(a) 
Applicable utility related fees including community impact, tap and deposit fees shall be paid prior to issuance of a building permit. Refer to Article 8.000 herein for fee information.
(b) 
Building application review fees shall be paid at time of application submittal. Building inspection fees shall be paid at time of issuance of permit.
(c) 
Land use, subdivision and site improvement fees shall be paid at time of application submittal. Subdivision construction inspection fees shall be paid prior to final inspection of the improvements.
(d) 
Third-party plan review fees shall be paid prior to approval of an application or issuance of a permit. Any unpaid or uncollected fees required herein, including any third-party inspection fees, shall be paid prior to city issuance of any final inspections or certificates of occupancy or acceptance of any subdivision improvements by the city.
(e) 
All costs incurred by the city in lawfully abating or authorizing abatement of conditions that are a hazard to public safety, health or welfare for properties requesting permits or approvals for development shall be paid prior to issuance of building permits or approval of applications for land use, subdivision platting or site improvements.
(f) 
Unless otherwise provided for in this Code of Ordinances, fees shall be collected in the amounts provided for in the schedule contained in this section. Any reference to fees contained in any code adopted by reference in this code or contained in any chapter of this code shall be superseded by the following fee schedule. All fees provided for in this section shall be nonrefundable.
(Ordinance CO08-03-03-27-13A adopted 3/27/03; Ordinance CO07.23.12.21.E1 adopted 12/21/2023)
Residential Building Fees
New single-family and townhomes
New construction
$0.10 per sq. ft. for total foundation/floor area including porches and patios, minimum $25
Building plan review
$50
Plumbing permit
$0.10 per sq. ft. for total foundation/floor area including porches and patios, minimum $25
Electrical permit
$0.10 per sq. ft. for total foundation/floor area including porches and patios, minimum $25
Mechanical permit
$100 per living unit plus $25 per floor above 1st floor
New Manufactured Home
Building permit
$0.10 per sq ft, minimum $25
Building plan review
$50
Plumbing tie in
$25
Electrical tie in
$25
Mechanical tie in
$25
Residential Remodel
Remodel permit
$50
Remodel plan review
$100
Plumbing permit
$100
Electrical permit
$100
Mechanical permit
$100
Miscellaneous Residential Fees
Penalty
$100 per day of occupancy prior to obtaining building final
Temporary meter loops/electrical service upgrade
$25 for up to 100 amp, $40 for over 100 amp
Water, gas, sewer line not in plumbing permit
$25
Commercial Building Fees
New Commercial Building
New construction
$0.10 per sq ft for total foundation/floor area, min. $35
3rd party plan review service
Paid directly to 3rd party service (not to exceed ICC plan review fees plus $100 base fee)
In-house building plan review
Valuation* < $3,000,000 = Valuation X .0011
Valuation* $3,000,000 — $6,000,000 = $3,300 for 1st $3,000,000 valuation plus amount in excess of $3,000,000 X .0005
Valuation* #eg $6,000,001 = $4,800 for 1st $6,000,001 valuation plus amount in excess of $6,000,001 X .0035
In-house mechanical review
25% of building review fee
In-house electrical review
25% of building review fee
In-house plumbing review
25% of building review fee
In-house energy conservation review
25% of building review fee
Plumbing permit
$0.10 per sq ft for total foundation/floor area, min. $35
Electrical permit
$0.15 per sq ft
Mechanical permit
$100 for 1st 2,500 sq ft
$75 for each additional 2,500 sq ft
*Valuation to be calculated using the most current ICC Building Valuation Table as published on www.iccsafe.org
Lease Space Finish-Out
Building permit
$0.10 per sq ft for total foundation/floor area, min. $35
Building plan review
$50
Plumbing permit
$0.05 per sq ft for total foundation/floor area, min. $35
Electrical permit
$0.05 per sq ft for total foundation/floor area, min. $35
Shell Building
Building permit
$0.10 per sq ft for total foundation/floor area, min. $35
In-house shell building review
60% of total plan review fee
Plumbing permit
$0.05 per linear ft (excluding fire sprinkler system lines)
Electrical permit
$0.10 per sq ft for total foundation/floor area, min. $35
Foundation Only
Building permit
$100 for up to 2,500 sq ft, plus $0.04 per sq ft for over 2,500 sq ft
