[Ord. No. 01-29, 5-22-2001; Ord. No. 03-01, 2-6-2003; Ord. No. 04-54, 10-21-2004; Ord. No. 05-28, 9-1-2005; Ord. No. 06-10, 4-20-2006; Ord. No. 06-22, 7-20-2006; Ord. No. 06-49, 10-19-2006; Ord. No. 07-07, 3-1-2007; Ord. No. 07-21, 7-5-2007; Ord. No. 08-41, 11-20-2008; Ord. No. 11-02, 1-20-2011; Ord. No. 11-04, 2-3-2011; Ord. No. 13-24, 10-17-2013; Ord. No. 14-23, 1-22-2015; Ord. No. 20-02, 2-6-2020]
A.
Building permit fees for construction permits shall be issued in accordance with this Chapter. A formula is provided by the International Code Council Building Valuation Data (Square Foot Construction Costs chart). The Building Department shall use Table 500 found at Attachment 1 to this Section for calculating construction value of project.
Description | Project Valuation | Building Permit Fee |
|---|---|---|
Residential small job | $1,000.00 or less | $35.00 |
Residential | $1,001.00 to $5,000.00 | $50.00 |
Commercial | $0.00 to $5,000.00 | $50.00 |
Commercial and residential | Over $5,001.00 | $50.00 (base first $5,000.00), plus $4.50 per each additional $1,000.00 of valuation |
Example: Construction value is $10,000.00 |
$10,000.00 - $5,000.00 (base) = $5,000.00 |
$5,000.00 (additional valuation)/$1,000.00 = 5 |
5 x $4.50 = $22.50 |
$22.50 + $50.00 = $72.50 (building permit fees) |
B.
Plan review fees shall be paid at the time plans are submitted for review. A formula is provided by the International Code Council Building Valuation Data (Square Foot Construction Costs chart). The Building Department shall use Table 500 found at Attachment 1 to this Section for calculating construction value of project for plan review fees.
Project Valuations | Plan Review Fees |
|---|---|
Less than $30,000.00 or new single-family dwelling | $40.00 |
Over $30,000.00 | $1.50 per $1,000.00 |
C.
No building or structure shall be constructed, enlarged, altered, repaired, or moved until a permit has been issued by the Building Department. A permit is also required to erect, install, enlarge, alter, repair, remove, convert or replace any electrical, gas, mechanical or plumbing system, the installation of which is covered by the International Codes. Except upon a recommendation of the Planning Commission, no building permit shall be issued for any building where said construction, addition or alteration or use thereof would be in violation of any of the provisions of this Zoning Code.
No building permit shall be issued until after such time that there are adequately sized public water lines and public sewer lines with any necessary pumps or lift stations in place so that the proposed structure can make a direct connection to the public system without requiring an easement across any other property. Hollister must receive a copy of the Missouri Department of Natural Resources permits for construction of new infrastructure. There must be adequate capacity in the infrastructure, new or existing, and Hollister must approve the connections. After the adoption of a major street plan, no building permit shall be issued for and no building shall be erected on any lot within the territorial jurisdiction of the Planning Commission unless the street giving access to the lot upon which the building is proposed to be placed conforms to the requirements of Chapter 405.
D.
The application fee to go before the Building Board of Appeals is fifty dollars ($50.00).
E.
Refunds. Not more than eighty percent (80%) of the building permit fee paid for a permit to be issued shall be refunded when no work has been done under the permit issued. Plan review fees are non-refundable. All refunds must be requested in writing by the original permittee not later than one hundred eighty (180) days after the date of the payment.