Prior to the issuance of any permits for development within
a Traditional Neighborhood Development, the following steps shall
be completed according to the procedures outlined in this section:
A.
The applicant shall have had an initial conference with Village staff.
B.
A specific implementation plan and a Zoning Map amendment to a Traditional
Neighborhood Development District shall be approved by the Village
Board after review by the Plan Commission.
C.
A specific implementation plan shall be approved by the Village Board after review by the Plan Commission along with any plans and documentation required by Municipal Code Chapter 410, Subdivision of Land.
(1)
Initial conference. Before submitting an application for a Traditional
Neighborhood Development project, the applicant shall schedule an
appointment and meet with Community Development Director or his/her
designee to discuss the procedure for approval of a Traditional Neighborhood
Development project, including submittal requirements and design standards.
(2)
General implementation plan. Following the initial conference,
the applicant shall submit a general implementation plan to the Community
Development Director or his/her designee together with an application
for rezoning request to a Traditional Neighborhood Development District
and a reasonable schedule for the implementation of the development
to the satisfaction of the Plan Commission and Village Board.
(a)
Within 45 days, the Plan Commission shall consider the Zoning
Map amendment request and make a recommendation for approval or disapproval
of a general implementation plan. The Plan Commission shall receive
a report from the municipal staff recommending approval, disapproval
or approval with specified modifications. Within 30 days, the Plan
Commission shall recommend the Village Board either:
(b)
The Village Board shall receive the recommendation from the
Plan Commission and report from municipal staff and hold a public
hearing on the proposed general implementation plan. Upon due consideration,
the Village Board shall either:
(3)
General implementation plan submittal requirements. The purpose
of the general implementation plan is to establish the intent, density,
and intensity for a proposed development. The general implementation
plan shall include the following:
(a)
A general location map of suitable scale, but no less than one
inch equals 200 feet, which shows the location of the property within
the community and adjacent parcels including locations of any public
streets, railroads, major streams or rivers and other major features
within 1,000 feet of the site.
(b)
A site inventory and analysis to identify site assets or resources,
and constraints, including but not limited to floodplains, wetlands
and soils classified as "poorly drained" or "very poorly drained,"
soils with bedrock at or within 42 inches of the surface, utility
easements for high-tension electrical transmission lines (>69KV),
steep slopes greater than 15%, and brownfields.
(c)
A conceptual site plan, at a scale of no less than one inch
equals 100 feet, which indicates topography in two-foot contours for
sites with 15 feet or more of local relief, or one-foot contours for
local sites with less than 15 feet of local relief, consisting of
a map with proposed features and existing site features and uses that
will remain. These features should include building outlines, location
of streets, transit stops, drives and parking areas, pedestrian and
bicycle paths, service access areas for receiving material and trash
removal, and other impervious surfaces. The location of proposed and
existing to remain trees and shrubs should also be included, along
with any other significant features.
(d)
A conceptual stormwater management plan identifying the proposed
patterns of major stormwater runoff, locations of stormwater infiltration
areas, and other significant stormwater best management practices.
(e)
Identification of the architectural style(s) of the Traditional
Neighborhood Development and the accompanying site design style(s).
The design style of the Traditional Neighborhood Development shall
be conveyed with drawings or computer simulations of typical proposed
building elevations (including dimensions of building height and width,
and facade treatment).
(f)
A written report that provides general information about the
covenants, conservation easements, or agreements which will influence
the use and maintenance of the proposed development. The report shall
also describe the site conditions and the development objectives.
(g)
Any other information deemed necessary by the Village in order
to evaluate plans.
(h)
A copy of the above information shall be submitted plus a PDF
and one reduced set no larger than 11 inches by 17 inches.
(4)
Specific implementation plan. The purpose of the specific implementation
plan is to establish a detailed development proposal. The specific
implementation plan can be proposed, reviewed, and acted upon as whole
or in part or phases. Following approval of the general implementation
plan, the applicant shall submit a specific implementation plan to
the Plan Commission.
(a)
Within 30 days following receipt of the specific implementation
plan, the Plan Commission shall receive a report from the municipal
staff recommending approval, disapproval or approval with specified
modifications. The Plan Commission shall determine that the proposed
specific implementation plan is in substantial conformance with the
approved general implementation plan. Upon due consideration, the
Plan Commission shall recommend that the Village Board either:
[1]
Approve the specific implementation plan as being
in substantial conformance with the general implementation plan;
[2]
Approve the specific implementation plan as being
in substantial conformance with the general implementation plan with
specified modifications; or
[3]
Deny the specific implementation plan.
