Exciting enhancements are coming soon to eCode360! Learn more 🡪
Township of North Newton, PA
Cumberland County
By using eCode360 you agree to be legally bound by the Terms of Use. If you do not agree to the Terms of Use, please do not use eCode360.
The Board of Supervisors requires that all driveways and roadways be designed to accommodate the amount and type of traffic they will serve considering the type and character of the roadway that the driveway or roadway will access.
A. 
Purpose.
(1) 
These guidelines detail the procedures to be utilized when conducting a traffic impact study for a proposed site development which is expected to impact traffic operations on a Township roadway. Such studies are necessary to define the possible magnitude of the impact(s) of the proposed development on the traffic operations of the affected Township roadway(s) and determine improvements necessary to provide for accommodation of the traffic due to the proposed development.
(2) 
Studies to be conducted under these guidelines are separate from any other requirements which the municipality may have in regards to traffic impact analysis or Act 209/1990 requirements.[1]
[1]
Editor's Note: See 53 P.S. § 10501-A et seq.
B. 
Determining the need for a traffic impact study.
(1) 
Traffic impact studies are conducted to enable the Board of Supervisors to identify the potential impacts of a proposed development and determine any roadway improvements necessary to provide an acceptable level of service. These studies are to be conducted during the initial stages of the site development review and approval process in order to adequately consider the impacts the development will have on the local transportation network.
(2) 
Not all developments will have a significant enough impact to require a traffic impact study. The use of engineering judgement is necessary in making this determination and consideration should be given not only to changes in projected traffic volume but also safety or capacity deficiencies which could impact the roadway system.
(3) 
In all cases, a traffic impact study will be conducted when, in the opinion of the Board, the site development is expected to have a significant impact on the safety and/or traffic flow of the affected roadway(s).
(4) 
A traffic impact study shall be submitted along with subdivision or land development plans when any one of the following conditions exist or are created by the proposed subdivision or land development.
(a) 
The proposed development is expected to generate 400 or more vehicle trips per day (total inbound and outbound development traffic).
(b) 
The proposed development is expected to generate traffic flow which will be comprised of greater than 15% by aggregate, of trucks, buses and RV vehicles. This maximum percentage of trucks, buses and RVs will apply whether or not the development is expected to generate 400 vehicle trips per day (total inbound and outbound).
(c) 
The total traffic flow on the adjoining roadway will exceed 250 vehicles per hour during the adjoining roadway's peak hour, and 25 or more of the vehicles are newly generated peak direction trips to or from the site.
(d) 
Residential, commercial and industrial subdivisions shall estimate the expected vehicle trips based upon complete build-out of the subdivision, including all existing and future phases of the development.
C. 
Preparation of the study.
(1) 
When it has been determined that a traffic impact study is required for a proposed site development, it shall be the responsibility of the developer to ensure the study is conducted and a final report submitted in accordance with these guidelines. The traffic impact study and final report shall be prepared under the supervision of a registered professional engineer who possesses a current license issued by the Pennsylvania State Registration Board for Professional Engineers. The final traffic impact study report must have the seal and signature of the supervising engineer on it when submitted.
(2) 
The conduct of the traffic impact study must be in cooperation with and coordinated with the appropriate state and local officials. Of special importance is the need to work closely with the involved municipal officials in determining the improvements which are to be implemented on the affected roadway(s). Where the recommended improvements will require a commitment from the municipality for continued maintenance and/or operation, such as with traffic signals, the report should indicate a commitment from the developer to accept these responsibilities.
D. 
Study procedures.
(1) 
General requirements.
(a) 
The traffic impact study will be conducted using currently accepted traffic engineering practices and procedures. The use of computer programs to conduct the required analyses is acceptable; provided, the programs reflect the most current provisions of the analysis procedures upon which they are based. Recommended geometric or traffic operations improvements must meet or exceed all applicable state and/or local minimum design criteria.
(b) 
The study engineer will be responsible for the collection of all information and data required to support the study effort. When traffic counts are required for the study, the study engineer shall collect such data to include peak-hour turning movements on an average day as defined in the PA Department of Transportation's Publication 201.
(c) 
The procedures and requirements outlined in these guidelines are intended to provide a basic framework for the conduct of a traffic impact study. Additions or modifications to this framework may be made, provided such changes are approved by the Township.
(2) 
Study area characteristics.
(a) 
The limits for the study area should be based upon engineering judgement and a knowledge of the existing traffic conditions in the vicinity of the proposed site development. The area must be of sufficient size to include the key roadway corridors and critical intersections which may be impacted by the proposed site traffic.
(b) 
Existing and proposed land uses in the study area must be considered in the study. Where the current/proposed land use of the site is being modified, an analysis of the proposed changes should be made to determine the extent to which traffic volumes for the site must be modified.
(c) 
Characteristics of the study area roadway network, intersections and the proposed site access point(s) to include geometries and traffic control need to be identified as part of the study. Included in this identification will be all driveways adjacent to or across from the proposed site access point(s).
(3) 
Traffic analysis.
(a) 
The study area roadway network is to be analyzed for safety and capacity sufficiency for three separate conditions: existing network conditions, future network conditions without the proposed development, and future network conditions with the proposed development. For each of the three conditions, the following analyses shall be completed:
[1] 
Mainline ADT volumes and turning movement volumes for all critical intersections within the study area will be determined for the a.m. peak hour, p.m. peak hour and the proposed development peak hour if other than either the a.m. or p.m. peak hour of the network.
