[Ord. 691, 9/10/2009]
1.
The applicant shall obtain the required stormwater management permit for regulated activities specified in § 26-405, Subsection 3A and B, after obtaining the required subdivision or land development plan approval and stormwater management plan approval as specified in Part 4D. The stormwater management permit will be issued by the Board of Supervisors concurrently with the final subdivision and land development approval.
2.
The applicant shall obtain the required stormwater management permit for regulated activities specified in § 26-405, Subsection 3C and D, after obtaining the required building permit approval and stormwater management plan approval as specified in Part 4D. The stormwater management permit will be issued by the Code Enforcement Officer concurrently with the issuance of the building permit.
[Ord. 691, 9/10/2009; as amended by Ord. 737, 1/19/2017]
Applications for stormwater management permits required by this Part 4 shall be made on forms supplied by the Township. Such applications shall provide a brief description of the stormwater management controls and regulated activities. This application shall become part of the stormwater management plan submission required by Part 4E.
[Ord. 691, 9/10/2009]
1.
All stormwater management permits shall expire 24 months from the date of issuance, unless construction is commenced prior to this date or an extension of time is approved.
2.
An extension of an expired stormwater management permit shall be issued by the Township following the submission of a written request if, in the opinion of the Township Engineer, the subject property or affected surrounding area has not been altered in a manner which requires alteration to the stormwater management plan.
3.
A renewal of an expired stormwater management permit may be issued by the Township following a resubmittal of the permit application form and review by the Township Engineer to determine if any changes have occurred in project site conditions or stormwater management plan requirements since the original permit was issued. If such changes have occurred, the Township may require the applicant to resubmit the stormwater management plan for a new review pursuant to Part 4D.
4.
The refusal of the Township to reissue an expired stormwater management permit shall contain the reasons for such refusal.
5.
A stormwater management permit shall not expire while a request for an extension is pending.
[Ord. 691, 9/10/2009]
1.
Any stormwater management permit issued under this Part 4 may be suspended or revoked by the Board of Supervisors for:
A.
Noncompliance with or failure to implement any provision of the permit.
B.
A violation of any provision of this Part 4 or any other applicable law, ordinance, rule or regulation relating to the project.
C.
The creation of any condition or the commission of any act during construction or development which constitutes or creates a hazard or nuisance or which endangers the life or property of others.
2.
A suspended stormwater management permit shall be reinstated by the Township when: