[Ord. 871, 5/22/1991, § 118-501; as amended by Ord. 995, 12/10/2003]
1. 
Permanent concrete or durable stone monuments 30 inches by six inches shall be set at all boundary corners, angle points of boundary, street intersections and such intermediate points as may be required. Bench marks shall be placed on the monuments at all street intersections based on the U.S. Coast and Geodetic Sandy Hook Datum. All lot corners shall be staked and plainly marked with oak or metal pins, where feasible.
2. 
The installation and certification shall be made by a registered professional engineer or a registered surveyor prior to the final approval of the subdivision, consolidation or land development. In lieu of such prior installation, the applicant shall furnish a cash deposit in the form of a certified check to guarantee the proper installation of the required monuments, bench marks and lot pins. The refundable deposit shall be in the amount as established from time to time by resolution of Borough Council per required survey monument.
[Ord. 871, 5/22/1991, § 118-502; as amended by Ord. No. 1075, 11/14/2018]
Each lot shall be served by water and sanitary sewers provided by the developer and constructed in accordance with the design standards of Part 6 and the Borough Construction Standards [Part 9]. Storm sewers and drainage facilities shall be provided by the developer in each plan and shall be constructed in accordance with the Design Standards of Part 6 and the Borough Construction Standards [Part 9]. If required by Chapter 23 of the Borough Code of Ordinances, Stormwater Management, stormwater management facilities shall be constructed by the developer in accordance with Borough Construction Standards [Part 9] and Chapter 23 of the Borough Code of Ordinances.
[Ord. 871, 5/22/1991, § 118-503]
The developer shall be responsible for contracting with private utility companies and for providing any easements required by those utility companies to guarantee that each lot shall be served by telephone, gas and/or electricity.
[Ord. 871, 5/22/1991, § 118-504]
Each lot shall front on a street improved to Borough Construction Standards [Part 9] and the Design Standards of Part 6 of this chapter.
[Ord. 871, 5/22/1991, § 118-505]
1. 
Sidewalks shall be required to be installed by the developer under the following circumstances:
A. 
Where sidewalks exist in the same block on the same side of the street.
B. 
Along the full frontage of lots located on arterial or collector streets, as defined by this chapter.
C. 
Within a land development plan proposed to be developed for multifamily residences.
D. 
Within a land development plan proposed to be developed for commercial or industrial use.
2. 
Sidewalks shall be installed in accordance with the Design Standards of Part 6 of this chapter and the Borough Construction Standards [Part 9].
[Ord. 871, 5/22/1991, § 118-506]
For the safety and convenience of the public, the developer shall install street lights of a type approved by the Borough and on poles prescribed by the Borough on all public and private streets. Installation shall be in accordance with the Borough Construction Standards [Part 9]. The cost of the lights, poles and installation shall be assumed by the developer.
[Ord. 871, 5/22/1991, § 118-507]
The developer shall install street name signs, approved by the Borough, at all street intersections. The cost of the street signs and posts shall be assumed by the developer. Street signs shall be installed in accordance with the Borough Construction Standards [Part 9].
[Ord. 871, 5/22/1991, § 118-508]
At the time of construction or reconstruction of curbs and/or sidewalks at any intersection in the Borough, the developer shall provide lowered curbs to facilitate accessibility for the handicapped in accordance with the specifications contained in the Borough Construction Standards [Part 9].