(a)
No person or agency may install any utility or other encroachment, make a pavement cut or excavate in a public street, curb, easement, or alley without first obtaining a permit. Application for a permit shall be made no less than two city working days prior to the date of the proposed activity unless an emergency exists, in which case immediate notice must be given to the city. If the proposed cut or excavation is to be made in the public right-of-way dedicated to the state, a city permit is required in addition to any and all permits required by the state.
(b)
A permit does not relieve the applicant of the responsibility to coordinate with other utilities and to protect existing facilities.
(1993 Code, sec. 96.30; 2006 Code, sec. 66-61; Ordinance 342, sec. 2, adopted 11/2/92; Ordinance adopting 2015 Code)