The Town Board of the Town of Wales finds that the potential
and/or actual damages from flooding and erosion may be a problem to
the residents of the Town of Wales and that such damages may include
destruction or loss of private and public housing, damage to public
facilities, both publicly and privately owned, and injury to and loss
of human life. In order to minimize the threat of such damages and
to achieve the purposes and objectives hereinafter set forth, this
chapter is adopted.
Unless specifically defined below, words or phrases used in
this chapter shall be interpreted so as to give them the meaning they
have in common usage and to give this chapter its most reasonable
application.
ACCESSORY STRUCTURE
A structure used solely for parking (two-car detached garages
or smaller) or limited storage, represent a minimal investment of
not more than 10% of the value of the primary structure, and may not
be used for human habitation.
APPEAL
A request for a review of the Local Administrator's
interpretation of any provision of this chapter or a request for a
variance.
AREA OF SHALLOW FLOODING
A designated AO, AH or VO Zone on a community's Flood
Insurance Rate Map (FIRM) with a 1% or greater annual chance of flooding
to an average annual depth of one to three feet where a clearly defined
channel does not exist, where the path of flooding is unpredictable
and where velocity flow may be evident. Such flooding is characterized
by ponding or sheet flow.
AREA OF SPECIAL FLOOD HAZARD
The land in the floodplain within a community subject to
a 1% or greater chance of flooding in any given year. This area may
be designated as Zone A, AE, AH, AO, A1-A30, A99, V, VO, VE, or V1-V30.
It is also commonly referred to as the base floodplain or 100-year
floodplain. For purposes of this chapter, the term "special flood
hazard area (SFHA)" is synonymous in meaning with the phrase "area
of special flood hazard."
BASE FLOOD
The flood having a 1% chance of being equaled or exceeded
in any given year.
BASEMENT
That portion of a building having its floor subgrade (below
ground level) on all sides.
CELLAR
Has the same meaning as "basement."
CRAWLSPACE
An enclosed area beneath the lowest elevated floor, 18 inches
or more in height, which is used to service the underside of the lowest
elevated floor. The elevation of the floor of this enclosed area,
which may be of soil, gravel, concrete or other material, must be
equal to or above the lowest adjacent exterior grade. The enclosed
crawl space area shall be properly vented to allow for the equalization
of hydrostatic forces which would be experienced during periods of
flooding.
DEVELOPMENT
Any man-made change to improved or unimproved real estate,
including but not limited to buildings or other structures, mining,
dredging, filling, paving, excavation or drilling operations or storage
of equipment or materials.
ELEVATED BUILDING
A nonbasement building built, in the case of a building in
Zones A1-A30, AE, A, A99, AO, AH, B, C, X, or D, to have the top of
the elevated floor, or in the case of a building in Zones V1-30, VE,
or V, to have the bottom of the lowest horizontal structure member
of the elevated floor, elevated above the ground level by means of
pilings, columns (posts and piers), or shear walls parallel to the
flow of the water and adequately anchored so as not to impair the
structural integrity of the building during a flood of up to the magnitude
of the base flood. In the case of Zones A1-A30, AE, A, A99, AO, AH,
B, C, X, or D, "elevated building" also includes a building elevated
by means of fill or solid foundation perimeter walls with openings
sufficient to facilitate the unimpeded movement of floodwaters. In
the case of Zones V1-V30, VE, or V, "elevated building" also includes
a building otherwise meeting the definition of "elevated building,"
even though the lower area is enclosed by means of breakaway walls
that meet the federal standards.
FLOOD BOUNDARY AND FLOODWAY MAP (FBFM)
An official map of the community published by the Federal
Emergency Management Agency as part of a riverine community's
Flood Insurance Study. The FBFM delineates a regulatory floodway along
water courses studied in detail in the Flood Insurance Study.
