A.
The Borough shall inspect all phases of the installation of the best
management practices (BMPs) and/or stormwater management (SWM) facilities
as deemed appropriate by the Borough.
B.
During any stage of the work, if the Borough determines that the
BMPs and/or stormwater management facilities are not being installed
in accordance with the approved SWM site plan, the Borough shall revoke
any existing permits or other approvals and issue a cease and desist
order until a revised SWM site plan is submitted and approved as specified
in this chapter and until the deficiencies are corrected.
C.
A final inspection of all BMPs and/or stormwater management facilities
may be conducted by the Borough to confirm compliance with the approved
SWM site plan prior to the issuance of any occupancy permit.
D.
The applicant and/or developer shall be responsible for providing
as-built plans of all SWM BMPs included in the approved SWM site plan.
The as-built plans and an explanation of any discrepancies which were
reviewed and received approval by the Borough shall be submitted to
the Borough.
E.
The as-built submission shall include a certification of completion
signed by a qualified professional verifying that all SWM BMPs have
been constructed according to the approved plans and specifications.
If any qualified professionals contributed to the construction plans,
they must sign and seal the completion certificate.