Alterations, Repairs, Remodels, and Add-Ons:
| |
---|---|
Residential
| |
Building permit
|
$600.00 + $1.00 sq. foot
|
Commercial
| |
Building permit
|
Commercial step rate
|
Fire code review (if applicable)
|
$80.00
|
Final certificate of occupancy
|
$100.00
|
Mixed Use
| |
Finish out mixed use - residential
|
$1.00 per sq. foot
|
Finish out mixed use - commercial
|
Commercial step rate
|
Other Charges
| |
Curb cut - established driveway
|
$100.00 residential
$200.00 commercial
|
Accessory building
|
$150.00 residential or commercial
|
Culvert permit
|
$100.00 residential
$150.00 commercial
|
Deck > 30" above grade
|
$100.00
|
Demolition - entire building
|
$100.00
|
Demolition - interior
|
$50.00
|
Demolition - pool
|
$100.00
|
Fence
|
$80.00 residential
$160.00 commercial
|
Foundation repair
|
$150.00
|
Gas test
|
$100.00 residential
$200.00 commercial
|
Retaining wall > 48" tall
|
$100.00
|
Siding
|
$100.00
|
Licenses, Registrations, and Trades
| |
---|---|
Registration for unlicensed contractors
|
$100.00 residential
$100.00 commercial
|
Electrical, gas, mechanical, plumbing permit
|
$100.00 residential
$100.00 commercial
|
Solicitor's registration
|
$25.00
|
Solicitor's identification badge
|
$2.50
|
Food truck permit fee (annual)
|
$85.00
|
Food truck health permit fee (annual health inspection)
|
$130.00
|
Food truck reinspection fee
|
$50.00
|
Other Charges
| |
---|---|
Demolition permit
|
$200.00
|
Carport/canopy/patio cover
|
$100.00
|
Construction trailer
|
$100.00
|
Commercial flat work (parking lot)
|
$200.00
|
Concrete patio/sidewalks
|
$100.00
|
Residential flat work (patio side walls)
|
$100.00
|
Garage sale
|
Free
|
Miscellaneous
|
$100.00
|
Move in - manufactured home
|
$1,100.00 + truck fee plus direct [expenses of professional
consultants for review of application and submitted materials]
|
Move in - truck
|
$100.00 per truck
|
Roof
|
$100.00 residential
$200.00 commercial
|
Sales trailer
|
$100.00
|
Screening wall
|
$100.00
|
Sign - banner
|
$75.00
|
Sign - permanent
|
$150.00
|
Solar panels
|
$250.00
|
Water heater
|
$150.00
|
Window replacement
|
$75.00
|
Excavation permit
|
2% of $2,500.00–$100,000.00 1% of $100,001.00
$200,000.00 1/2% of $200,000.00
|
Plan review
|
50% of new construction permit fee
|
Food service establishments (temp)
|
$50.00 per event + $10.00 booth operation
|
HVAC
|
$50.00 residential
$100.00 commercial
|
Irrigation
|
$100.00 residential
$150.00 commercial
|
Reinspection fee
|
$100.00 residential
$200.00 commercial
|
Special event permit
|
$25.00
|
Park pavilion deposit - refundable
|
$100.00
|
Park pavilion rental for nonresident (nonrefundable)
|
$45.00 for 3-hours and $5.00 for each additional hour
|
Park pavilion rental for city residents (nonrefundable)
|
$32.00 for 3-hours and $5.00 for each additional hour
|
Farmers market vendor permit (nonrefundable)
|
$50.00
|
Utility - electric release
|
Free
|
Utility - water release
|
Free
|
Utility and pipeline fees (professional fees will be billed)
|
$200.00 plus professional fees
|
New Commercial Buildings - Step Rates
| |
---|---|
Total Valuation
|
Permit Fee
|
$1.00 to $5,000.00
|
$110.00
|
$5,001.00 to $10,000.00
|
$130.00
|
$10,001.00 to $25,000.00
|
$130.00 for 1st $10,000.00 + $14.00 per each additional $1,000.00
|
$25,001.00 to $50,000.00
|
$303.00 for 1st $25,000.00 + $12.12 per each additional $1,000.00
|
$50,001.00 to $100,000.00
|
$421.25 for 1st $50,000.00 + $10.10 per each additional $1,000.00
|
$100,001.00 to $500,000.00
|
$1,023.75 for 1st $100,000.00 + $5.60 per each additional $1,000.00
|
$500,001.00 to $1,000,000.00
|
$3,263.75 for 1st $500,000.00 + $4.75 per each additional $1,000.00
|
$1,000,001.00 and up
|
$5,638.75 for 1st $1,000,000 + $3.15 per each additional $1,000.00
|
Fire Permit Description
|
Fee
|
---|---|
Access control
|
$50.00
|
Alarm system
|
$100.00 per floor + $2.00 per device
|
Christmas tree lot
|
$50.00
|
Explosives and blasting
|
$50.00
|
Fixed extinguishing system
|
$75.00 per system
|
Flammable/combustible liquid/tanks
|
$50.00
|
Fumigation/thermal insect fog
|
$50.00
|
Hydrant flow test
|
$50.00
|
Liquid petroleum gases
|
$25.00
|
Mechanical trench burn
|
$200.00 per day
|
Places of assembly
|