(b)
Following Plan Commission recommendation, the Village Board
shall receive the recommendation from the Plan Commission and the
report from the municipal staff. Upon due consideration, the Village
Board shall either:
[1]
Approve the specific implementation plan as being
in substantial conformance with the general implementation plan;
[2]
Approve the specific implementation plan as being
in substantial conformance with the general implementation plan with
specified modifications; or
[3]
Deny the specific implementation plan.
(5)
Specific implementation plan submittal requirements. The applicant
shall submit a series of plans, maps, and written materials which
include the following information:
(a)
A general location map of suitable scale which shows the boundaries
and dimensions of the property within the context of the Village and
adjacent parcels, including locations of any public streets, railroads,
major streams or rivers and other major features within 1,000 feet
of the site, along with a legal description of the property.
(b)
A site inventory and analysis to identify site assets or resources,
and constraints, including but not limited to floodplains, wetlands
and soils classified as "poorly drained" or "very poorly drained,"
soils with bedrock at or within 42 inches of the surface, utility
easements for high-tension electrical transmission lines (>69KV),
slopes greater than 15%, and brownfields.
(c)
A site plan, including proposed topographic contours at one-foot
intervals, with the following information:
[1]
The location of proposed structures and existing
structures that will remain, with height and gross floor area noted.
[2]
The location of street and pedestrian lighting,
including lamp intensity and height.
[3]
Location of proposed open space.
[4]
The circulation system indicating pedestrian, bicycle,
and motor vehicle movement systems, including existing and proposed
public streets or rights-of-way; transit stops.
[5]
Easements or other reservations of land on the
site; the location and dimensions of existing and proposed curb cuts,
off-street parking and loading spaces, include service access for
receiving and trash removal; sidewalks and other walkways.
[6]
Location of all trees, shrubs, and ground cover
(proposed or existing) to remain on the site.
(d)
A stormwater management plan for the site. The grading plan
shall show existing and proposed ground elevations with contours (one-foot
contour interval) and spot elevations at significant high points,
low points, and transition points. The grading plan shall also note
the finished ground floor elevations of all buildings. The plan shall
also show the locations of all storm drainage sewers and structures,
and infiltration or detention/retention structures; and all wetlands
on the site, using the Federal Manual for Identifying and Delineating
Jurisdictional Wetlands, and copies of documents completed in making
the wetlands identification.
(e)
Detailed elevations of all proposed commercial buildings and
typical elevations of residential buildings. Scaled elevations should
identify all signs, building materials and percentage of ground floor
commercial facade in windows; the location, height and material for
screening walls and fences, including outdoor trash storage areas,
electrical, mechanical and gas metering equipment, storage areas for
trash and recyclable materials, and rooftop equipment.
(f)
A utilities plan showing underground and aboveground lines and
structures for sanitary sewers, electricity, gas, telecommunications,
etc.
(g)
A written report which completely describes the proposal and
indicates covenants or agreements that will influence the use and
maintenance of the proposed development. The report also shall describe
the analysis of site conditions and the development objectives.
(h)
Phasing plans, where applicable.
(i)
Any other information deemed necessary by the Village Board
in order to evaluate plans.
(j)
A copy of the above information shall be submitted plus a PDF
and one reduced set no larger than 11 inches by 17 inches.
(6)
Amendments to the specific implementation plan.
(a)
Minor changes to the specific implementation plan adopted by
the Village Board may be approved by the Community Development Director
or his/her designee, provided that the changes do not involve:
(b)
A major change to a specific implementation plan which is less
restrictive than any conditions of approval for the initial specific
implementation plan shall require approval by a majority vote of all
members of the Village Board.
(7)
Subdivision of land. If the Traditional Neighborhood Development involves the subdivision of land as defined in the Village's subdivision ordinance, Chapter 410, Subdivision of Land, the applicant shall submit all required land division documents in accordance with the requirements of the subdivision ordinance and Chapter 236 of the Wisconsin Statutes. If there is a conflict between the design standards of the subdivision ordinance and the design guidelines of this chapter, the provisions of this chapter shall apply.
(8)
Ownership and maintenance of public space. Provisions shall
be made for the ownership and maintenance of streets, squares, parks,
open space, and other public spaces in a Traditional Neighborhood
Development by dedication to the Village.
(9)
Recording of documents. The following documents need to be filed
by the applicant in the Brown County Register of Deeds Office within
30 days after approval of the document by the Village Board a certified
copy of this chapter amendment designating a tract of land as a Traditional
Neighborhood Development; the general implementation plan; and the
specific implementation plan.