[Ord. No. 338, 1/10/2011]
1. PADEP or its designees normally ensure compliance with any permits
issued, including those for stormwater management. In addition to
PADEP compliance programs, Elizabethville Borough or its assignee
may inspect all phases of the installation of temporary or permanent
stormwater management facilities.
2. During any stage of earth disturbance activities, if the municipality
determines that the temporary or permanent stormwater management facilities
are not being installed in accordance with the approved SWM site plan,
Elizabethville Borough shall revoke any existing permits or approvals
until a revised SWM site plan is submitted and approved as specified
in this chapter.
3. Stormwater BMPs shall be inspected by the landowner, or the landowner's
designee, according to the inspection schedule described on the SWM
site plan for each BMP.
A. Elizabethville Borough may require copies of the inspection reports,
in a form as stipulated by Elizabethville Borough.
B. If such inspections are not conducted or inspection reports not submitted
as scheduled, Elizabethville Borough, or its designee, may conduct
such inspections and charge the owner appropriate fees. Nonpayment
of fees may result in a lien against the property.
(1)
Prior to conducting such inspections, Elizabethville Borough
shall inform the owner of its intent to conduct such inspections.
The owner shall be given 30 days to conduct required inspections and
submit the required inspection reports to the Borough.
[Ord. No. 338, 1/10/2011]
1. Upon presentation of proper credentials, duly authorized representatives
of Elizabethville Borough may enter at reasonable times, upon any
property within the Borough, to inspect the implementation, condition,
or operations and maintenance of the stormwater BMPs in regard to
any aspect governed by this chapter.
2. Stormwater BMP owners and operators shall allow persons working on
behalf of Elizabethville Borough ready access to all parts of the
premises for the purposes of determining compliance with this chapter.
3. Persons working on behalf of Elizabethville Borough shall have the
right to temporarily locate on any stormwater BMP in the Borough such
devices as are necessary to conduct monitoring and/or sampling of
the discharges from such stormwater BMP.
4. Unreasonable delay in allowing the Borough access to a stormwater
BMP is a violation of this chapter.