Ord. 137-1970
4/6/1970
Authorizing and approving an agreement dated March 1, 1970, between Spring Township Authority and Milesburg - Boggs Township Joint Authority
Res. 144-1970
7/1/1970
Releasing Harris, Henry & Potter, Inc., as engineers of the sewer project
Res. 167-1971
12/6/1971
Authorizing Gannett, Fleming, Cordry and Carpenter to finalize the sewer study and cost estimates in conjunction with Bellefonte Borough and/or Mid Centre Authority
Res. 208-1974
11/4/1974
Furnishing municipal sewer service to the new Pleasant Gap School
Ord. 26-1979
8/6/1979
Approving an agreement, dated August 15, 1979, between Spring Township and Spring-Benner Joint Authority to construct and acquire a complete sanitary sewage collection system
Ord. 27-1979
8/6/1979
Granting Spring-Benner Joint Authority certain rights and privileges in connection with said authority's sewer system
Res. 40-1980A
6/2/1980
Approving the plan revision of the Belle-Spring Skateland holding tank, as a temporary measure until the sewer is in operation
Res. 52-1980
9/9/1980
Approving the plan revision of Melvina McGranahan for a holding tank as a temporary measure until the public sewer is in operation
Res. 53-1980
9/9/1980
Approving the plan revision for Thomas Martinec for a holding tank as a temporary measures until the public sewer is in operation
Res. 54-1980
9/9/1980
Approving the plan revision of Jeffrey Kennedy for a holding tank as a temporary measure until the public sewer is in operation
Res. 55-1980
9/9/1980
Approving the plan revision of Franklin Thomas for a holding tank as a temporary measure until the public sewer is in operation
Res. 58-1980
10/6/1980
Approving the plan revision of several specified property owners for holding tanks as temporary measures until the public sewer is in operation
Res. 59-1980
10/6/1980
Approving the plan revision of Marlin Sheuy, Bush Addition, for a holding tank as a temporary measure until the public sewer is in operation
Res. 60-1980
10/6/1980
Approving the plan revision of Russell Day, Pleasant Gap, for a holding tank as a temporary measures until the public sewer is in operation
Res. 75-1981
7/6/1981
Approving the request for a holding tank for the mother of Mrs. Clearance McCool, as a temporary measure with certain specified stipulations
Res. 12-1982
6/7/1982
Amending Res. 78-1981 regarding the Clarence McCool holding tank
Res. 20-1982
9/7/1982
Approving an agreement with the Spring-Benner Joint Authority to assist in the collection of delinquent sewer rental payments
Res. 61-1985
11/4/1985
Adopting and submitting to the Department of Environmental Resources for its approval as a revision to the official plan of the Township the Pleasant Hills P.R.D. planning module
Res. 83-1986
11/3/1986
Waiving the requirement of Kenneth and Delores Weaver to connect their property to the Township's sewer system
Res. 92-1987
2/2/1987
Approving a plan revision for John W. Sheckler subdivision for a holding tank as a temporary measure until the public sewer is operational
Res. 119-1988
2/8/1988
Adopting and submitting to the Department of Environmental Resources for its approval as a revision to the official plan of the Township the Greenhill Farms, Section 5, planning module
Res. 120-1988
2/8/1988
Adopting and submitting to the Department of Environmental Resources for its approval as a revision to the official plan of the Township the Two Lot Subdivision planning module
Res. 123-1988A
2/29/1988
Adopting and submitting to the Department of Environmental Resources for its approval as a revision to the official plan of the Township the John W. Steckler, Phase II planning module
Res. 124-1988
2/29/1988
Adopting and submitting to the Department of Environmental Resources for its approval as a revision to the official plan of the Township the Erin Enterprises planning module
Res. 125-1988
7/5/1988
Adopting and submitting to the Department of Environmental Resources for its approval as a revision to the official plan of the Township the Corman Subdivision planning module
Res. 126-1988
7/5/1988
Adopting and submitting to the Department of Environmental Resources for its approval as a revision to the official plan of the Township the Musser Hills Subdivision, Section I planning module
Res. 127-1988
7/5/1988
Adopting and submitting to the Department of Environmental Resources for its approval as a revision to the official plan of the Township the Iron Ore Village, Section II planning module
Res. 133-1988
12/5/1988
Approving temporary holding tanks for several specified persons until the public sewer is operational
Res. 7-1989
3/7/1989
