[Ord. No. 5.503 § 1, 12-3-1990; Ord. No. 2005-07-25-04 § 1, 7-25-2005]
No person, company, association or corporation shall within the corporate limits of the City of Greenwood, Missouri, conduct, exercise, carry on, deal in or engage in the opening or excavation or any incident thereto, in a street or alley within the corporate limits of the City of Greenwood, without first having applied to the City Clerk for a permit for permission to engage in said practice.
[Ord. No. 5.503 § 2, 12-3-1990; Ord. No. 2005-07-25-04 § 1, 7-25-2005]
When said permit is granted, said person, company, association or corporation shall pay to the City Clerk the sum of thirty-five dollars ($35.00) for said permit application fee plus administrative, inspection and right-of-way management fees. Said permit shall be operative and in effect only when said applicant shall post with the City Clerk a cash bond as determined by the City Engineer per Section 510.200. The bond shall be returned only after City inspection, if required, and when the street is repaired to its original condition.
[Ord. No. 5.503 § 3, 12-3-1990; Ord. No. 2005-07-25-04 § 1, 7-25-2005]
Repair of any alley or street cut shall conform to standards set forth in this Article. Existing pavement shall be saw cut to a clean line. Backfill requirements shall be per APWA 2602.3.C specifications. Flowable fill shall have a twenty-eight-day compressive strength less than one hundred (100) psi. MoDOT type 5 aggregate may be substituted for all flowable fill if aggregate certification is delivered with the material. Prior to asphalt paving, all adjacent pavement surfaces shall be clean and tacked with emulsion per APWA 2204 specifications. Asphalt pavement shall be replaced per detail in Section 510.100. Final surface of the patched area shall neither impede nor collect surface water.
[Ord. No. 5.503 § 4, 12-3-1990; Ord. No. 2005-07-25-04 § 1, 7-25-2005]
If the applicant as above described shall fail at any time to repair the street or alley so disturbed or excavated within three (3) days after notification by the City Inspector, City Engineer or his/her designated agent or representative, the bond and monies deposited with the City Clerk shall be deemed forfeited and the City with the use of said monies shall make the necessary repairs.
[Ord. No. 5.503 § 5, 12-3-1990; Ord. No. 2005-07-025-04 § 1, 7-25-2005]
The person, company, association or corporation applying for said permit and same having been granted, shall, during all times of construction and in the operation of any work incidental to the granting of the permit and until such time as same has been approved, have the responsibility and the duty and shall in said respect hold the City of Greenwood harmless from said duty for the erection, maintenance and attention of all necessary barricades, flares and supervision of said construction in accordance with the Manual of Uniform Traffic Control Devices.
[Ord. No. 5.503 § 6, 12-3-1990; Ord. No. 2005-07-25-04 § 1, 7-25-2005]
A violation of this Article will be construed and is hereby deemed a misdemeanor and anyone violating same shall be punished by a fine not to exceed one hundred dollars ($100.00).
[Ord. No. 5503, Exhibit A, 12-3-1990; Ord. No. 2005-07-25-04 § 1, 7-25-2005]
510a Street Cut Repair.tif
Notes:
1. City right-of-way permit shall be on site at all times.
2. Contractor shall contact City Hall for inspection prior to placing filter fabric and again prior to placing asphalt.
3. The one (1) foot step cut on either side of original trench shall not be removed until backfill has been placed and compacted.
4. All street cuts shall be backfilled and compacted to ninety-eight percent (98%) of standard density and reconstructed matching the original street section with exception that not less than six (6) inches of asphalt will be allowed in any instance. Asphalt pavement shall be a minimum of four inch Type I base and two inch Type III surface. The Type I base shall be placed and compacted in individual lifts, not exceeding four (4) inches.
5. Asphalt shall comply with APWA specifications as follows:
Type I — Base Course
Type III — Surface Course
6. Contractor shall provide and maintain traffic control devices per the Manual on Uniform Traffic Control Devices (MUTCD).
7. All grass areas disturbed during construction shall be fertilized, seeded and mulched, prior to release of surety.