This section covers construction of a foundation course for a pavement surface course or other base courses. The base shall be composed of either caliche, crushed stone, gravel, iron ore topsoil, shell, etc., and shall be constructed in one or more courses to the lines and grades shown on the plans. All construction procedures and materials shall be in accordance with TxDOT Item 247.
(Ordinance 2007-106, App. B, adopted 3/20/07)
Unless specifically stated otherwise on the Bid Form, the accepted materials and work described in this Section will be measured by the square yard of the compacted in place flexible base to the thickness shown on the plans and/or listed on the Bid Form. The price bid for the work described in this Section shall be full compensation for furnishing all materials; for delivery on the road; for spreading, shaping, compacting, and finishing; and for all manipulations, labor, tools and incidentals necessary to complete the work.
(Ordinance 2007-106, App. B, adopted 3/20/07)
The applicable provisions of the following standards shall apply as if written here in their entirety:
TxDOT Texas Department of Transportation Standard Specifications for Construction of Highways, Streets and Bridges
(Ordinance 2007-106, App. B, adopted 3/20/07)
Submit certification from supplier or manufacturer that base material meets the requirements of this section.
(Ordinance 2007-106, App. B, adopted 3/20/07)
Provide samples of flexible base material delivered for incorporation into the project for testing by the Owner or its designated representative. Contractor shall pay for failed tests and the Owner shall pay for passing tests.
(Ordinance 2007-106, App. B, adopted 3/20/07)