Observation #1
|
Initial Center Line Staking and Grading
|
Observation #2
|
Clearing and Grubbing Operations, Erosion Controls
|
Observation #3
|
Earthwork Operations, Fire Tank Excavation and Installations,
and Detention Ponds
|
Observation #4
|
Storm Drainage Systems, Public Sewer Systems, and Public Utilities
|
Observation #5
|
Retaining Wall Construction
|
Observation #6
|
Roadway Subgrade Operations
|
Observation #7
|
Sub-base Courses
|
Observation #8
|
Base Course
|
Observation #9
|
Stone Seal (as may be required)
|
Observation #10
|
Surface Course
|
Observation #11
|
Landscaping, Trees, and Shrubs
|
Observation #12
|
As-Builts, Bounds, Final Grading
|