Adopting and submitting to the Department of Environmental Resources for its approval as a revision to the official plan of the Township the Terry and Doris Horner planning module
Res. 8-1989
4/3/1989
Adopting and submitting to the Department of Environmental Resources for its approval as a revision to the official plan of the Township the plot and resubdivision of lot A of the Thomas J. Donovan Subdivision into two lots planning module
Res. 20-1989
9/5/1989
Not approving any new construction as related to sewer and EDU counts unless it has been approved by the Spring Township Board of Supervisors, Spring Township Planning Commission and Spring Township Code Enforcement Officer
Res. 28-1989
12/18/1989
Adopting and submitting to the Department of Environmental Resources for its approval as a revision to the official plan of the Township the Noerr's Garage planning module
Res. 30-1990
6/4/1990
Adopting and submitting to the Department of Environmental Resources for its approval as a revision to the official plan of the Township the Brockerhoff Heights planning module
Res. 31-1990
6/4/1990
Adopting and submitting to the Department of Environmental Resources for its approval as a revision to the official plan of the Township the Root Subdivision planning module
Res. 32-1990
6/4/1990
Adopting and submitting to the Department of Environmental Resources for its approval as a revision to the official plan of the Township the A.H. Smith Estate planning module
Res. 39-1990
10/1/1990
Adopting and submitting to the Department of Environmental Resources for its approval as a revision to the official plan of the Township the State Correctional Institutional at Rockview planning module
Res. 40-1990
10/16/1990
Adopting and submitting to the Department of Environmental Resources for its approval as a revision to the official plan of the Township the Pleasant Hills PRD Phases 4, 7, 8 and 9 planning module
Res. 43-1990
11/5/1990
Adopting and submitting to the Department of Environmental Resources for its approval as a revision to the official plan of the Township the development plan for the property of Robert Delafield and James Quici, Jr., planning module
Res. 44-1990
12/11/1990
Adopting and submitting to the Department of Environmental Resources for its approval as a revision to the official plan of the Township the Sylvan Acres, Section II, planning module
Res. 58-1991
1/23/1991
Appointing a workshop committee the address the feasibility of putting public sewer in the portion of Spring Township, in the Lyonstown and Jacksonville area
Res. 59-1991
2/4/1991
Authorizing the Spring-Benner-Walker Joint Authority to proceed with the Jacksonville/Lyonstown project
Res. 61-1991
1991
Authorizing the Spring-Benner-Walker Joint Authority and Bellefonte Sewer Authority to proceed with the sewage flow from the State Penitentiary at Rockview
Res. 64-1991
3/4/1991
Adopting and submitting to the Department of Environmental Resources for its approval as a revision to the official plan of the Township the Stonehenge Phase 2-6 planning module
Res. 67-1991
5/6/1991
Adopting and submitting to the Department of Environmental Resources for its approval as a revision to the official plan of the Township the Brockerhoff Heights, replot and resubdivision of previously approved Brockerhoff Subdivision planning module
Res. 68-1991
5/6/1991
Adopting and submitting to the Department of Environmental Resources for its approval as a revision to the official plan of the Township the Subdivision of Lot 2 & 3 of Brockerhoff Subdivision into 4 lots and lot addition Lot 2A and Lot of G.V. & M.W. Noll C & D planning module
Res. 69-1991
5/6/1991
Adopting and submitting to the Department of Environmental Resources for its approval as a revision to the official plan of the Township the Penn Eagle Industrial Park, Phase 2 planning module
Res. 82-1991
7/1/1991
Granting parcel #13-01B-14, presently listed as Correl property, for sale, the owner the right to install a holding tank
Res. 90-1991
10/7/1991
Granting unto Mr. and Mrs. Leslie Root permission to make module application for Act 537 approval of 100 EDU capped sewers for their planned development
Res. 93-1991
10/7/1991
Granting unto Centre County Industrial Development Corporation the right to submit planning module for Act 537 for Phase 2 of the Penn Eagle Industrial Park
Res. 95-1991
9/3/1991
Adopting and submitting to the Department of Environmental Resources for its approval as a revision to the official plan of the Township the William P. Watson planning module
Res. 103-1991
12/18/1991
