A. 
In all areas of special flood hazards, the following standards are required.
B. 
The Planning Board shall also determine, with the advice and assistance of the Township Engineer, Construction Official and other competent authorities, that:
(1) 
The proposed utilities and facilities, such as water, sewer and electrical systems, are located, elevated and constructed to minimize or eliminate flood damage. These shall include watertight manholes with vents, raised vents, flap valves, etc. Such facilities shall be constructed with overflow elevations two feet above flood level.
(2) 
Drainage is provided to reduce exposure to flood hazards.
(3) 
Watertight doors will be installed.
(4) 
The construction makes use of paints, membranes or mortars to reduce seepage of water through walls.
(5) 
Backfill should be of soils with natural low permeability.
(6) 
Eight inches of compacted granular fill is used beneath the ground floor; said fill materials shall act as a french drain.
(7) 
No buried fuel oil tanks shall be permitted unless properly anchored and vented, with the vent two feet above the flood level.
A. 
All new construction and substantial improvements shall be anchored to prevent flotation, collapse, or lateral movement of the structure.
B. 
All manufactured homes shall be anchored to resist flotation, collapse or lateral movement. Methods of anchoring may include, but are not to be limited to, use of over-the-top or frame ties to ground anchors. This requirement is in addition to applicable state and local anchoring requirements for resisting wind forces.
(1) 
Over-the-top ties shall be provided at each of the four corners of the mobile home, with two additional ties per side at intermediate locations, with mobile homes less than 50 feet long requiring one additional tie per side.
(2) 
Frame ties shall be provided at each corner of the home, with five additional ties at intermediate points, with mobile homes less than 50 feet long requiring four additional ties per side.
(3) 
All components of the anchoring system shall be capable of carrying a force of 4,800 pounds.
(4) 
Any additions to the mobile home shall be similarly anchored.
A. 
All new construction and substantial improvements shall be constructed with materials and utility equipment resistant to flood damage.
B. 
All new construction and substantial improvements shall be constructed using methods and practices that minimize flood damage.
A. 
All new and replacement water supply systems shall be designed to minimize or eliminate infiltration of floodwaters into the system;
B. 
New and replacement sanitary sewage systems shall be designed to minimize or eliminate infiltration of floodwaters into the systems and discharge from the systems into floodwaters;
C. 
On-site waste disposal systems shall be located to avoid impairment to them or contamination from them during flooding; and
D. 
Electrical, heating, ventilation, plumbing and air-conditioning equipment and other service facilities shall be designed and/or located so as to prevent water from entering or accumulating within the components during conditions of flooding.
A. 
All subdivision proposals shall be consistent with the need to minimize flood damage;
B. 
All subdivision proposals shall have public utilities and facilities such as sewer, gas, electrical, and water systems located and constructed to minimize flood damage;
C. 
All subdivision proposals shall have adequate drainage provided to reduce exposure to flood damage; and
D. 
Base flood elevation data shall be provided for subdivision proposals and other proposed development which contain at least 50 lots or five acres (whichever is less).
All new construction and substantial improvements having fully enclosed areas below the lowest floor that are usable solely for parking of vehicles, building access or storage in an area other than a basement and which are subject to flooding shall be designed to automatically equalize hydrostatic flood forces on exterior walls by allowing for the entry and exit of floodwaters. Designs for meeting this requirement must either be certified by a registered professional engineer or architect or must meet or exceed the following minimum criteria: A minimum of two openings having a total net area of not less than one square inch for every square foot of enclosed area subject to flooding shall be provided. The bottom of all openings shall be no higher than one foot above grade. Openings may be equipped with screens, louvers, or other covering or devices, provided that they permit the automatic entry and exit of floodwaters.
In all areas of special flood hazards where base flood elevation data has been provided as set forth in § 136-7, Basis for establishing areas of special flood hazard, or in § 136-15, Use of other base flood and floodway data, the following standards below are required.
A. 
New construction and substantial improvement of any residential structure shall have the lowest floor, including basement, together with the attendant utilities and sanitary facilities, elevated to or above base flood elevation;
B. 
Within any AO Zone on the municipality's FIRM, that all new construction and substantial improvement of any residential structure shall have the lowest floor, including basement, elevated above the highest adjacent grade at least as high as the depth number specified in feet (at least two feet if no depth number is specified), and require adequate drainage paths around structures on slopes to guide floodwaters around and away from proposed structures.
In an area of special flood hazard, all new construction and substantial improvement of any commercial, industrial or other nonresidential structure shall have the lowest floor, including basement, together with the attendant utilities and sanitary facilities, either elevated to the level of the base flood elevation and, within any AO Zone on the municipality's DFIRM, that all new construction and substantial improvement of any commercial, industrial or other nonresidential structure shall have the lowest floor, including basement, elevated above the highest adjacent grade at least as high as the depth number specified in feet (at least two feet if no depth number is specified), and require adequate drainage paths around structures on slopes to guide floodwaters around and away from proposed structures, or:
A. 
Be floodproofed so that below the base flood level the structure is watertight with walls substantially impermeable to the passage of water;
B. 
Have structural components capable of resisting hydrostatic and hydrodynamic loads and effects of buoyancy; and
C. 
Be certified by a registered professional engineer or architect that the design and methods of construction are in accordance with accepted standards of practice for meeting the applicable provisions of this section. Such certification shall be provided to the official as set forth in § 136-12C.
A. 
Manufactured homes shall be anchored in accordance with § 136-22B.
B. 
All manufactured homes to be placed or substantially improved within an area of special flood hazard shall be elevated on a permanent foundation such that the top of the lowest floor is at or above the base flood elevation.
C. 
No mobile homes shall be placed in a floodway.
Located within areas of special flood hazard established in § 136-7 are areas designated as floodways. Since the floodway is an extremely hazardous area due to the velocity of floodwaters which carry debris, potential projectiles, and erosion potential, the following provisions apply:
A. 
Prohibit encroachments, including fill, new construction, substantial improvements, and other development, unless a technical evaluation demonstrates that encroachment shall not result in any increase in flood levels during the occurrence of the base flood discharge.
B. 
If § 136-31A is satisfied, all new construction and substantial improvements must comply with Article V, Provisions for Flood Hazard Reduction.
C. 
In all areas of special flood hazard in which base flood elevation data has been provided and no floodway has been designated, the cumulative effect of any proposed development, when combined with all other existing and anticipated development, shall not increase the water surface elevation of the base flood more than 0.2 of a foot at any point.