FLOOD ELEVATION STUDY
An examination, evaluation and determination of the flood
hazards and, if appropriate, corresponding water surface elevations,
or an examination, evaluation and determination of flood-related erosion
hazards.
FLOOD HAZARD BOUNDARY MAP (FHBM)
An official map of a community, issued by the Federal Emergency
Management Agency, where the boundaries of the areas of special flood
hazard have been designated as Zone A but no flood elevations are
provided.
FLOOD INSURANCE RATE MAP (FIRM)
An official map of a community, on which the Federal Emergency
Management Agency has delineated both the areas of special flood hazard
and the risk premium zones applicable to the community.
FLOOD or FLOODING
A.
A general and temporary condition of partial or complete inundation
of normally dry land areas from:
(1)
The overflow of inland or tidal waters;
(2)
The unusual and rapid accumulation or runoff of surface waters
from any source.
B.
"Flood" or "flooding" also means the collapse or subsidence of land along the shore of a lake or other body of water as a result of erosion or undermining caused by waves or currents of water exceeding anticipated cyclical levels or suddenly caused by an unusually high water level in a natural body of water, accompanied by a severe storm, or by an unanticipated force of nature, such as a flash flood or an abnormal tidal surge, or by some similarly unusual and unforeseeable event which results in flooding as defined in Subsection
A(1) above.
FLOODPROOFING
Any combination of structural and nonstructural additions,
changes, or adjustments to structures which reduce or eliminate flood
damage to real estate or improved real property, water and sanitary
facilities, structures and their contents.
FLOODWAY
Has the same meaning as "regulatory floodway."
FUNCTIONALLY DEPENDENT USE
A use which cannot perform its intended purpose unless it
is located or carried out in close proximity to water, such as a docking
or port facility necessary for the loading and unloading of cargo
or passengers, shipbuilding, and ship repair facilities. The term
does not include long-term storage, manufacturing, sales, or service
facilities.
HIGHEST ADJACENT GRADE
The highest natural elevation of the ground surface, prior
to construction, next to the proposed walls of a structure.
HISTORIC STRUCTURE
Any structure that is:
A.
Listed individually in the National Register of Historic Places
(a listing maintained by the Department of the Interior) or preliminarily
determined by the Secretary of the Interior as meeting the requirements
for individual listing on the National Register;
B.
Certified or preliminarily determined by the Secretary of the
Interior as contributing to the historical significance of a registered
historic district or a district preliminarily determined by the Secretary
to qualify as a registered historic district;
C.
Individually listed on a state inventory of historic places
in states with historic preservation programs which have been approved
by the Secretary of the Interior; or
D.
Individually listed on a local inventory of historic places
in communities with historic preservation programs that have been
certified either:
(1)
By an approved state program as determined by the Secretary
of the Interior; or
(2)
Directly by the Secretary of the Interior in states without
approved programs.
LOCAL ADMINISTRATOR
The person appointed by the community to administer and implement
this chapter by granting or denying development permits in accordance
with its provisions. This person is often the Building Inspector,
Code Enforcement Officer, or employee of an engineering department.
LOWEST FLOOR
Lowest floor of the lowest enclosed area (including basement
or cellar). An unfinished or flood-resistant enclosure, usable solely
for parking of vehicles, building access, or storage in an area other
than a basement area is not considered a building's lowest floor,
provided that such enclosure is not built so as to render the structure
in violation of the applicable nonelevation design requirements of
this chapter.
MANUFACTURED HOME
A structure, transportable in one or more sections, which
is built on a permanent chassis and designed to be used with or without
a permanent foundation when connected to the required utilities. The
term does not include a "recreational vehicle."
MEAN SEA LEVEL
For purposes of the National Flood Insurance Program, the
National Geodetic Vertical Datum (NGVD) of 1929, the North American
Vertical Datum of 1988 (NAVD 88), or other datum, to which base flood
elevations shown on a community's Flood Insurance Rate Map are
referenced.
