant applied to the outside. The pipe shall be aligned and carefully entered into the socket until it just makes contact with the gasket. The joint assembly shall be completed by inserting the pipe past the gasket until it makes contact with the bottom of the socket. The pipe shall be pulled home with an approved jack assembly as recommended by the pipe manufacturer. If assembly is not accomplished by reasonable force, the plain end shall be removed and the condition corrected.
(3) 
For the purpose of electrical bonding, the pipe manufacturer shall furnish serrated bronze wedges for installation in the horizontal plane between the pipe barrel and the pipe bell. The contractor shall install two wedges at each joint, one wedge on each side of each joint in strict conformance with the manufacturer's instructions.
(4) 
It shall be the responsibility of the contractor to test for electrical continuity throughout any new piping installed in the presence of the Village Engineer or his representative if any question of electrical continuity should arise.
B. 
Bolted mechanical joints.
(1) 
Mechanical joints shall be made up with gaskets, glands and bolts. When a joint is to be made up, the bell or docket and plain end shall be cleaned and washed with a solution of mild soap in water; the gland and gasket shall be slid into the plain end and the end then entered into the socket until it is fully home in the centering ring. The gasket shall then be painted with soapy water and slid into position, followed by the gland. All bolts shall be inserted and made up hand-tight and then tightened with a ratchet wrench; torque to be applied to each bolt shall be tightened alternately to bring the gland into position evenly. Excess tightening up of the bolts shall be avoided and torsion wrenches shall be used if needed to prevent excessive tightening. Care shall be taken to assure that the pipe remains fully home while the joint is being made up.
(2) 
Gaskets for all mechanical joints, including valves and fittings, shall be approved lead-tipped rubber gaskets.
A. 
Where shown on plans or where ordered by the Village Engineer or his representative, the contractor shall provide rodding to prevent joint separation. The rodding shall comply with generally accepted standards. Bands shall be 1/2 inch thick by two inches wide. The bands shall be wrought iron and fabricated to provide a snug fit behind the pipe or fitting bell. The tie rods shall be three-fourths-inch-diameter steel threaded rods unless otherwise specified. Before backfilling, all exposed metal shall receive a heavy coat of bitumastic paint.
B. 
The rodding shall supplement as a safety factor and shall not reduce the thrust blocking requirements.
A. 
Concrete thrust blocking shall be provided at plugs, tees, bends, hydrants and at other locations as may be designated where a sizable unbalanced thrust will be developed. The blocking shall be in general of such shape and form that the load due to the thrust shall not exceed two tons per square foot against earth or five tons per square foot against rock when the water pressure in the line is carried at the test pressure. The excavation at such locations shall receive special attention with such hand trimming as may be required to provide a good bearing against undisturbed materials within as short distance as possible from the pipe or fitting.
B. 
Where reactions are in the vertical plane, provisions to restrain the thrust shall be made to meet the existing field conditions by either concrete anchorages, steel dowels grouted into holes drilled in rock or a combination of both.
A. 
The contractor shall provide restraining rods for each and every hydrant installation in strict compliance with the manufacturer's assembly instructions. The rods shall be of three-fourths-inch size and threaded and assembled as follows: the tee shall be rodded to the hydrant valve and then from the valve to the hydrant, two distinct operations. Eye bolts shall be used as directed by the Village Engineer or his authorized representatives. The rods shall supplement as a safety factor and shall not reduce the thrust block requirement as directed.
B. 
Hydrants shall be set exactly plumb and to such depth as directed by the Village Engineer or his representative. They shall rest upon a selected stone or block or concrete not less than 12 inches by 12 inches by six inches and shall be similarly backed up to prevent movement of any kind. Hydrants shall be surrounded by at least five cubic feet of one-and-one-half-inch crushed stone or gravel. In excavations where drainage cannot be secured in this way, other arrangements for damage will be provided as directed. Prior to the completion of the installations, all hydrants shall be painted with two coats of paint in accordance with the manufacturer's specifications. Any hydrants deemed unacceptable shall be reset regardless of prior approval.
[Amended 1-19-1999 by L.L. No. 2-1999]
A. 
General backfill and fill materials. The contractor shall provide approved soil materials for backfill and fill which shall be free of clay, rock larger than six inches in any dimension, debris, waste, frozen materials and vegetable, organic and other deleterious matter.
B. 
Immediately after the pipes have been laid, backfilling shall be done with approved material. The material surrounding the pipe shall be carefully placed and carefully backfilled and tamped so as to have a thoroughly compacted material. Backfill material shall be placed evenly and carefully above the pipe in six-inch layers, and each layer shall be thoroughly tamped until one foot of cover exists over the pipe. The remainder of the backfill may be material excavated from the trench containing no stones larger than six inches in diameter but shall be carefully placed and compacted, if the contractor wishes to use excavated trench material, such material shall be stockpiled and tested in accordance with ASTM D698, Method C, including Note 2, so that proctor testing baseline can be established. Testing shall be performed by an approved laboratory. Until excavated material is tested and approved, the contractor shall utilize backfill material specified in Subsection C below.
C. 
Suitable backfill.
(1) 
If, in the opinion of the Engineer, the material excavated from the trench is not suitable to be used as backfill, the Engineer may direct that the trench be backfilled with well-graded granular material or run-of-bank gravel free from organic matter conforming to NYSDOT Item 304.02, Type I, with the following gradation:
Size
WT Percent Passing
3 inches
100
2 inches
90-100
1/4 inch
30-65
No. 40
5-40
No. 200
0-10
(2) 
A sample of the material shall be submitted for approval. The Engineer shall be advised in writing of its source and furnished with certification of conformance with the specification.
A. 
Requirements.
(1) 
Water mains shall be laid at least 10 feet horizontally from any existing or proposed sewer. The distance shall be measured edge-to-edge. In cases where it is not practical to maintain ten-foot separation, the Orange County Department of Health may allow deviation on a case-by-case basis. Such deviation may allow installation of the water main closer to a sewer, provided that the water main is laid in a separate trench or on an undisturbed earth shelf located on one side of the sewer at such an elevation that the bottom of the water main is at least 18 inches above the top of the sewer.
(2) 
Water mains crossing sewers shall be laid to provide a minimum vertical distance of 18 inches between the outside of the water main and the outside of the sewer. This shall be the case where the water main is either above or below the sewer. At crossings, one full length of water pipe shall be located so both joints will be as far from the sewer as possible. Special structural support for the water and sewer pipes may be required by the Village Engineer.
B. 
The Orange County Department of Health must specifically approve any variation from the above requirements when is impossible to obtain the specified separation distance.
C. 
No water pipe shall pass through or come in contact with any part of a sewer manhole.