This Zoning Ordinance shall not apply to structures or uses lawfully in existence or lawfully begun, or to a building or special permit issued before the first publication of notice of the public hearing required by MGL c. 40A, § 5 at which this Zoning Ordinance, or any relevant part thereof, was adopted. Such prior, lawfully existing nonconforming uses and structures may continue, provided that no modification of the use or structure is accomplished, unless authorized hereunder.
The Board of Appeals may award a special permit to change a nonconforming use in accordance with this article only if it determines that such change or extension shall not be substantially more detrimental than the existing nonconforming use to the neighborhood. The following types of changes to nonconforming uses may be considered by the Board of Appeals:
A. 
Change from one nonconforming use to another, less detrimental nonconforming use.
[Amended eff. 8-6-2004 by Ord. No. 775]
A. 
Nonconforming single- and two-family residential structures may be reconstructed, extended, altered or structurally changed upon a determination by the Building Commissioner that such proposed reconstruction, extension, alteration or change does not increase the nonconforming nature of said structure. The following circumstances shall not be deemed to increase the nonconforming nature of said structure:
(1) 
Alteration to a structure located on a lot with insufficient area which complies with all current setback, yard, building coverage and building height requirements.
(2) 
Alteration to a structure located on a lot with insufficient frontage which complies with all current setback, yard, building coverage, and building height requirements.
(3) 
Alteration to a structure which encroaches upon one or more required yard or setback areas, where the alteration will comply with all current setback, yard, building coverage and building height requirements.
B. 
In the event that the Building Commissioner determines that the nonconforming nature of such structure would be increased by the proposed reconstruction, extension, alteration or change, the Board of Appeals may, by special permit, allow such reconstruction, extension, alteration or change where it determines that the proposed modification will not be substantially more detrimental than the existing nonconforming structure to the neighborhood.
The Board of Appeals may award a special permit to reconstruct, extend, alter or change a nonconforming structure in accordance with this article only if it determines that such reconstruction, extension, alteration or change shall not be substantially more detrimental than the existing nonconforming structure to the neighborhood. The following types of changes to nonconforming structures may be considered by the Board of Appeals:
A. 
Reconstructed, extended or structurally changed.
B. 
Altered to provide for the same purpose in a substantially different manner or to a substantially greater extent.
Except as provided in § 9.3 above, the reconstruction, extension or structural change of a nonconforming structure in such a manner as to increase an existing nonconformity or create a new nonconformity, including the extension of an exterior wall at or along the same nonconforming distance within a required yard, shall require the issuance of a special permit from the Board of Appeals.
A nonconforming use or structure that has been abandoned, or not used for a period of two years, shall lose its protected status and be subject to all of the provisions of this Zoning Ordinance.
A nonconforming structure may be reconstructed after a catastrophe or after demolition in accordance with the following provisions:
A. 
Reconstruction of said premises shall commence within two years after such catastrophe or demolition.
B. 
The building(s), as reconstructed, shall be located on the same footprint as the original nonconforming structure, shall be only as great in volume or area as the original nonconforming structure, and shall meet all applicable requirements for yards, setbacks and height.
C. 
A special permit shall be required from the Board of Appeals prior to such demolition in the event that the proposed reconstruction would:
(1) 
Cause the structure to exceed the volume or area of the original nonconforming structure; or
(2) 
Exceed applicable requirements for yards, setbacks and/or height; or
(3) 
Cause the structure to be located other than on the original footprint.
No nonconforming use shall, if changed to a conforming use, revert to a nonconforming use.
In the instance where the special permit granting authority believes that the magnitude of the proposed use or structure is such as to require special expertise, the SPGA may retain an outside individual or firm to aid it in ensuring compliance with the requirements of the Zoning Ordinance of the City of Methuen. The cost of such review shall be borne in full by the applicant seeking the extension of the nonconformity.