MOBILE HOME
Has the same meaning as "manufactured home."
NEW CONSTRUCTION
Structures for which the "start of construction" commenced
on or after the effective date of a floodplain management regulation
adopted by the community and includes any subsequent improvements
to such structure.
PRINCIPALLY ABOVEGROUND
That at least 51% of the actual cash value of the structure,
excluding land value, is aboveground.
RECREATIONAL VEHICLE
A vehicle which is:
A.
Built on a single chassis;
B.
Four hundred square feet or less when measured at the largest
horizontal projections;
C.
Designed to be self-propelled or permanently towable by a light-duty
truck; and
D.
Not designed primarily for use as a permanent dwelling but as
temporary living quarters for recreational, camping, travel, or seasonal
use.
REGULATORY FLOODWAY
The channel of a river or other watercourse and the adjacent land areas that must be reserved in order to discharge the base flood without cumulatively increasing the water surface elevation more than a designated height as determined by the Federal Emergency Management Agency in a Flood Insurance Study or by other agencies as provided in §
103-15B of this chapter.
START OF CONSTRUCTION
A.
The date of permit issuance for new construction and substantial
improvements to existing structures, provided that actual start of
construction, repair, reconstruction, rehabilitation, addition placement,
or other improvement is within 180 days after the date of issuance.
The actual start of construction means the first placement of permanent
construction of a building (including a manufactured home) on a site,
such as the pouring of a slab or footings, installation of pilings
or construction of columns.
B.
Permanent construction does not include land preparation (such
as clearing, excavation, grading, or filling), or the installation
of streets or walkways, or excavation for a basement, footings, piers
or foundations, or the erection of temporary forms, or the installation
of accessory buildings such as garages or sheds not occupied as dwelling
units or not part of the main building. For a substantial improvement,
the actual "start of construction" means the first alteration of any
wall, ceiling, floor, or other structural part of a building, whether
or not that alteration affects the external dimensions of the building.
STRUCTURE
A walled and roofed building, including a gas or liquid storage
tank that is principally aboveground, as well as a manufactured home.
SUBSTANTIAL DAMAGE
Damage of any origin sustained by a structure whereby the
cost of restoring the structure to its before damaged condition would
equal or exceed 50% of the market value of the structure before the
damage occurred.
SUBSTANTIAL IMPROVEMENT
A.
Any reconstruction, rehabilitation, addition, or other improvement
of a structure, the cost of which equals or exceeds 50% of the market
value of the structure before the "start of construction" of the improvement.
The term includes structures which have incurred "substantial damage,"
regardless of the actual repair work performed. The term does not,
however, include either:
(1)
Any project for improvement of a structure to correct existing
violations of state or local health, sanitary, or safety code specifications
which have been identified by the local code enforcement official
and which are the minimum necessary to assure safe living conditions;
or
(2)
Any alteration of an "historic structure," provided that the
alteration will not preclude the structure's continued designation
as an "historic structure."
VARIANCE
A grant of relief from the requirements of this chapter which
permits construction or use in a manner that would otherwise be prohibited
by this chapter.
VIOLATION
The failure of a structure or other development to be fully
compliant with the community's floodplain management regulations.
This chapter shall apply to all areas of special flood hazard
within the jurisdiction of the Town of Wales.
The invalidity of any section or provision of this chapter shall
not invalidate any other section or provision thereof.
No structure in an area of special flood hazard shall hereafter be constructed, located, extended, converted, or altered and no land shall be excavated or filled without full compliance with the terms of this chapter and any other applicable regulations. Any infraction of the provisions of this chapter by failure to comply with any of its requirements, including infractions of conditions and safeguards established in connection with conditions of the permit, shall constitute a violation. Any person who violates this chapter or fails to comply with any of its requirements shall, upon conviction thereof, be fined no more than $250 or imprisoned for not more than 15 days or both. Each day of noncompliance shall be considered a separate offense. Nothing herein contained shall prevent the Town of Wales from taking such other lawful action as necessary to prevent or remedy an infraction. Any structure found not compliant with the requirements of this chapter for which the developer and/or owner has not applied for and received an approved variance under §§
103-19 and
103-20 will be declared noncompliant and notification sent to the Federal Emergency Management Agency.
