A.
General requirement.
(1)
In accordance with the authority granted by § 236.13 of the Wisconsin Statutes, the Village of Howards Grove hereby requires that, as a condition of final plat or certified survey approval, the subdivider agree to make and install to the subdivision boundary lines of all streets to be dedicated, all public improvements required by this chapter and that the subdivider shall provide the Village with security to ensure that the subdivider will make the required improvements. As a further condition of approval, the Village Board hereby requires that the subdivider be responsible for the cost of any necessary alterations of any existing utilities which, by virtue of the platting or certified survey map, fall within the public right-of-way.
(2)
As a condition for the acceptance of dedication of public rights-of-way, the Village requires that the public ways have been previously provided with all necessary facilities constructed to Village specifications and installed to the boundary lines of the subdivision, including, but not limited to, sewerage, storm drainage, grading and improvement of the streets and other public ways, sidewalks, street signing, streetlighting and such other facilities required by the Village Board or that a specific portion of the costs be paid in advance as provided in § 66.0709(2), Wis. Stats.
(3)
The required public improvements shall be installed by the Village at the subdivider's expense. Inspection of the public improvement installation shall be made by the Village Engineer. Cost of the inspection shall be paid by the developer. The Village shall let bids for such projects. The Village may, at its discretion, allow the developer to bid and install the required public improvements at the developer's expense. Inspection by the Village Engineer would still be required, the cost of which would be paid by the developer.
B.
Payment for public improvements.
(1)
Whenever the Village does any of the work required by this chapter, the owner of the area being subdivided shall pay the costs therefor, together with any expenses the Village may incur in connection therewith, including engineering fees. Such payment shall be made as follows:
(a)
One hundred ten percent before the start of the project, based on an estimate of what the total costs will be or actual contract amounts.
(b)
Before the final plat of a subdivision is approved, the subdivider shall agree to pay for the improvements and installation costs as herein required of the subdivider. He shall give satisfactory proof as required by § 408-20 that he has the financial ability to meet these obligations.
(c)
The adequacy of all facilities shall be subject to the approval of the Village Board or its designee.
(2)
By submitting the plat for approval the owner does authorize and consent to the entry against the property, as a special charge, a lien for any delinquencies as to the above required payments and a statement to that effect will be clearly designated upon such plat under the caption: "Notice of Lien."
C.
General standards. The required public improvements shall be installed in accordance with the engineering standards and specifications which have been adopted by the Village Board. Where standards and specifications have not been adopted, the improvements shall be made in accordance with established engineering practices, approved prior to the start of construction by the Village Engineer. When new or revised standards and/or specifications have been adopted by the Village, work on public improvements not begun within five years of the date of final plat adoption shall be made to the new or revised standards and/or specifications. The Village Engineer shall review and approve the construction plans, specifications and calculations for the construction of the required public improvements.