[2] 
The effectiveness of the traffic signal control at all critical intersections will be evaluated by approach in terms of vehicle stops and delays.
[3] 
Gap studies will be conducted at the proposed site access points to evaluate the need for signal control, turn prohibitions or additional site access points to reduce the left turn volume from the site driveway(s).
[4] 
Queue length studies will be completed to evaluate the potential for a backup of traffic from controlled intersections which could impact other intersections, including access points to the proposed development.
[5] 
An analysis of the volume and capacity of the network and all critical intersections will be conducted utilizing the most current Highway Capacity Manual procedures. Levels of service will be determined and documented.
(b) 
The analysis of the existing roadway and intersection conditions in the study area will be based upon the current geometric conditions and traffic control operations. This analysis will serve as a basis for determining the current adequacy of the roadway network and to document any deficiencies.
(c) 
The analysis of the future conditions without the proposed development will document the adequacy of the study area network to accommodate traffic in the design year(s) without the proposed development. This analysis must include a full consideration of all committed roadway improvements to the study area network when determining the expected levels of service. For the analysis of the future conditions with the proposed development, one of the key factors will be the development of the projected site generated traffic and its distribution on the study area network. The study preparer must fully document the methodology which was used to complete this effort and provide sufficient information such that the Board can verify the results. In addition, care must be taken to ensure that adequate consideration is given to that portion of the already projected future network traffic which will utilize the proposed development access points. (Failure to account for this "captured" traffic will result in a "double counting" of a portion of the future traffic.)
(4) 
Improvement recommendations.
(a) 
The overall goal of this section will be to detail necessary improvements to the study area roadway network which will provide for a level of service for the design year(s) with the development which is at least equivalent to the projected level of service for the design year(s) without the proposed development. Based upon a comparison of the traffic analysis for the future conditions with and without the proposed development, roadway and traffic operational improvements which will support this goal are to be identified and analyzed. These improvements may include both on-site and off-site roadway and traffic operational changes as determined by the preceding analyses.
(b) 
In developing the proposed improvements, the study preparer is to consider the following:
[1] 
All roadway capacity evaluations shall consider not only the overall intersection level of service and delay but also evaluate each approach and movement to identify any substandard values which need to be improved.
[2] 
For locations where the level of service of the design year without the proposed development is F, the improvements shall provide an estimated delay which will be no worse than the delay for the design year without the proposed development.
[3] 
Where new intersections are being established to serve as access to the proposed development, these intersections must be designed to at least operate at level of service C or better (rural conditions) or level of service D or better (urban conditions).
[4] 
For access points to the proposed development which are not proposed to be controlled by a traffic signal, an analysis will be completed to determine the design details for a separate left turn lane on the adjoining highway.
[5] 
For access points to the proposed development where traffic signal control is being proposed, a traffic signal warrant analysis shall be performed in accordance with the requirements of the PA Department of Transportation's Publication 201. Although a left turn lane shall be provided, an analysis shall be completed to determine the type of signal phasing required.
(c) 
The final recommended study area network with proposed improvements will also be subjected to all the traffic analyses which are required under the previous section of these guidelines. These analyses will serve to document the "adequacy" of the improvements.
E. 
Final report.
(1) 
General.
(a) 
A final report must be prepared to document the results of the traffic impact study and the recommended improvements to accommodate the projected traffic due to the proposed development. Since this report will be reviewed by officials with varying levels of technical expertise, the report must be presented in a format and context which can be understood by both technical and nontechnical parties.
(b) 
The presentation of data and analyzes results should, preferably, be accomplished on either schematic diagrams of the study area, or through the use of charts and/or tables. All sources of data and methodologies which were used in the study (including computer programs) must be properly referenced, and procedures must be properly documented to enable a review of the appropriateness of the modification.
(2) 
Contents. The final report will include the following:
(a) 
Executive summary which provides a concise description of the study area, results of the traffic analyses and any recommended improvements.
(b) 
Description of the proposed development site to include a map showing the sites location in regards to the region and the area roadway network.
(c) 
Schematic diagram/map of the designated study area showing all major roadways and critical intersections.
(d) 
Results of the traffic analyses for the three traffic conditions. At a minimum, the following data must be shown for each of the three conditions:
[1] 
Mainline ADT and intersection turning movement counts.
[2] 
Levels of service.
[3] 
Projected traffic distribution and network assignment for the proposed site.
[4] 
Recommended improvements to the study area network to include preliminary cost estimates, proposed implementation schedule and expected levels of service for the recommended network.
The general principles of design and the minimum requirements for the laying out of subdivisions and land developments stipulated in this chapter may be varied by the Board of Supervisors in the case of a project large enough to constitute self-contained neighborhood, industrial park or commercial center. Such a project shall be developed in accordance with a Comprehensive Plan which, in the judgement of the Board, has made adequate provisions for all essential requirements. Provided, however, that no modification shall be granted by the Board which would conflict with features of any adopted long-range plan of the Township or with the intent and purpose of the general principles of design of this chapter. Any request for an exemption shall be in writing and shall satisfactorily set forth the reasons therein.