Plumbing permit
$100 for up to 2,500 sq ft, plus $0.04 per sq ft for over 2,500 sq ft
Electrical permit
$100 for up to 2,500 sq ft, plus $0.04 per sq ft for over 2,500 sq ft
Remodel
Building permit
$100
Building plan review
$50
Plumbing permit
$100
Electrical permit
$100
Mechanical permit
$100
Miscellaneous Commercial Fees
Certificate of occupancy
$50
Coolers/freezers
$25
Industrial pre-treatment plan review
$25
Outside utility lines (water, fire line and sewer)
$0.10 per linear ft for all lines
Penalty
$100 per day of occupancy prior to obtaining building final
Professional recovery fee
$200
Resubmittal Review Fee (4th resubmittal and above)
$100 per resubmittal
Temporary certificate of occupancy extension
$250 per request
Temporary meter loops/electrical service upgrade
$50 for up to 200 amp, $100 for over 200 amp
Water, gas, sewer line not in plumbing permit
$35
Sign Permits
New and temporary
$2.00 per sq ft, $50 minimum
Advertising search light
$100
Miscellaneous Building Permit Fees
Irrigation Systems
Residential
$25
Commercial
$50 plus $25 per each additional backflow preventer
Temporary Construction Trailer Permit
Building permit
$0.10 per sq ft, minimum $35
Electrical permit
$25
Plumbing permit
$25
Mechanical permit
$25
Temporary Structures/Other Membrane Structure Permit
Building permit
$50
Plan review
$35
Swimming Pool - Above Ground
Building permit
$50
Plumbing (if gas heated)
$50
Electrical
$50
Plan review
$25
Swimming Pool - In-Ground
Building permit
$100
Plumbing (if gas heated)
$100
Electrical
$100
Plan review
$50
Accessory Structures
Permit fee
$0.10 per sq ft, minimum $35
Plan review
$25
Administrative Change
$25
Demolition Permit
$50
Flatwork Permit (driveways, sidewalks, ADA ramps (excludes single family
$35
HVAC Changeout/Addition
$50
Moving Permit
$50
Reinspection Fee
$75
Special Event Permit
$100
Temporary Meter Loops/Electrical Service Upgrade
$50
Water Heater Install/Changeout
$50
Water Softener Installation
$50
Water, Gas, Sewer Line Not in Plumbing Permit
$25
(Ordinance CO08-03-03-27-13A adopted 3/27/03; Ordinance CO09-06-02-09-3D adopted 2/9/06; Ordinance CO15-13-01-10-C5 adopted 1/10/13; Ordinance CO20-15-12-17-C2 adopted 12/17/15; Ordinance CO07.23.12.21.E1 adopted 12/21/2023)
Annexation (Voluntary)
Application review
$400.00
Pre-annexation development agreement
$1,500.00
Board of Adjustment
Application review
$500.00
Easement Vacation/Encroachment
Application review
$50.00
Floodplain Development Permit
Construction within flood hazard areas
$500.00
LOMR/CLOMR review
$500.00
Network Nodes, Node Support Poles, and Transport Facilities in Public Right-of-Way
Network node application fee
$500.00 up to five network nodes, with an additional $100.00 for each network node beyond five
New node support pole application fee
$1,000.00
Annual fee
$270.00 per network node per year for all recurring fees, including any possible ROW access fee or fee for attachment to municipally-owned structures in the ROW
NPS Pollution Control Permit
Type 1 permit
$250.00 plus $25.00/acre up to 100 acres; $5.00/acre over 100
Master plan review
$25.00/acre up to 100; $5.00/acre over 100
Right-of-Way Use Permit
Application review
$100.00
Rough-Cut/Grading Permit
Application review
$100.00
Site Development Permit
Plan Review Fees
(A) Imp. cover up to 50,000 sf
$0.04 per sf
(B) Imp cover 50,000 — 100,000 sf
$0.02/sf +(A)
(C) Imp cover 100,000 — 200,000 sf
$0.01/sf + (A) + (B)
(D) Imp cover over 200,000 sf
$0.002/sf + (A) + (B) + (C)
Site development permit revision
50% of original application fee
Inspection Fees
(A)Imp. cover up to 50,000 sf
$125.00
(B)Imp cover 50,000 — 100,000 sf
$150.00
(C)Imp cover 100,000 — 200,000 sf
$250.00
(D)Imp cover over 200,000 sf
$500.00
Miscellaneous Site Development Review Fees
Industrial pre-treatment review
$25.00
Please refer to article 4.000, fire protection related fees, for additional applicable fees
Street Name Change
Application review
$250.00
Subdivision Review
Preliminary Plan
Public works and engineering review fee
$750.00 plus $10.00 per acre or lot, whichever is greater
Planning review fee
$500.00 + $48 per lot or acre, whichever is greater
Preliminary plan revision review fee
50% of original application fee
Final Plat/Development Plat
Public works and engineering review fee
$500.00 plus $5.00 per acre or lot, whichever is greater
Planning review fee
$700 + $8 per lot or acre, whichever is greater.