$50.00
|
Sprinkler system - new
|
$125.00 per riser/system + $0.012 per sf
|
Sprinkler system - remodel - between 0–40 heads
|
$50.00
|
Sprinkler system - remodel - 41 or more heads
|
$100.00
|
Standpipe system
|
$100.00 per system
|
Tents/canopies/air supported
|
$50.00
|
Underground sprinkler system
|
$50.00
|
Annexations
|
$500.00 plus direct expenses of professional consultants for
review of application and submitted material
|
Concept plan
|
$500.00
|
Final plat - commercial
|
$400.00 plus $50.00 per acre plus direct expenses of professional
consultants for review of application and submitted material
|
Final plat - residential
|
$400.00 plus $10.00 per lot for the first 10 lots and $7.00
per each additional lot plus $20.00 per acre for acres not platted
into lots plus direct expenses of professional consultants for review
of application and submitted material
|
Planned development
|
$1,000.00 per PD plus direct expenses of professional consultants
for review of application and submitted material
|
Plat abandonment
|
$200.00
|
Plat revision
|
$300.00 plus direct expenses of professional consultants for
review of application and submitted material
|
Plat revision notice
|
$20.00 per notice
|
Preliminary plat - commercial
|
$700.00 plus $50.00 per acre plus direct expenses of professional
consultants for review of application and submitted material
|
Preliminary plat - residential
|
$700.00 plus $20.00 per lot for the first 10 lots and $7.00
per each additional lot plus $25.00 per acre for areas not platted
into lots plus direct expenses of professional consultants for review
of application and submitted material
|
Replat
|
$100.00 plus $2.00 per lot plus direct expenses of professional
consultants for review of application and submitted material
|
Refunding of fees
|
The city secretary may refund moneys collected as fees, if the
application is withdrawn and no expenses have been incurred by the
city on the applicant's behalf. Written request is required within
ten (10) days by the applicant for the city secretary to refund any
inadvertent overcharges.
|
Resubmitted final plat
|
$50.00 plus direct expenses of professional consultants for
review of application and submitted material
|
Resubmitted preliminary plat
|
$50.00 plus direct expenses of professional consultants for
review of application and submitted material
|
Specific use permit
|
$400.00 plus direct expenses of [sic]
|
Variance
|
$400.00 per variance plus $50.00 for each additional variance
request within the same application plus direct expenses of professional
consultants for review of application and submitted material.
|
Zoning change
|
$400.00 plus direct expenses of professional consultants for
review of application and submitted material
|
New Single-Family Residential
| |
Building permit
|
$700.00 + $0.50/sq. foot
|
Plan review
|
50% of the new construction permit
|
Fire code review (if applicable)
|
$100.00
|
New Multifamily Residential
| |
Building permit
|
Commercial step rate
|
Plan review
|
65% of building permit
|
Fire code review (if applicable)
|
20% of building permit
|
New Commercial
| |
Building permit
|
Commercial step rate
|
Plan review
|
65% of building permit
|
Fire code review (if applicable)
|
20% of building permit
|
Other New Construction Fees
| |
Final Certificate of Occupancy (Not applicable to Manufactured
Homes)
|
$100.00 residential and commercial
|
Driveway with Curb Cut
|
$100.00 residential/$200.00 commercial
|
Culvert permit
|
$100.00 residential/$200.00 commercial
|
Sign permit (monument)
|
$100.00
|
Irrigation
|
$100.00 residential/$150.00 commercial
|
Fence
|
$80.00 residential/$160.00 commercial
|
Accessory building
|
Air-conditioned space $0.75 square foot
Non air-conditioned space $0.50 square foot
Building not on slab $0.23 square foot
|
New construction shell - mixed use building
|
Commercial step rate
|
Shell building
|
Commercial step rate
|
Grading permit
|
$100.00 residential/$300.00 commercial
|
Storm/tornado shelter prefab and built on-site
|
$400.00 for prefab/$450.00 for built onsite
|
Reinspections after second red-tag
|
$100.00
|
Work without permit
|
Double the permit fee for anyone caught working without a permit.
|