Adopting and submitting to the Department of Environmental Resources for its approval as a revision to the official plan of the Township the Division of Lot 8 Sylvan Acres, Section II, planning module
Res. 106-1992
2/3/1992
Adopting and submitting to the Department of Environmental Resources for its approval as a revision to the official plan of the Township the Pleasant Hills North planning module
Res. 107-1992
2/3/1992
Adopting and submitting to the Department of Environmental Resources for its approval as a revision to the official plan of the Township the Root Subdivision planning module
Res. 108-1992
2/3/1992
Adopting and submitting to the Department of Environmental Resources for its approval as a revision to the official plan of the Township the Division of Lot 8 Sylvan Acres, Section II, planning module
Res. 111-1992
2/3/1992
Adopting and submitting to the Department of Environmental Resources for its approval as a revision to the official plan of the Township the Brockerhoff Heights II planning module
Res. 112-1992
2/5/1992
Adopting and submitting to the Department of Environmental Resources for its approval as a revision to the official plan of the Township an unnamed planning module for Gary G. Wilt
Res. 122-1992
4/9/1992
Adopting and submitting to the Department of Environmental Resources for its approval as a revision to the official plan of the Township the Spring Corners planning module
Res. 146-1993
3/1/1993
Approving the plans as submitted by Centre Lime & Stone for the sewage planning module for Tract 14 Subdivision
Res. 171-1994
1/3/1994
Adopting and submitting to the Department of Environmental Resources for its approval as a revision to the official plan of the Township the JoAnn Benner Subdivision III planning module
Res. 172-1994
1/3/1994
Adopting and submitting to the Department of Environmental Resources for its approval as a revision to the official plan of the Township the Lutheran Retirement Community at Pleasant Gap planning module
Res. 174-1994
1/3/1994
Adopting and submitting to the Department of Environmental Resources for its approval as a revision to the official plan of the Township the Spring Township Act 537 Sanitary Sewage Facilities Plan
Res. 177-1994
3/7/1994
Adopting and submitting to the Department of Environmental Resources for its approval as a revision to the official plan of the Township the Springfield Phase II planning module
Res. 181-1994
5/11/1994
Approving an agreement with the Spring-Benner-Walker Joint Authority to assist in the collection of delinquent sewer rental payments by termination of public water service provided by the Township to such delinquent customers
Res. 182-1994
6/6/1994
Adopting and submitting to the Department of Environmental Resources for its approval as a revision to the official plan of the Township the Preliminary/Final 3 Lot Subdivision and Lot Addition to Lot 7 in Brockerhoff Heights, Phase I, planning module
Res. 192-1994
12/4/1994
Designating any member of the Board of Supervisors to sign off on the applications for any individual apply for a low interest Pennvest Loan to repair an existing onlot malfunctioning sewer system
Res. 194-1994
10/3/1994
Adopting and submitting to the Department of Environmental Resources for its approval as a revision to the official plan of the Township the Lot Addition and Two Lot Subdivision planning module
Res. 195-1994
12/5/1994
Adopting and submitting to the Department of Environmental Resources for its approval as a revision to the official plan of the Township the M. Donald Shawver Subdivision planning module
Res. 196-1994
12/5/1994
Adopting and submitting to the Department of Environmental Resources for its approval as a revision to the official plan of the Township the Preliminary Subdivision Plan Brockerhoff Heights II, Phase 2 planning module
Res. 203-1995
2/6/1995
Wishing to include Musser Lane in the Act 537 update for sewer service and notifying Mr. George Stallman to update the Comprehensive Plan to include Musser Lane
Res. 206-1995
3/6/1995
Adopting and submitting to the Department of Environmental Resources for its approval as a revision to the official plan of the Township the Hickory Hills, Phase II, planning module
Res. 208-1995
3/6/1995
Declaring no objection to the proposed location of sewer lateral from the Tom Capparelle property to Route 550 main sewer service line, placing the sewer lateral in the Township right-of-way
Res. 209-1995
4/26/1995
Adopting and submitting to the Department of Environmental Resources for its approval as a revision to the official plan of the Township the T.C. Capparelle planning module