The degree of flood protection required by this chapter is considered
reasonable for regulatory purposes and is based on scientific and
engineering considerations. Larger floods can and will occur on rare
occasions. Flood heights may be increased by man-made or natural causes.
This chapter does not imply that land outside the area of special
flood hazards or uses permitted within such areas will be free from
flooding or flood damages. This chapter shall not create liability
on the part of the Town of Wales, any officer or employee thereof,
or the Federal Emergency Management Agency, for any flood damages
that result from reliance on this chapter or any administrative decision
lawfully made there under.
The Code Enforcement Officer is hereby appointed Local Administrator
to administer and implement this chapter by granting or denying floodplain
development permits in accordance with its provisions.
A floodplain development permit is hereby established for all construction and other development to be undertaken in areas of special flood hazard in this community for the purpose of protecting its citizens from increased flood hazards and insuring that new development is constructed in a manner that minimizes its exposure to flooding. It shall be unlawful to undertake any development in an area of special flood hazard, as shown on the Flood Insurance Rate Map enumerated in §
103-6, without a valid floodplain development permit. Application for a permit shall be made on forms furnished by the Local Administrator and may include, but not be limited to: plans, in duplicate, drawn to scale and showing: the nature, location, dimensions, and elevations of the area in question; existing or proposed structures, fill, storage of materials, drainage facilities, and the location of the foregoing.
All applications for a floodplain development permit shall be
accompanied by an application fee as established by Town Board resolution
from time-to-time. In addition, the applicant shall be responsible
for reimbursing the Town of Wales for any additional costs necessary
for review, inspection and approval of this project. The Local Administrator
may require a deposit of no more than $500 to cover these additional
costs.
The following standards apply to new development, including new and substantially improved structures, in the areas of special flood hazard shown on the Flood Insurance Rate Map designated in §
103-6.
A. Subdivision proposals. The following standards apply to all new subdivision
proposals and other proposed development in areas of special flood
hazard (including proposals for manufactured home and recreational
vehicle parks and subdivisions):
(1) Proposals shall be consistent with the need to minimize flood damage;
(2) Public utilities and facilities such as sewer, gas, electrical and
water systems shall be located and constructed to minimize flood damage;
and
(3) Adequate drainage shall be provided to reduce exposure to flood damage.
B. Encroachments.
(1) Within Zones A1-A30 and AE, on streams without a regulatory floodway,
no new construction, substantial improvements or other development
(including fill) shall be permitted, unless:
(a)
The applicant demonstrates that the cumulative effect of the
proposed development, when combined with all other existing and anticipated
development, will not increase the water surface elevation of the
base flood more than one foot at any location; or
(b)
The Town of Wales agrees to apply to the Federal Emergency Management
Agency (FEMA) for a conditional FIRM revision, FEMA approval is received
and the applicant provides all necessary data, analyses and mapping
and reimburses the Town of Wales for all fees and other costs in relation
to the application. The applicant must also provide all data, analyses
and mapping and reimburses the Town of Wales for all costs related
to the final map revision.
(2) On streams with a regulatory floodway, as shown on the Flood Boundary and Floodway Map or the Flood Insurance Rate Map adopted in §
103-6, no new construction, substantial improvements or other development in the floodway (including fill) shall be permitted, unless:
(a)
A technical evaluation by a licensed professional engineer demonstrates
through hydrologic and hydraulic analyses performed in accordance
with standard engineering practice that such an encroachment shall
not result in any increase in flood levels during occurrence of the
base flood; or
(b)
The Town of Wales agrees to apply to the Federal Emergency Management
Agency (FEMA) for a conditional FIRM and floodway revision, FEMA approval
is received, and the applicant provides all necessary data, analyses
and mapping and reimburses the Town of Wales for all fees and other
costs in relation to the application. The applicant must also provide
all data, analyses and mapping and reimburse the Town of Wales for
all costs related to the final map revisions.
