A.
All on-site wastewater disposal systems shall be installed by a person or firm that has a valid installer's permit issued by the Middleton BOH.
B.
Construction of the on-site wastewater disposal systems system shall be performed in accordance with the approved plans and any requirements set forth by the BOH. Failure to comply with the requirements of the design shall constitute a basis for revocation of the installer's permit and fines as outlined under § 339-23, Severability; violations and penalties.
C.
The designer shall inspect and verify the bottom of the leaching system elevation(s) and all pipe invert elevations during construction.
D.
The BOH shall be notified when the construction has been completed to the following stages to allow for inspection. The installer shall request an inspection a minimum of 24 hours in advance for all inspections in addition to as outlined:
(1)
When excavation is completed prior to the placement of sand and stone for the leaching field;
(2)
When the trench, pit, or bed excavation is complete prior to placement of stone;
(3)
After placement of tanks, distribution boxes, piping, etc., prior to installation of backfill material around these items; and
(4)
When stone has been placed around system components prior to final backfilling. During this inspection, a water flow test may be conducted to determine if proper flow characteristics exist.