[Ord. 722, 2/19/2015]
The Township Manager or his designee is hereby appointed to
administer and enforce this chapter and is referred to herein as the
"floodplain administrator." In the absence of a designated floodplain
administrator, the floodplain administrator duties are to be fulfilled
by the Assistant Township Manager.
[Ord. 722, 2/19/2015]
A floodplain permit shall be required before any construction
or development is undertaken within any identified floodplain area
of Warminster Township.
[Ord. 722, 2/19/2015]
A copy of all plans and applications for any proposed construction
or land development in any Identified floodplain area to be considered
for approval shall be submitted by the floodplain administrator to
any other appropriate agencies and/or individuals (e.g., county conservation
district, planning commission, municipal engineer, etc.) for review
and comment.
[Ord. 722, 2/19/2015]
After the issuance of a floodplain permit by the floodplain
administrator, no changes of any kind shall be made to the application,
permit or any of the plans, specifications or other documents submitted
with the application without the written consent or approval of the
floodplain administrator. Requests for any such change shall be in
writing, and shall be submitted by the applicant to the floodplain
administrator for consideration.
[Ord. 722, 2/19/2015]
In addition to the floodplain permit, the floodplain administrator
shall issue a placard which shall be displayed on the premises during
the time construction is in progress. This placard shall show the
number of the floodplain permit, the date of its issuance, and be
signed by the floodplain administrator.
[Ord. 722, 2/19/2015]
Applicants for a floodplain permit shall, at the time of making
application, pay to Warminster Township, a fee in accordance with
a fee schedule adopted by resolution of the Board of Supervisors upon
enactment of this chapter or as such schedule may be amended by resolution
of the Board of Supervisors.