Exciting enhancements are coming soon to eCode360! Learn more 🡪
Village of Montgomery, NY
Orange County
By using eCode360 you agree to be legally bound by the Terms of Use. If you do not agree to the Terms of Use, please do not use eCode360.
Table of Contents
Table of Contents
Flushing, hydrostatic and leakage testing shall conform to appropriate AWWA Standard C600 for ductile-iron pipe, and the following.
A. 
Testing to be performed only after partial or complete backfill and restraint blocking using high-early-strength cement has had 36 hours to cure or blocking using standard cement has had seven days to cure.
B. 
The contractor shall furnish and install, complete with reaction blocking, necessary plugs and caps required for this operation. Main line valves shall be utilized wherever possible to segregate test sections except as directed by the Village Engineer or his representative.
C. 
The contractor is to furnish all equipment and labor to complete testing.
D. 
The main shall be partially backfilled or braced against movement during the test. All air must be bled out of the section to be tested. If necessary, the contractor shall install corporation stops at the high points, for blowoffs. After all air has been expelled, the corporation cocks shall be closed and the pressure test applied. After examination of exposed parts of the system, the test pressure will be increased to 1 1/2 times the normal pressure, based upon the elevation of the lowest point in the line or section under test, but such pressure shall not be less than 125 psi or more than 200 psi, and exposed parts again examined. The minimum duration of the leakage test shall be two hours.
E. 
Allowable system leakage shall be as specified in the referenced standards. If leakage in the system is greater than allowable, the contractor will locate and repair the system at his expense and retest, continue to test and repair the system until leakage is within allowable limits.
A. 
Flushing. The contractor shall initially flush the pipeline completely, in sections, governed by the sources of clean water and suitable discharge points. The pipe section shall be flushed until the water runs clear. The contractor is advised that flushing may not create sufficient velocities to clear the pipeline of matter that may cause an unsatisfactory bacteriological test. Note that flushing is not a substitute for preventive measures during construction. Permission of the Village Engineer to stop flushing or directions to continue flushing shall involve no responsibility for the results of the bacteriological test.
B. 
Procedure for disinfecting. The water injector for introducing the chlorine-bearing water into the pipe should be supplied from a tap on the pressure side of the gate valve controlling the flow into the pipeline extension.
C. 
Rate of applications. Water from the existing distribution system or other source of supply shall be controlled as to flow slowly into the newly laid pipeline during the application of chlorine. If the continuous-feed method permitted by C651 is utilized, the rate of chlorine mixture flow shall be in such proportion to the rate of water entering the pipe that the chlorine dose applied to the water entering the newly laid pipe shall produce at least 25 parts per million residual, with a reading of 10 parts per million after a twenty-four-hour period. If the slug method of C651 is utilized, the rate of chlorine mixture flow shall be in such proportion that the chlorine dose applied to the water entering the newly laid pipe shall produce at least 100 parts per million residual. The chlorine shall be applied continuously and for a sufficient period to develop a solid column, or slug, of chlorinated water that will, as it moves through the main, expose all interior surface to a concentration of approximately 100 milligrams per liter for least three hours.
D. 
Final flushing and testing. Following chlorination, all treated water shall be thoroughly flushed from the newly laid pipeline at its extremities until the replacement water throughout its entire length shall, upon testing, be proved comparable in quality to the water served the public from the existing water supply system and as approved by the public health authority having jurisdiction. Should the initial treatment fail to result in the conditions specified, the entire procedure shall be repeated until satisfactory results are obtained. The contractor is responsible to properly dispose of the chlorinated water. The environment to which the chlorinated water is to be discharged shall be inspected. If there is any question that the chlorinated discharge will cause damage to the environment, then a reducing agent shall be applied to the water to be wasted to neutralize thoroughly the chlorine residual remaining in the water. Where necessary, state and county agencies should be contacted to determine special provisions for the disposal of heavily chlorinated water.
E. 
Bacteriological tests. The contractor shall make all arrangements with the Orange County Department of Health for bacteriological tests and shall make the tests under their direction, if required. The contractor shall furnish all equipment, disinfectants, piping, etc., required for the tests. Samples shall be taken in the presence of the Village Engineer and delivered to the test laboratory by the contractor. In the event that the initial test results do not meet Health Department standards, the contractor shall be responsible for flushing and rechlorinating the pipelines and retesting additional samples until satisfactory bacteriological test results have been achieved. All costs related in achieving satisfactory results are to be borne by the contractor. The contractor shall obtain certificates of satisfactory bacteriological testing and furnish them to the Village Engineer before the request is made for acceptance of the work.
[Amended 1-19-1999 by L.L. No. 2-1999]
F. 
The contractor shall furnish all water for flushing, testing and disinfection. The contractor shall furnish all means and apparatus for getting the water into the pipelines and shall furnish, install and remove any additional temporary blowoff piping required to discharge water used for flushing, testing and disinfection.
A. 
The contractor shall give the Village Engineer reasonable notice as to the time when he will be prepared to test portions of the work, so that inspection of all testing and disinfection can be scheduled.
B. 
Upon completion of work, the contractor will provide the Village Engineer with three sets of as-built plans of waterlines indicating valves, fittings and hydrants, with measurements. Upon receipt of this plan, an inspection of the work area will be made and any deficiencies corrected by the contractor, prior to the Village of Montgomery's acceptance of the new line.