A. 
The Borough or its designee shall inspect all phases or the installation of any temporary or permanent SWM facilities.
B. 
A schedule of required inspections shall be determined through a pre-construction meeting with Borough staff.
C. 
Required inspections shall be scheduled through the Borough a minimum of 24 hours prior to the time the inspection is requested.
D. 
During any stage of work, if the Borough or its designee determines that any temporary or permanent SWM facilities are not being installed in accordance with the approved SWM site plan, the Borough shall revoke any existing permits until a revised SWM site plan is submitted and approved, as specified in this chapter.