[Ord. No. 11/9/1977, § 1]
1.
All construction, materials and workmanship shall be in accordance with the Pennsylvania Department of Transportation, Form 408, latest edition, and shall be subject to review and approval by the Township and Township Engineer.
2.
All work including grading, drainage, and paving shall be under the direct supervision of the Township Engineer or his authorized representative, and all costs for supervision shall be paid by the owner/developer prior to final acceptance by the Township.
3.
A performance bond in the amount of 100% of the construction cost shall be delivered to the Township prior to the beginning of construction.
4.
The owner/developer shall provide the Township with a one-year maintenance bond for 10% of the construction costs of the project as surety against defective materials or workmanship which may develop during the one-year period after completion and acceptance of the work performed.
5.
The contractor must submit to the subdivider and/or developer weight slips for all materials, which will in turn be transferred to the Township Supervisors.
6.
The owner shall furnish record plans of all streets as actually constructed for the files of the Forward Township Supervisors, the cost of this to be paid by the owner/subdivider/developer.