(3) In Zones A1-A30, AE and AH, and also Zone A if base flood elevation
data are available, if any development is found to increase or decrease
base flood elevations, the Town of Wales shall as soon as practicable,
but not later than six months after the date such information becomes
available, notify FEMA and the New York State Department of Environmental
Conservation of the changes by submitting technical or scientific
data in accordance with standard engineering practice.
The following standards apply to new development, including new and substantially improved structures, in the areas of special flood hazard shown on the Flood Insurance Rate Map designated in §
103-6.
A. Anchoring. New structures and substantial improvement to structures
in areas of special flood hazard shall be anchored to prevent flotation,
collapse, or lateral movement during the base flood. This requirement
is in addition to applicable state and local anchoring requirements
for resisting wind forces.
B. Construction materials and methods.
(1) New construction and substantial improvements to structures shall
be constructed with materials and utility equipment resistant to flood
damage.
(2) New construction and substantial improvements to structures shall
be constructed using methods and practices that minimize flood damage.
(3) For enclosed areas below the lowest floor of a structure within Zones
A1-A30, AE, AO or A, new and substantially improved structures shall
have fully enclosed areas below the lowest floor that are useable
solely for parking of vehicles, building access or storage in an area
other than a basement and which are subject to flooding, designed
to automatically equalize hydrostatic flood forces on exterior walls
by allowing for the entry and exit of floodwaters.
(a)
Designs for meeting this requirement must either be certified
by a licensed professional engineer or architect or meet or exceed
the following minimum criteria:
[1]
A minimum of two openings of each enclosed area having a total
net area of not less than one square inch for every square foot of
enclosed area subject to flooding;
[2]
The bottom of all such openings no higher than one foot above
the lowest adjacent finished grade; and
[3]
Openings not less than three inches in any direction.
(b)
Openings may be equipped with louvers, valves, screens or other
coverings or devices provided they permit the automatic entry and
exit of floodwaters. Enclosed areas subgrade on all sides are considered
basements and are not permitted.
C. Utilities.
(1) New and replacement electrical equipment, heating, ventilating, air
conditioning, plumbing connections, and other service equipment shall
be located at least two feet above the base flood elevation, or at
least three feet above the highest adjacent grade in a Zone A without
an available base flood elevation, or be designed to prevent water
from entering and accumulating within the components during a flood
and to resist hydrostatic and hydrodynamic loads and stresses. Electrical
wiring and outlets, switches, junction boxes and panels shall be elevated
or designed to prevent water from entering and accumulating within
the components unless they conform to the appropriate provisions of
the electrical part of the Building Code of New York State or the
Residential Code of New York State for location of such items in wet
locations;
(2) New and replacement water supply systems shall be designed to minimize
or eliminate infiltration of floodwaters into the system;
(3) New and replacement sanitary sewage systems shall be designed to
minimize or eliminate infiltration of floodwaters. Sanitary sewer
and storm drainage systems for buildings that have openings below
the base flood elevation shall be provided with automatic backflow
valves or other automatic backflow devices that are installed in each
discharge line passing through a building's exterior wall; and
(4) On-site waste disposal systems shall be located to avoid impairment
to them or contamination from them during flooding.
D. Storage tanks.
(1) Underground tanks shall be anchored to prevent flotation, collapse
and lateral movement during conditions of the base flood.
(2) Aboveground tanks shall be:
(a)
Anchored to prevent flotation, collapse or lateral movement
during conditions of the base flood; or
(b)
Installed at or above the base flood elevation as shown on the Flood Insurance Rate Map enumerated in §