A.
For subdivisions
and land developments the applicant shall provide a financial guarantee
to the Township of Muhlenberg for the timely installation and proper
construction of all stormwater management controls as:
B.
For other regulated
activities, the Township of Muhlenberg may require a financial guarantee
from the applicant.
C.
At the completion
of the project and as a prerequisite for the release of the performance
guarantee, the applicant or his representatives shall:
D.
After the Township
of Muhlenberg receives the certification, a final inspection shall
be conducted by the Township Engineer or designee to certify compliance
with this chapter.
It shall be unlawful to alter or remove any
permanent stormwater control and BMP required by an approved stormwater
control and BMP operations and maintenance plan or to allow the property
to remain in a condition which does not conform to an approved stormwater
control and BMP operations and maintenance plan.
A.
The property
owner shall sign an operations and maintenance agreement with the
Township of Muhlenberg covering all stormwater controls and BMPs that
are to be privately owned. The agreement shall be substantially the
same as the agreement in Appendix A of this chapter.[1]
[1]
Editor's Note: Appendix A is included as an
attachment to this chapter.
B.
Other items may
be included in the agreement where determined necessary to guarantee
the satisfactory operation and maintenance of all permanent stormwater
controls and BMPs. The agreement shall be subject to the review and
approval of the Township of Muhlenberg.
A.
Stormwater management
easements are required for all areas used for off-site stormwater
control, unless a waiver is granted by the Commissioners of the Township
of Muhlenberg with recommendation by the Planning Commission.
B.
Stormwater management easements shall be provided by the property owner if necessary for access for inspections and maintenance or preservation of stormwater runoff conveyance, infiltration and detention areas and other stormwater controls and BMPs by persons other than the property owner. The purpose of the easement shall be specified in any agreement under § 297-35.
A.
The owner of
any land upon which permanent stormwater controls and BMPs will be
placed, constructed or implemented, as described in the stormwater
control and BMP operations and maintenance plan, shall record the
following documents in the office of the Recorder of Deeds for Berks
County within 15 days of approval of the stormwater control and BMP
operations plan by the Commissioners of the Township of Muhlenberg:
B.
The Commissioners
of the Township of Muhlenberg may suspend or revoke any approvals
granted for the project site upon discovery of the failure of the
owner to comply with this section.
A.
Persons installing
stormwater controls or BMPs shall be required to pay a specified amount
to the Municipal Stormwater Control and BMP Operation and Maintenance
Fund to help defray costs of periodic inspections and maintenance
expenses. The amount of the deposit shall be determined as follows:
(1)
If the stormwater
control or BMP is to be privately owned and maintained, the deposit
shall cover the cost of periodic inspections performed by the Township
of Muhlenberg for a period of 10 years, as estimated by the Township
Engineer. After that period of time, inspections will be performed
at the expense of the Township of Muhlenberg.
(2)
If the stormwater
control or BMP is to be owned and maintained by the Township of Muhlenberg,
the deposit shall cover the estimated costs for maintenance and inspections
for 10 years. The Township Engineer will establish the estimated costs
utilizing information submitted by the applicant.
(3)
The amount
of the deposit to the fund shall be converted to present worth of
the annual series values. The Township Engineer shall determine the
present worth equivalents, which shall be subject to the approval
of the Commissioners of the Township of Muhlenberg.
B.
If a stormwater
control or BMP is proposed that also serves as a recreation facility
(e.g., ball field, lake), the Commissioners of the Township of Muhlenberg
may reduce or waive the amount of the maintenance fund deposit based
upon the value of the land for public recreation purpose.
C.
If at some future
time a stormwater control or BMP (whether publicly or privately owned)
is eliminated due to the installation of storm sewers or other storage
facility, the unused portion of the maintenance fund deposit will
be applied to the cost of abandoning the facility and connecting to
the storm sewer system or other facility. Any amount of the deposit
remaining after the costs of abandonment are paid will be returned
to the depositor.
D.
If stormwater
controls or BMPs are accepted by the Commissioners of the Township
of Muhlenberg for dedication, the Commissioners of the Township of
Muhlenberg may require persons installing stormwater controls or BMPs
to pay a specified amount to the Municipal Stormwater Control and
BMP Operation and Maintenance Fund to help defray costs of operations
and maintenance activities. The amount may be determined as follows:
(1)
If the stormwater
control or BMP is to be owned and maintained by the Township of Muhlenberg,
the amount shall cover the estimated costs for operations and maintenance
for 10 years, as determined by the Commissioners of the Township of
Muhlenberg.
(2)
The amount
shall then be converted to present worth of the annual series values.
E.
Long-term maintenance.
The Commissioners of the Township of Muhlenberg shall require applicants
to pay a fee to the Municipal Stormwater Maintenance Fund to cover
long-term maintenance of stormwater control and best management practices.
F.
Stormwater-related
problems. The Commissioners of the Township of Muhlenberg may require
applicants to pay a fee to the Municipal Stormwater Maintenance Fund
to cover stormwater-related problems which may arise from the land
development and earth disturbance. The Township Engineer will establish
the estimated cost, utilizing information submitted by the applicant.