[Ord. 00030, 7/11/2005, § 601]
Public Sanitary Sewer Systems. All subdivision or land development is to be provided with a complete public sanitary sewer system connected to Akron Borough sewer system. A statement of approval from the engineer of the sewage system to which it will be connected shall be submitted to Akron Borough. Where required, a DEP planning module approval shall also be obtained for final plan approval.
[Ord. 00030, 7/11/2005, § 602]
1. 
Provision of System. The subdivision or land development shall be provided with a complete public water main supply system, which shall be connected to Akron Borough municipal water supply system.
2. 
Plans. The plans for the installation of the mains of a water supply system shall be prepared for the subdivision or land development and approved by the Borough Engineer. Upon the completion of the water supply system, one copy of the as built plans for such system shall be filed with Akron Borough.
3. 
Fire Hydrants. Fire hydrants shall be provided as an integral part of any public water supply system. Fire hydrants shall be placed so that all proposed building(s) will be no more than 500 feet from a hydrant measured along traveled ways.
[Ord. 00030, 7/11/2005, § 603]
1. 
Easements for utilities shall have a minimum width of 30 feet, with easement access identified.
2. 
To the fullest extent possible, easements for public facilities shall be centered on or adjacent to rear or side lot lines.
3. 
Water, sewer, telephone, electric, TV cable and such other utilities shall be installed underground and shall be provided within the street right-of-way, and whenever possible out of the cartway or in easements to be dedicated for such facilities, and in accordance with plans approved by the Akron Borough and the applicable facility company. Underground installation of the facility distribution and service lines shall be completed prior to street paving, gutter, curbing, and sidewalk installation.
[Ord. 00030, 7/11/2005, § 604]
1. 
Monuments shall be of concrete or stone at least six inches by six inches by 30 inches and marked on top with a copper or brass dowel. They shall be set at the intersection of lines forming angles in the boundaries of the subdivision and at the intersection of street lines. Markers shall be iron pipes or brass 30 inches by 3/4 inch diameter and set at all points where lines or lines and curves intersect.
2. 
Monument Replacement. Any monuments or markers that are removed must be replaced by a registered land surveyor at the expense of the person responsible for the removal.
[Ord. 00030, 7/11/2005, § 605; as amended by Ord. 00077, 4/14/2014, § 13]
1. 
Street name signs, speed limit signs, directional signs, stop signs, no parking signs, street striping, and any other street safety improvement conforming to PennDOT specifications shall be provided and installed by the subdivider or developer for all streets.
2. 
As-Built Plan. At such time as the construction of the improvements is found to meet all requirements of this chapter and the approved plans, as modified, the developer, prior to offering the improvements for dedication, shall submit to the Borough a Mylar and an electronic version of the as-built plan of the improvements which shall form a part of the permanent records of the Borough. The plan shall be prepared by using the approved final plan as a base plan. As-built plans shall show the following:
A. 
Location of all concrete monuments which were set at all angle breaks, points of curvature and tangents around the perimeter of the total tract. When the outside perimeter of a tract falls within or along an existing road right-of-way, then the right-of-way of that roadway shall be monumented at the above referenced points.
B. 
Location of all iron pins or drill holes within the street right-of-way for all individual lot lines.
C. 
Location of cartway center line versus right-of-way center line.
D. 
Location of floodplain by elevation and dimension from property line.
E. 
Location and cross section of swales and accompanying easements.
F. 
Horizontal and vertical location of stormwater management, sanitary sewer, and waterline facilities including type and size of storm drainage, sanitary, and waterline pipes.
G. 
Location of buildings, parking lots, and driveways for land development plans.
H. 
Detention basin:
(1) 
Contours of the detention basin.
(2) 
Outlet structure details including type, size and inverts of outlet pipes and orifice.
(3) 
Elevation of the top of embankment and emergency spillway.
(4) 
A table showing the stage/storage/discharge curve for the constructed conditions.
3. 
Other improvements to promote public safety and health as required by Akron Borough as a condition of approval.
4. 
All plans, including, but not limited to, all subsequent as-built plans, shall comply with the SWMO [Chapter 17].
[Ord. 00030, 7/11/2005, § 606]
At the time each improvement is to be installed and upon its completion, the subdivider shall notify the Borough Zoning Officer so that adequate inspections can be made. The inspection will be made by the Akron Borough Engineer. All costs of undertaking the inspection will be borne by the subdivider.
[Ord. 00030, 7/11/2005, § 607]
Completion of improvements or guarantee thereof is a prerequisite to final plat approval and shall be accomplished in conformance with Pennsylvania Municipalities Planning Code provisions in effect at that time.
[Ord. 00030, 7/11/2005, § 608]
Release of improvement bonds shall be accomplished in conformance with the Pennsylvania Municipalities Planning Code provisions in effect at that time.
[Ord. 00030, 7/11/2005, § 609]
Remedies to effect completion of improvements shall be in conformance with the Pennsylvania Municipalities Planning Code.