Resubdivision (Replat)
Public works and engineering review fee
Same as new subdivision
Planning review fee
Same as new subdivision
Short Form Final Plat (Amending Plat)
Public works and engineering review fee
$50.00
Planning review fee
$500.00
Subdivision improvements
Subdivision construction plan review
$2500.00 plus $10.00 per acre or lot, whichever is greater
Subdivision construction inspection fee
(1) The hourly rate for the estimated actual direct time of the City's employees performing the subdivision construction inspections; or
(2) The actual costs assessed to the City by a third-party entity that provides subdivision construction inspections to the City.
Miscellaneous Subdivision Review Fees
GIS digitizing fee
$25.00
Subdivision vacation
$100.00
Subdivision variance
$100.00 per variance
Subdivision approval extension
$300.00
Legal lot determination
$100.00
Please refer to article 4.000, fire protection related Fees, for additional applicable fees
Traffic Impact Analysis (TIA)
2,000 — 5,000 trips per day
$1,500.00
5,001 — 10,000 trips per day
$2,400.00
10,001  —  15,000 trips per day
$3,300.00
15,001 plus trips per day
$3,700.00
TIA revision
50% of original application fee
Zoning Map Amendment (Original or Rezoning)
Base and Overlay Districts/Special Use Permit
Up to 3 acres
$300.00
Above 3 acres
$300.00 for the first 3 acres, $25.00 per acre thereafter, maximum $2,000
Planned Unit Development
New
$2,000.00, plus $75.00 per acre, maximum $10,000
Amendment
50% of original application fee
Postponement Request
Legal Notification Fee
Zoning Verification Letter
Application review
$50.00
Miscellaneous Review and Inspection Fees
Professional recovery fee
$200.00
Resubmittal review fee (4th submittal and above)
$500.00 each resubmittal
Third-party plan review and/or inspections
The actual costs assessed to the City by a third-party entity that provides plan review and inspection services to the City. Applicable plan review and inspection fees paid with the initial submittal will be credited towards the total actual cost.
Certificate of completion inspection
1st inspection free, each reinspection $50 per dept
Drainage study review (not associated with a development permit)
$250.00 plus the professional recovery fee
(Ordinance CO08-03-03-27-13A adopted 3/27/03; Ordinance CO47-17-08-24-E1 adopted 8/24/17; Ordinance CO15-19-05-09-E1 adopted 5/9/19; Ordinance CO25.23.08.24.E1 adopted 8/24/2023; Ordinance CO07.23.12.21.E1 adopted 12/21/2023)
Miscellaneous Development Review and Inspection Fees
Appeal of a development services committee determination
$100.00
Copies
Computer print out
$0.40 per page
Photocopies
$0.55 for the first page, $0.15 for each additional page
Legal Notification Fees
Newspaper
$300.00
Mail notices
$2.00 per property owner/notice
Sign notice
$10.00 per sign per roadway < 45 mph, and $25.00 per sign per roadway > 45 mph, maximum 3 signs per roadway
(Ordinance CO08-03-03-27-13A adopted 3/27/03; Ordinance CO50-09-05-14-C4 adopted 5/14/09; Ordinance CO60-09-09-10-C1, sec. 1, adopted 9/10/09; Ordinance CO07.23.12.21.E1 adopted 12/21/2023)