[Zoning Order §3.240, 4-2-2008]
No new or existing building or structure, for which the Jefferson
County Building Code requires an occupancy permit, shall be occupied
or used within the County until a certificate of occupancy (temporary
and final), certifying that the building or use complies with all
regulations of this UDO and other applicable provisions of the County
Code, has been issued by the Building Official pursuant to the Building
Code.
[Zoning Order §3.250, 4-2-2008]
The request shall be considered by the Building Official and
may be granted if found to satisfy the criteria set forth in the Building
Code and other related issues as required by the Planning Division
and other governmental agencies that regulate occupancy of a structure
or use.
[Zoning Order §3.260, 4-2-2008]
All appeals for non-issuance of a certificate of occupancy request
or revocation of a certificate of occupancy shall be as set forth
in the Building Code.
[Zoning Order §3.270, 4-2-2008]
A record of all certificates of occupancy shall be kept on file
in the office of the Building Official.
[Zoning Order §3.280, 4-2-2008]
Except where some other method of handling liquid waste has
been specifically approved by the County, no certificate of occupancy
shall be issued by the Building Official for any building or use until
the property has been connected with a sanitary sewer/wastewater system
that has been approved by the applicable State and local authority.
[Zoning Order §3.290, 4-2-2008]
Prior to issuance of a certificate of occupancy for a new building or structure or change in use of an existing building or structure, all parking requirements, as specified in Article
XII of this UDO for the new use, shall be met or otherwise approved by the Director.