The fee required by this chapter is the Township review fee. The Township review fee shall be established by resolution of the Board of Supervisors of Lower Paxton Township to defray review costs incurred by the Township and the Township Engineer. The applicant shall pay all fees.
A. 
The fees required by this chapter shall, at a minimum, cover:
(1) 
Administrative and clerical costs.
(2) 
Review of the SWM site plan and report by the Township.
(3) 
Preconstruction meetings.
(4) 
Inspection of stormwater management facilities/BMPs and drainage improvements during construction.
(5) 
Final inspection upon completion of the stormwater management facilities/BMPs and drainage improvements presented in the SWM site plan.
(6) 
Any additional work required to enforce any permit provisions regulated by this chapter, correct violations, and assure proper completion of stipulated remedial actions.
A. 
The owner of any land upon which permanent BMPs will be placed, constructed, or implemented, as described in the SWM site plan, shall record the following documents in the office of the Recorder of Deeds of Dauphin County, within 30 days of approval of the SWM site plan by the Township and shall produce a recording receipt to the Township prior to the issuance of a storm water management permit:
(1) 
The SWM site plan.
(2) 
Operations and maintenance (O&M) agreement (Appendix A).
(3) 
Easements under § 170-701.
B. 
Lower Paxton Township may suspend or revoke any approvals granted for the project site upon discovery of the failure of the owner to comply with this section.