A.
At the developer's option, the developer may grant to the Township
of Connoquenessing an easement for drainage. The developer should
consider granting the following easements:
B.
In lieu of granting an easement to the Township of Connoquenessing
for drainage, the developer shall enter into a legal agreement approved
by the Solicitor, which shall hold the Township harmless from any
and all liability relating to storm drainage collection and its discharge
during construction of the stormwater system and thereafter.
C.
The owner or developer shall secure, where necessary, all off-site
easements for storm drainage (i.e., downstream properties).
D.
All easement agreements will be recorded with a reference to the
recorded development plan.
A.
Where the developer grants an easement for a drainageway, drainage
swale, watercourse, channel or stream, the easement should be a minimum
of 20 feet wide and paralleling the center line of such drainageway,
drainage swale, watercourse, channel or stream; and to the extent
possible, such drainage easements should encompass the one-hundred-year
floodplain.
B.
The Township of Connoquenessing may refuse acceptance of any easement
that in the opinion of the Township Engineer is of insufficient width
to allow for proper maintenance and servicing of the drainageway,
drainage swale, watercourse, channel or stream.
C.
The Township of Connoquenessing may refuse acceptance of any easement
that in the opinion of the Township Engineer does not provide for
a means of ingress, regress and egress to the drainageway, drainage
swale, watercourse, channel or stream.
In all residential subdivisions and land developments where
a homeowner's association is not proposed for the maintenance of common
facilities, the developer shall dedicate the stormwater management
facilities to the Township of Connoquenessing, provided that a minimum
twenty-foot right-of-way for access and easement around the entire
perimeter of the facility is provided. All facilities which are dedicated
to the Township shall be subject to payment of a stormwater maintenance
fee as a prerequisite to acceptance of the dedication, said fee to
be established by resolution of the Township of Connoquenessing Board
of Supervisors based on the cubic capacity of the detention facility.