Unless otherwise indicated on the Bid Form, the measurement and payment for the work specified in this Section shall be as follows:
Casing pipe installed by bore, including carrier pipe, and the construction of a bored hole for pipe without casing, including the pipe within the bored hole, shall be measured by the linear foot. Payment shall be made at the unit price bid for all labor, materials, equipment, etc. required for the completed casing with carrier pipe or carrier pipe installation by bore. Where installation of the casing pipe is allowed by open cut, payment shall be made at the unit price bid for casing installed by open cut, including the carrier pipe. When required at railroad crossings, no separate payment shall be made for any cathodic protection when required for the carrier pipe or casing.
(Ordinance 2007-106, App. B, adopted 3/20/07)